Chestnut

Block K, Bashundhara R/A

Expected Completion Date

December 2025

Status Updated

October, 2025

SL. No Name of the work Location Progress details Remarks
01 Foundation work   100% completed.  
02 Super Structure work   100%  
03 Block Work Apartment =A1

Apartment =A2

Apartment =A3

Apartment =A4

Apartment =A5

Apartment =A6

Apartment =A7

 

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

 
04 Electrical conduiting work (Wall) Apartment =A1

Apartment =A2

Apartment =A3

Apartment =A4

Apartment =A5

Apartment =A6

Apartment =A7

 

100% Complete

100% Complete

95% Complete

100% Complete

100% Complete

100% Complete

100% Complete

 
05 Door frame fitting work Apartment =A1

Apartment =A2

Apartment =A3

Apartment =A4

Apartment =A5

Apartment =A6

Apartment =A7

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

 
06 Sanitary & plumbing line work Apartment =A1

Apartment =A2

Apartment =A3

Apartment =A4

Apartment =A5

Apartment =A6

Apartment =A7

85% Complete

85% Complete

85% Complete

85% Complete

85% Complete

85% Complete

85% Complete

 
07 In side Plastering work (Wall plaster work) Apartment =A1

Apartment =A2

Apartment =A3

Apartment =A4

Apartment =A5

Apartment =A6

Apartment =A7

 

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

 

 
08 Electrical cable wiring work Apartment =A1

Apartment =A2

Apartment =A3

Apartment =A4

Apartment =A5

Apartment =A6

Apartment =A7

 

60% Complete

90% Complete

80% Complete

90% Complete

100% Complete

100% Complete

90% Complete

 
09 Wall tiles work Apartment =A1

Apartment =A2

Apartment =A3

Apartment =A4

Apartment =A5

Apartment =A6

Apartment =A7

 

50% Complete

75% Complete

60% Complete

 

85% Complete

85% Complete

85% Complete

 
10 Common sanitary & Plumbing line work   60% Complete  
11 Outside plastering work Apartment =A1

Apartment =A2

Apartment =A3

Apartment =A4

Apartment =A5

Apartment =A6

Apartment =A7

 

90% Complete

95% Complete

95% Complete

95% Complete

95% Complete

95% Complete

95% Complete

 

 
12 Floor tiles/Marble work Apartment =A1

Apartment =A2

Apartment =A3

Apartment =A4

Apartment =A5

Apartment =A6

Apartment =A7

 

 

75% Complete

 

 

85% Complete

85% Complete

85% Complete

 

 
13 L.C.C work    

 

 
14 Grill & Railing work Apartment =A1

Apartment =A2

Apartment =A3

Apartment =A4

Apartment =A5

Apartment =A6

Apartment =A7

 

 

 

 

 

 

50% Complete

80% Complete

 
15 Inside paint & Polishing work Apartment =A1

Apartment =A2

Apartment =A3

Apartment =A4

Apartment =A5

Apartment =A6

Apartment =A7

 

   
16 Switch -Socket fitting work Apartment =A1

Apartment =A2

Apartment =A3

Apartment =A4

Apartment =A5

Apartment =A6

Apartment =A7

 

 

 

 
17 Outside paint work    5% Complete  
18 Door shutter work Apartment =A1

Apartment =A2

Apartment =A3

Apartment =A4

Apartment =A5

Apartment =A6

Apartment =A7

 

 

 

 
19 Aluminum work Apartment =A1

Apartment =A2

Apartment =A3

Apartment =A4

Apartment =A5

Apartment =A6

Apartment =A7

 

   
20 Tiles Pointing work & Marble finishing work Apartment =A1

Apartment =A2

Apartment =A3

Apartment =A4

Apartment =A5

Apartment =A6

Apartment =A7

 

   
21 Commode – Basin fitting work and C.P fittings work Apartment =A1

Apartment =A2

Apartment =A3

Apartment =A4

Apartment =A5

Apartment =A6

Apartment =A7

 

   
22 Lift/Generator /Substation /Solar work      
23 Boundary wall /Ground floor development work   50% Complete  
24 Roof top finishing work   80% Complete  
25 Roof top Gardening work G.F Garden work      