Deja Vu

Aftabnagar, Dhaka

Expected Completion Date

April 2028

Status Updated

April, 2026

SL. No Name of the work Location Progress details Remarks
01 Foundation work   100% completed  
02 Super Structure work   96% completed  
03 Block Work Apartment =A2

Apartment =B2

Apartment =A3

Apartment =B3

Apartment =A4

Apartment =B4

Apartment =A5

Apartment =B5

Apartment =A6

Apartment =B6

Apartment =A7

Apartment =B7

Apartment = A8

Apartment = B8

Apartment = A9

Apartment =B9

 

95% Complete

95% Complete

95% Complete

95% Complete

95% Complete

95% Complete

60% Complete

60% Complete

55% Complete

55% Complete

50% Complete

50% Complete

40% Complete

40% Complete

0% Complete

0% Complete

 

 
04 Electrical conduiting work Apartment =A2

Apartment =B2

Apartment =A3

Apartment =B3

Apartment =A4

Apartment =B4

Apartment =A5

Apartment =B5

Apartment =A6

Apartment =B6

Apartment =A7

Apartment =B7

Apartment = A8

Apartment = B8

Apartment = A9

Apartment =B9

 

50% Complete

50% Complete

50% Complete

50% Complete

50% Complete

50% Complete

50% Complete

50% Complete

50% Complete

50% Complete

50% Complete

50% Complete

50% Complete

50% Complete

50% Complete

50% Complete

 
05 Door frame fitting work Ground floor

1st floor

2nd Floor

3rd Floor

4th floor

5th floor

6th floor

7th floor

8th floor

9th floor

0% Complete

0% Complete

0% Complete

0% Complete

0% Complete

0% Complete

0% Complete

0% Complete

0% Complete

0% Complete

 

 
06 Sanitary & plumbing line work   20% Complete  
07 In side Plastering work Apartment =A2

Apartment =B2

Apartment =A3

Apartment =B3

Apartment =A4

Apartment =B4

Apartment =A5

Apartment =B5

Apartment =A6

Apartment =B6

Apartment =A7

Apartment =B7

Apartment = A8

Apartment = B8

Apartment = A9

Apartment =B9

 

40% Complete

40% Complete

40% Complete

40% Complete

40% Complete

40% Complete

40% Complete

40% Complete

40% Complete

40% Complete

40% Complete

40% Complete

40% Complete

40% Complete

0% Complete

0% Complete

 

 
08 Electrical cable wiring work   12% Complete

 

 
09 Wall tiles work      
10 Common sanitary & Plumbing line work      
11 Outside plastering work      
12 Floor tiles/Marble work      
13 L.C.C work      
14 Grill & Railing work      
15 Inside paint & Polishing work      
16 Switch -Socket fitting work      
17 Outside paint work      
18 Door shutter work      
19 Aluminum work      
20 Tiles Pointing work & Marble finishing work      
21 Commode-Basin fitting work and CP fittings work      
22 Lift/Generator /Substation /Solar work      
23 Boundary wall /Ground floor development work      
24 Roof top finishing work      
25 Roof top Gardening work G.F Garden work      