Expected Completion Date
February 2027
Status Updated
May, 2025
SL. No | Name of the work | Location | Progress details | Remarks |
01 | Foundation work | 100% completed | ||
02 | Super Structure work | T1 : 7th floor roof slab casting completed.
T2 : 8th floor roof slab casting completed. T3 : 8th floor roof slab casting completed. |
||
03 | Block Work | Apartment =A2
Apartment =B2 Apartment =C2 Apartment =D2 Apartment =E2 Apartment =F2 Apartment =G2 Apartment =H2 Apartment =I2 Apartment =J2 Apartment =A3 Apartment =B3 Apartment =C3 Apartment =D3 Apartment =E3 Apartment =F3 Apartment =G3 Apartment =H3 Apartment =I3 Apartment =J3 Apartment =A4 Apartment =B4 Apartment =C4 Apartment =D4 Apartment =E4 Apartment =F4 Apartment =G4 Apartment =H4 Apartment =I4 Apartment =J4
|
55% Complete
55% Complete 55% Complete 55% Complete 55% Complete 55% Complete 55% Complete 55% Complete 55% Complete 55% Complete 35% Complete 35% Complete 35% Complete 35% Complete 35% Complete 35% Complete 35% Complete 35% Complete 35% Complete 35% Complete 20% Complete 20% Complete 20% Complete 20% Complete 20% Complete 20% Complete 20% Complete 20% Complete 20% Complete 20% Complete
|
|
04 | Electrical conduiting work | Apartment =A2
Apartment =B2 Apartment =C2 Apartment =D2 Apartment =E2 Apartment =F2 Apartment =G2 Apartment =H2 Apartment =I2 Apartment =J2 Apartment =A3 Apartment =B3 Apartment =C3 Apartment =D3 Apartment =E3 Apartment =F3 Apartment =G3 Apartment =H3 Apartment =I3 Apartment =J3 Apartment =A4 Apartment =B4 Apartment =C4 Apartment =D4 Apartment =E4 Apartment =F4 Apartment =G4 Apartment =H4 Apartment =I4 Apartment =J4
|
55% Complete
55% Complete 55% Complete 55% Complete 55% Complete 55% Complete 55% Complete 55% Complete 55% Complete 55% Complete 35% Complete 35% Complete 35% Complete 35% Complete 35% Complete 35% Complete 35% Complete 35% Complete 35% Complete 35% Complete 20% Complete 20% Complete 20% Complete 20% Complete 20% Complete 20% Complete 20% Complete 20% Complete 20% Complete 20% Complete
|
|
05 | Door frame fitting work | |||
06 | Sanitary & plumbing line work | |||
07 | In side Plastering work | |||
08 | Electrical cable wiring work | |||
09 | Wall tiles work | |||
10 | Common sanitary & Plumbing line work | |||
11 | Outside plastering work | |||
12 | Floor tiles/Marble work | |||
13 | L.C.C work | |||
14 | Grill & Railing work | |||
15 | Inside paint & Polishing work | |||
16 | Switch -Socket fitting work | |||
17 | Outside paint work | |||
18 | Door shutter work | |||
19 | Aluminum work | |||
20 | Tiles Pointing work & Marble finishing work | |||
21 | Commode-Basin fitting work and CP fittings work | |||
22 | Lift/Generator /Substation /Solar work | |||
23 | Boundary wall /Ground floor development work | |||
24 | Roof top finishing work | |||
25 | Roof top Gardening work G.F Garden work |
16604