Cosmopolis

Mirpur, Dhaka

Expected Completion Date

September 2026

Status Updated

July, 2025

SL. No Name of the work Progress details
  Foundation work 100% Completed
  Super Structure work 99% completed
  Block work T-1,2,3&4, A-Type=83%, B-Type=83% C-Type=83%, D-Type=83%,
  Electrical  conduit work T-3&4, A-Type=77%, B-Type=77%, C-Type=77%, D-Type=77%,

T-1,2 Type (A)= 47%, B-Type= 47%,

C-Type=47%,

  Door frame fitting work 49%
  Sanitary & plumbing line  work 42%
  In side Plastering work 52%
  Electrical cable wiring work 0.5%
  Wall tiles  work 0.5%
  Common Area sanitary & Plumbing line work N/A
  Outside plastering work 5%
  Floor tiles/Marble work N/A
  L.C.C work N/A
  Grill & Railing work N/A
  Inside paint & Polishing work N/A
  Switch -Socket fitting work N/A
  Outside paint work N/A
  Door shutter work N/A
  Aluminum/Glazing work N/A
  Tiles Pointing work & Marble finishing work N/A
  Commode – Basin fitting work and C.P fittings work N/A
  Lift/Generator /Substation /Solar work N/A
  Boundary wall /Ground floor development work 16%
  Roof top finishing work N/A
  Roof top Gardening work N/A

 