Cosmopolis

Mirpur, Dhaka

Expected Completion Date

September 2026

Status Updated

November, 2025

SL. No Name of the work Progress details
  Foundation work 100% Completed
  Super Structure work 99% completed
  Block work T-1,2,3&4, A-Type=93%, B-Type=93% C-Type=93%, D-Type=93%,
  Electrical  conduit work T-3&4, A-Type=91%, B-Type=91%, C-Type=91%, D-Type=91%,

T-1,2 Type (A)= 62%, B-Type= 62%,

C-Type=62%,

  Door frame fitting work 66%
  Sanitary & plumbing line  work 49%
  In side Plastering work 62%
  Electrical cable wiring work 1%
  Wall tiles  work 32.%
  Common Area sanitary & Plumbing line work N/A
  Outside plastering work 26%
  Floor tiles/Marble work N/A
  L.C.C work N/A
  Grill & Railing work 4%
  Inside paint & Polishing work N/A
  Switch -Socket fitting work N/A
  Outside paint work N/A
  Door shutter work N/A
  Aluminum/Glazing work N/A
  Tiles Pointing work & Marble finishing work N/A
  Commode – Basin fitting work and C.P fittings work N/A
  Lift/Generator /Substation /Solar work N/A
  Boundary wall /Ground floor development work 36%
  Roof top finishing work 16%
  Roof top Gardening work N/A