Crown Manor

Expected Completion Date

February 2029

Status Updated

April, 2026

SL. No Name of the work Location Progress details Remarks
01 Foundation work 100% completed
02 Super Structure work Gr. Floor Roof Casting Completed
03 Block Work
04 Electrical conduiting work
05 Door frame fitting work
06 Sanitary & plumbing line work
07 In side Plastering work
08 Electrical cable wiring work
09 Wall tiles work
10 Common sanitary & Plumbing line work
11 Outside plastering work
12 Floor tiles/Marble work
13 L.C.C work
14 Grill & Railing work
15 Inside paint & Polishing work
16 Switch -Socket fitting work
17 Outside paint work
18 Door shutter work
19 Aluminum work
20 Tiles Pointing work & Marble finishing work
21 Commode-Basin fitting work and CP fittings work
22 Lift/Generator /Substation /Solar work
23 Boundary wall /Ground floor development work
24 Roof top finishing work
25 Roof top Gardening work G.F Garden work

16604