Chestnut

Bashundhara R/A, Dhaka

Expected Completion Date

August 2025

Status Updated

December, 2024

SL. No Name of the work Location Progress details Remarks
01 Foundation work   100% completed.  
02 Super Structure work 7th Floor roof Slab & Beam Shuttering work is on progress.  
03 Block Work Apartment =A1

Apartment =A2

Apartment =A3

Apartment =A4

Apartment =A5

Apartment =A6

Apartment =A7

 

25% Complete

80% Complete

80% Complete

10% Complete

 

 

 
04 Electrical conduiting work      
05 Door frame fitting work      
06 Sanitary & plumbing line work      
07 In side Plastering work Apartment =A1

Apartment =A2

Apartment =A3

Apartment =A4

Apartment =A5

Apartment =A6

Apartment =A7

 

20% Complete

30% Complete

30% Complete

30% Complete

30% Complete

 

Only ceiling plaster work has done.
08 Electrical cable wiring work      
09 Wall tiles work    

 

 
10 Common sanitary & Plumbing line work      
11 Outside plastering work      
12 Floor tiles/Marble work    

 

 
13 L.C.C work    

 

 
14 Grill & Railing work      
15 Inside paint & Polishing work      
16 Switch -Socket fitting work    

 

 
17 Outside paint work      
18 Door shutter work    

 

 
19 Aluminum work      
20 Tiles Pointing work & Marble finishing work      
21 Commode – Basin fitting work and C.P fittings work      
22 Lift/Generator /Substation /Solar work      
23 Boundary wall /Ground floor development work      
24 Roof top finishing work      
25 Roof top Gardening work G.F Garden work      