Domus

Block K, Bashundhara R/A

Expected Completion Date

May 2026

Status Updated

February, 2026

SL. No Name of the work Progress details
01 Foundation work 100% Completed
02 Super Structure work 100% Completed
03 Block work  100%  Completed
04 Electrical  conduit  work 100% completed
05 Door frame fitting work 100% complete
06 Sanitary & plumbing line  work 95% complete
07 In side Plastering work 100% complete
08 Electrical cable wiring work 95% complete
09 Wall tiles  work 95% complete
10 Common sanitary & Plumbing line work 85% complete
11 Outside plastering work 100% complete
12 Floor tiles/Marble work 90% complete
13 L.C.C work 100% complete
14 Grill & Railing work 95% complete
15 Inside paint & Polishing work N/A
16 Switch -Socket fitting work N/A
17 Outside paint work N/A
18 Door shutter work N/A
19 Aluminum/Glazing work 70% complete
20 Tiles Pointing work & Marble finishing work N/A
21 Commode – Basin fitting work and C.P fittings work 2% complete
22 Lift/Generator /Substation /Solar work 80% complete
23 Boundary wall /Ground floor development work 80% complete
24 Roof top finishing work 70% complete
25 Roof top Gardening work N/A

 