Completion Date
July 2025
Status Updated
September, 2024
SL. No | Name of the work | Progress details | Remarks |
01 | Foundation work | 100% completed. | |
02 | Super Structure work | 100% Completed | |
03 | Brick Work | GF 50%, A1-100%, B1-100%, A2- 100%, B2-100%, A3-100%, B3-100%, A4-100%, B4-100%,A5-100%, B5-100%, A6-100% B6-100%, B7-100%, A7-100% | |
04 | Electrical work (Slab Conduit) | 100% Conduit laying done on Slab | |
05 | Door frame fitting work | 100% Complete | |
06 | Sanitary & plumbing line work | 100% Complete | |
07 | In side Plastering work | 100% Complete | |
08 | Electrical cable wiring work | 80% Complete | |
09 | Wall tiles work | 90% Complete | |
10 | Common sanitary & Plumbing line work | 50% Complete | |
11 | Outside plastering work | 95% Complete | |
12 | Floor tiles/Marble work | 80% Complete | |
13 | L.C.C work | ||
14 | Grill & Railing work | 80% Complete | |
15 | Inside paint & Polishing work | 20% Complete | |
16 | Switch -Socket fitting work | ||
17 | Outside paint work | ||
18 | Door shutter work | ||
19 | Aluminum/Glazing work | ||
20 | Tiles Pointing work & Marble finishing work | ||
21 | Commode – Basin fitting work and C.P fittings work | ||
22 | Lift/Generator /Substation /Solar work | ||
23 | Boundary wall /Ground floor development work | 10% Complete | |
24 | Land escape /Logo work | ||
25 | Roof top finishing work | ||
26 | Roof top Gardening work | ||