Domus

Block K, Bashundhara R/A

Expected Completion Date

April 2026

Status Updated

November, 2025

SL. No Name of the work Progress details
01 Foundation work 100% Completed
02 Super Structure work 100% Completed
03 Block work  100%  Completed
04 Electrical  conduit  work 100% completed
05 Door frame fitting work 100%
06 Sanitary & plumbing line  work 85% complete
07 In side Plastering work 100%
08 Electrical cable wiring work 90%
09 Wall tiles  work 75%
10 Common sanitary & Plumbing line work 20%
11 Outside plastering work 100%
12 Floor tiles/Marble work 40%
13 L.C.C work N/A
14 Grill & Railing work 50%
15 Inside paint & Polishing work N/A
16 Switch -Socket fitting work N/A
17 Outside paint work N/A
18 Door shutter work N/A
19 Aluminum/Glazing work N/A
20 Tiles Pointing work & Marble finishing work N/A
21 Commode – Basin fitting work and C.P fittings work N/A
22 Lift/Generator /Substation /Solar work N/A
23 Boundary wall /Ground floor development work 20%
24 Roof top finishing work N/A
25 Roof top Gardening work N/A

 