bti Celebration Point

Plot: 3 & 5, Road: 113/A, Gulshan-2, Dhaka-1212

Domus

Bashundhara R/A, Dhaka
Expected Completion Date June 2026
Status Updated April, 2026
Back to all projects
Domus

Construction progress details

The progress table comes directly from the WordPress post content.

SL. No Name of the work Progress details
01 Foundation work 100% Completed
02 Super Structure work 100% Completed
03 Block work  100%  Completed
04 Electrical  conduit  work 100% completed
05 Door frame fitting work 100% complete
06 Sanitary & plumbing line  work 100% complete
07 In side Plastering work 100% complete
08 Electrical cable wiring work 98% complete
09 Wall tiles  work 97% complete
10 Common sanitary & Plumbing line work 93% complete
11 Outside plastering work 100% complete
12 Floor tiles/Marble work 94% complete
13 L.C.C work 100% complete
14 Grill & Railing work 97% complete
15 Inside paint & Polishing work 45%
16 Switch -Socket fitting work N/A
17 Outside paint work 20%
18 Door shutter work N/A
19 Aluminum/Glazing work 85% complete
20 Tiles Pointing work & Marble finishing work N/A
21 Commode – Basin fitting work and C.P fittings work 5% complete
22 Lift/Generator /Substation /Solar work 85% complete
23 Boundary wall /Ground floor development work 89% complete
24 Roof top finishing work 75% complete
25 Roof top Gardening work N/A

 