Cosmopolis

Mirpur, Dhaka

Expected Completion Date

September 2026

Status Updated

February, 2026

SL. No Name of the work Progress details
  Foundation work 100% Completed
  Super Structure work 99% completed
  Block work T-1,2,3&4, A-Type=97%, B-Type=97% C-Type=97%, D-Type=97%,
  Electrical  conduit work T-3&4, A-Type=100%, B-Type=100%, C-Type=100%, D-Type=100%,

T-1,2 Type (A)= 70%, B-Type= 70%,

C-Type=70%,

  Door frame fitting work 98%
  Sanitary & plumbing line  work 70%
  In side Plastering work 89%
  Electrical cable wiring work 54%
  Wall tiles  work 65.%
  Common Area sanitary & Plumbing line work N/A
  Outside plastering work 50%
  Floor tiles/Marble work 45%
  L.C.C work N/A
  Grill & Railing work 25%
  Inside paint & Polishing work 1%
  Switch -Socket fitting work N/A
  Outside paint work N/A
  Door shutter work N/A
  Aluminum/Glazing work N/A
  Tiles Pointing work & Marble finishing work N/A
  Commode – Basin fitting work and C.P fittings work N/A
  Lift/Generator /Substation /Solar work N/A
  Boundary wall /Ground floor development work 43%
  Roof top finishing work 35%
  Roof top Gardening work 10%