Cosmopolis

Mirpur, Dhaka

Expected Completion Date

September 2026

Status Updated

December, 2025

SL. No Name of the work Progress details
  Foundation work 100% Completed
  Super Structure work 99% completed
  Block work T-1,2,3&4, A-Type=94%, B-Type=94% C-Type=94%, D-Type=94%,
  Electrical  conduit work T-3&4, A-Type=100%, B-Type=100%, C-Type=100%, D-Type=100%,

T-1,2 Type (A)= 62%, B-Type= 62%,

C-Type=62%,

  Door frame fitting work 98%
  Sanitary & plumbing line  work 65%
  In side Plastering work 85%
  Electrical cable wiring work 50%
  Wall tiles  work 60.%
  Common Area sanitary & Plumbing line work N/A
  Outside plastering work 40%
  Floor tiles/Marble work 40
  L.C.C work N/A
  Grill & Railing work 20%
  Inside paint & Polishing work N/A
  Switch -Socket fitting work N/A
  Outside paint work N/A
  Door shutter work N/A
  Aluminum/Glazing work N/A
  Tiles Pointing work & Marble finishing work N/A
  Commode – Basin fitting work and C.P fittings work N/A
  Lift/Generator /Substation /Solar work N/A
  Boundary wall /Ground floor development work 40%
  Roof top finishing work 30%
  Roof top Gardening work N/A

 