City Life

Lalkhanbazar, Chattogram

Expected Completion Date

July 2025

Status Updated

January, 2025

SL. No Name of the work Progress details (January-25) Remarks
01 Foundation work 100% completed.  
02 Super Structure work 100%  Completed  
03 Brick Work GF 50%, A1-100%, B1-100%, A2- 100%, B2-100%, A3-100%, B3-100%, A4-100%, B4-100%,A5-100%, B5-100%, A6-100% B6-100%,  B7-100%,  A7-100%  
04 Electrical work (Slab Conduit) 100%  Conduit laying done on Slab  
05 Door frame fitting work 100% Complete  
06 Sanitary & plumbing line  work 100% Complete  
07 In side Plastering work 100% Complete  
08 Electrical cable wiring work 93% Complete  
09 Wall tiles  work 99% Complete  
10 Common sanitary & Plumbing line work 85% Complete  
11 Outside plastering work 99% Complete  
12 Floor tiles/Marble work 97% Complete  
13 L.C.C work 100% Complete  
14 Grill & Railing work 97% Complete  
15 Inside paint & Polishing work 60% Complete  
16 Switch -Socket fitting work    
17 Outside paint work 50% Complete  
18 Door shutter work 70% Complete  
19 Aluminum/Glazing work 50% Complete  
20 Tiles Pointing work & Marble finishing work 10% Complete  
21 Commode – Basin fitting work and C.P fittings work    
22 Lift/Generator /Substation /Solar work    
23 Boundary wall /Ground floor development work 60% Complete  
24 Land escape /Logo work    
25 Roof top finishing work 70% Complete  
26 Roof top Gardening work    
       