Chestnut

Bashundhara R/A, Dhaka

Expected Completion Date

August 2025

Status Updated

November, 2024

SL. No Name of the work Progress details Remarks
01 Foundation work (Sub Structure) 100%

 

 
02 Super Structure work 6th  Floor Column work is on process  
03 Block Work Ground Floor=65%

1st Floor =15%

2nd Floor =65%

3rd Floor =55%

 
04 Electrical conduiting work    
05 Door frame fitting work    
06 Sanitary & plumbing line work    
07 In side Plastering work Ground Floor Ceiling Plaster=85%

1ST Floor Celling Plaster = 85%

2nd Floor Celling Plaster = 85%

3rd Floor Celling Plaster=75%

4th Floor Celling Plaster=65%

 
08 Electrical cable wiring work    
09 Wall tiles work    
10 Common sanitary & Plumbing line work    
11 Outside plastering work    
12 Floor tiles/Marble work    
13 L.C.C work    
14 Grill & Railing work    
15 Inside paint & Polishing work    
16 Switch -Socket fitting work    
17 Outside paint work    
18 Door shutter work    
19 Aluminum work    
20 Tiles Pointing work & Marble finishing work    
21 Commode – Basin fitting work and C.P fittings work    
22 Lift/Generator /Substation /Solar work    
23 Boundary wall /Ground floor development work    
24 Roof top finishing work    
25 Roof top Gardening work G.F Garden work    

 