City Pointe

Aftabnagar, Dhaka

Expected Completion Date

February 2027

Status Updated

July, 2025

SL. No Name of the work Location Progress details Remarks
01 Foundation work   100% completed  
02 Super Structure work   90% completed  
03 Block Work Apartment =A2

Apartment =B2

Apartment =C2

Apartment =D2

Apartment =E2

Apartment =F2

Apartment =G2

Apartment =H2

Apartment =I2

Apartment =J2

Apartment =A3

Apartment =B3

Apartment =C3

Apartment =D3

Apartment =E3

Apartment =F3

Apartment =G3

Apartment =H3

Apartment =I3

Apartment =J3

Apartment =A4

Apartment =B4

Apartment =C4

Apartment =D4

Apartment =E4

Apartment =F4

Apartment =G4

Apartment =H4

Apartment =I4

Apartment =J4

Apartment =A5

Apartment =B5

Apartment =C5

Apartment =D5

Apartment =E5

Apartment =F5

Apartment =G5

Apartment =H5

Apartment =I5

Apartment =J5

 

 

60% Complete

60% Complete

60% Complete

60% Complete

70% Complete

70% Complete

65% Complete

65% Complete

70% Complete

70% Complete

40% Complete

40% Complete

40% Complete

40% Complete

45% Complete

45% Complete

40% Complete

40% Complete

40% Complete

40% Complete

25% Complete

25% Complete

25% Complete

25% Complete

40% Complete

35% Complete

35% Complete

35% Complete

35% Complete

35% Complete

0% Complete

0% Complete

0% Complete

0% Complete

20% Complete

20% Complete

15% Complete

15% Complete

15% Complete

15% Complete

 

 

 

 

 
04 Electrical conduiting work Apartment =A2

Apartment =B2

Apartment =C2

Apartment =D2

Apartment =E2

Apartment =F2

Apartment =G2

Apartment =H2

Apartment =I2

Apartment =J2

Apartment =A3

Apartment =B3

Apartment =C3

Apartment =D3

Apartment =E3

Apartment =F3

Apartment =G3

Apartment =H3

Apartment =I3

Apartment =J3

Apartment =A4

Apartment =B4

Apartment =C4

Apartment =D4

Apartment =E4

Apartment =F4

Apartment =G4

Apartment =H4

Apartment =I4

Apartment =J4

 

 

 

70% Complete

70% Complete

70% Complete

70% Complete

60% Complete

60% Complete

60% Complete

60% Complete

60% Complete

60% Complete

45% Complete

45% Complete

45% Complete

45% Complete

40% Complete

40% Complete

40% Complete

40% Complete

40% Complete

40% Complete

30% Complete

30% Complete

30% Complete

30% Complete

25% Complete

25% Complete

25% Complete

25% Complete

25% Complete

25% Complete

 

 

 
05 Door frame fitting work      
06 Sanitary & plumbing line work   1% Complete  
07 In side Plastering work      
08 Electrical cable wiring work      
09 Wall tiles work      
10 Common sanitary & Plumbing line work      
11 Outside plastering work      
12 Floor tiles/Marble work      
13 L.C.C work      
14 Grill & Railing work      
15 Inside paint & Polishing work      
16 Switch -Socket fitting work      
17 Outside paint work      
18 Door shutter work      
19 Aluminum work      
20 Tiles Pointing work & Marble finishing work      
21 Commode-Basin fitting work and CP fittings work      
22 Lift/Generator /Substation /Solar work      
23 Boundary wall /Ground floor development work      
24 Roof top finishing work      
25 Roof top Gardening work G.F Garden work      

16604