City Pointe

Aftabnagar, Dhaka

Expected Completion Date

February 2027

Status Updated

June, 2025

SL. No Name of the work Location Progress details Remarks
01 Foundation work   100% completed  
02 Super Structure work   85% completed  
03 Block Work Apartment =A2

Apartment =B2

Apartment =C2

Apartment =D2

Apartment =E2

Apartment =F2

Apartment =G2

Apartment =H2

Apartment =I2

Apartment =J2

Apartment =A3

Apartment =B3

Apartment =C3

Apartment =D3

Apartment =E3

Apartment =F3

Apartment =G3

Apartment =H3

Apartment =I3

Apartment =J3

Apartment =A4

Apartment =B4

Apartment =C4

Apartment =D4

Apartment =E4

Apartment =F4

Apartment =G4

Apartment =H4

Apartment =I4

Apartment =J4

Apartment =A5

Apartment =B5

Apartment =C5

Apartment =D5

Apartment =E5

Apartment =F5

Apartment =G5

Apartment =H5

Apartment =I5

Apartment =J5

55% Complete

55% Complete

55% Complete

55% Complete

65% Complete

65% Complete

60% Complete

60% Complete

65% Complete

65% Complete

35% Complete

35% Complete

35% Complete

35% Complete

40% Complete

40% Complete

35% Complete

35% Complete

35% Complete

35% Complete

20% Complete

20% Complete

20% Complete

20% Complete

35% Complete

30% Complete

30% Complete

30% Complete

30% Complete

30% Complete

0% Complete

0% Complete

0% Complete

0% Complete

15% Complete

15% Complete

10% Complete

10% Complete

10% Complete

10% Complete

 
04 Electrical conduiting work Apartment =A2

Apartment =B2

Apartment =C2

Apartment =D2

Apartment =E2

Apartment =F2

Apartment =G2

Apartment =H2

Apartment =I2

Apartment =J2

Apartment =A3

Apartment =B3

Apartment =C3

Apartment =D3

Apartment =E3

Apartment =F3

Apartment =G3

Apartment =H3

Apartment =I3

Apartment =J3

Apartment =A4

Apartment =B4

Apartment =C4

Apartment =D4

Apartment =E4

Apartment =F4

Apartment =G4

Apartment =H4

Apartment =I4

Apartment =J4

 

65% Complete

65% Complete

65% Complete

65% Complete

55% Complete

55% Complete

55% Complete

55% Complete

55% Complete

55% Complete

40% Complete

40% Complete

40% Complete

40% Complete

35% Complete

35% Complete

35% Complete

35% Complete

35% Complete

35% Complete

25% Complete

25% Complete

25% Complete

25% Complete

20% Complete

20% Complete

20% Complete

20% Complete

20% Complete

20% Complete

 

 
05 Door frame fitting work   0% Complete  
06 Sanitary & plumbing line work   0% Complete  
07 In side Plastering work   0% Complete  
08 Electrical cable wiring work   0% Complete  
09 Wall tiles work   0% Complete  
10 Common sanitary & Plumbing line work   0% Complete  
11 Outside plastering work   0% Complete  
12 Floor tiles/Marble work   0% Complete  
13 L.C.C work   0% Complete  
14 Grill & Railing work   0% Complete  
15 Inside paint & Polishing work   0% Complete  
16 Switch -Socket fitting work   0% Complete  
17 Outside paint work   0% Complete  
18 Door shutter work   0% Complete  
19 Aluminum work   0% Complete  
20 Tiles Pointing work & Marble finishing work   0% Complete  
21 Commode-Basin fitting work and CP fittings work   0% Complete  
22 Lift/Generator /Substation /Solar work   0% Complete  
23 Boundary wall /Ground floor development work   0% Complete  
24 Roof top finishing work   0% Complete  
25 Roof top Gardening work G.F Garden work   0% Complete  

 

16604