Decoris

Bashundhara R/A, Dhaka
Expected Completion Date September 2026
Status Updated April, 2026
Back to all projects
Decoris

Construction progress details

The progress table comes directly from the WordPress post content.

SL. No Name of the work Progress details
01 Foundation work Foundation completed
02 Super Structure work 95%
03 Block Work  A1 = 100%, A2= 100%, A9= 100%, A4= 100%, A5= 100%, A6= 100%, A7= 100%,
04 Electrical conducting work Common area 40%, A1 = 70%, A2= 70%, A3= 70%, A4= 70%, A5= 50%,
05 Door frame fitting work A1 = 100%, A2= 100%, A3= 100% ,A4= 100%, A5= 100% ,A6= 100%
06 Sanitary & plumbing line work N/A
07 In side Plastering work A1 = 80%, A2= 90%, A9= 80%, A4= 90%, A5= 90%, A6= 90%, A7= 90%,
08 Electrical cable wiring work N/A
09 Wall tiles work 80%
10 Common sanitary & Plumbing line work N/A
11 Outside plastering work N/A
12 Floor tiles/Marble work 50%
13 L.C.C work N/A
14 Grill & Railing work N/A
15 Inside paint & Polishing work N/A
16 Switch -Socket fitting work N/A
17 Outside paint work N/A
18 Door shutter work N/A
19 Aluminum work N/A
20 Tiles Pointing work & Marble finishing work N/A
21 Commode – Basin fitting work and C.P fittings work N/A
22 Lift/Generator /Substation /Solar work N/A
23 Boundary wall /Ground floor development work N/A
24 Roof top finishing work

 

N/A
25 Roof top Gardening work G.F Garden work N/A