Completion Date
April 2025
Status Updated
March, 2024
SL. No | Name of the work | Progress details |
01 | Foundation work | 100% completed. |
02 | Super Structure work | 100% Completed |
03 | Brick Work | GF 50%, A1-100%, B1-100%, A2- 100%, B2-100%, A3-100%, B3-100%, A4-100%, B4-100%,A5-100%, B5-100%, A6-100% B6-100%, B7-75%, A7-50% |
04 | Electrical work (Slab Conduit) | 100% Conduit laying done on Slab |
05 | Door frame fitting work | 70% Complete |
06 | Sanitary & plumbing line work | 40% Complete |
07 | In side Plastering work | 60% Complete |
08 | Electrical cable wiring work | |
09 | Wall tiles work | |
10 | Common sanitary & Plumbing line work | |
11 | Outside plastering work | 30% Complete |
12 | Floor tiles/Marble work | |
13 | L.C.C work | |
14 | Grill & Railing work | 10% Complete |
15 | Inside paint & Polishing work | |
16 | Switch -Socket fitting work | |
17 | Outside paint work | |
18 | Door shutter work | |
19 | Aluminum/Glazing work | |
20 | Tiles Pointing work & Marble finishing work | |
21 | Commode – Basin fitting work and C.P fittings work | |
22 | Lift/Generator /Substation /Solar work | |
23 | Boundary wall /Ground floor development work | |
24 | Land escape /Logo work | |
25 | Roof top finishing work | |
26 | Roof top Gardening work | |