Get in touch

img

bti Celebration Point

Plot: 3 & 5, Road: 113/A, Gulshan-2, Dhaka-1212

City Life

Lalkhanbazar, Chattogram
Expected Completion Date August 2025
Status Updated July, 2025
Back to all projects
City Life

Construction progress details

The progress table comes directly from the WordPress post content.

SL. No Name of the work Progress details Remarks
01 Foundation work 100% completed.  
02 Super Structure work 100%  Completed  
03 Brick Work GF – 50%, A1-100%, B1-100%, A2- 100%, B2-100%, A3-100%, B3-100%, A4-100%, B4-100%,A5-100%, B5-100%, A6-100% B6-100%,  B7-100%,  A7-100%  
04 Electrical work (Slab Conduit) 100%  Conduit laying done on Slab  
05 Door frame fitting work 100% Complete  
06 Sanitary & plumbing line  work 100% Complete  
07 In side Plastering work 100% Complete  
08 Electrical cable wiring work 100% Complete  
09 Wall tiles  work 100% Complete  
10 Common sanitary & Plumbing line work 99% Complete  
11 Outside plastering work 100% Complete  
12 Floor tiles/Marble work 100% Complete  
13 L.C.C work 100% Complete  
14 Grill & Railing work 100% Complete  
15 Inside paint & Polishing work 95% Complete  
16 Switch -Socket fitting work 90% Complete  
17 Outside paint work 95% Complete  
18 Door shutter work 100% Complete  
19 Aluminum/Glazing work 98% Complete  
20 Tiles Pointing work & Marble finishing work 90% Complete  
21 Commode – Basin fitting work and C.P fittings work 95% Complete  
22 Lift/Generator /Substation /Solar work 85% Complete  
23 Boundary wall /Ground floor development work 90% Complete  
24 Land escape /Logo work 50% Complete  
25 Roof top finishing work 97% Complete  
26 Roof top Gardening work 70% Complete  
       
Contact Call WhatsApp