City Life

Lalkhanbazar, Chattogram

Completion Date

April 2025

Status Updated

March, 2024

SL. No Name of the work Progress details
01 Foundation work 100% completed.
02 Super Structure work 100%  Completed
03 Brick Work GF 50%, A1-100%, B1-100%, A2- 100%, B2-100%, A3-100%, B3-100%, A4-100%, B4-100%,A5-100%, B5-100%, A6-100% B6-100%,  B7-75%,  A7-50%
04 Electrical work (Slab Conduit) 100%  Conduit laying done on Slab
05 Door frame fitting work 70% Complete
06 Sanitary & plumbing line  work 40% Complete
07 In side Plastering work 60% Complete
08 Electrical cable wiring work  
09 Wall tiles  work  
10 Common sanitary & Plumbing line work  
11 Outside plastering work 30% Complete
12 Floor tiles/Marble work  
13 L.C.C work  
14 Grill & Railing work 10% Complete
15 Inside paint & Polishing work  
16 Switch -Socket fitting work  
17 Outside paint work  
18 Door shutter work  
19 Aluminum/Glazing work  
20 Tiles Pointing work & Marble finishing work  
21 Commode – Basin fitting work and C.P fittings work  
22 Lift/Generator /Substation /Solar work  
23 Boundary wall /Ground floor development work  
24 Land escape /Logo work  
25 Roof top finishing work  
26 Roof top Gardening work  
     

16604