Dreams Ville

Bashundhara R/A, Dhaka

Expected Completion Date

November 2024

Status Updated

November, 2024

SL. No Name of the work Progress details
01 Foundation work 100% completed.
02 Super Structure work 100% completed.
03 Block Work A-1 = 100%, A-2= 100%, A-3= 100%, A-4= 100%, A-5= 100%, A-6= 100%, A-7= 100%, A-8= 100%, A-9= 100%,
04 Electrical conducting work A-1 = 100%, A-2= 100%, A-3= 100%, A-4= 100%, A-5=100%, A-6= 100%, A-7= 100%, A-8= 100%, A-9= 100%,
05 Door frame fitting work A1= 100%, A-2= 100%, A-3= 100%, A-4= 100%, A-5= 100%, A-6= 100%, A-7= 100%, A-7= 100%, A-7= 100%,
06 Sanitary & plumbing line work  A-2= 80%, A-3= 80%, A-4= 60%, A-5= 90%, A-6= 90%, A-7= 80%, A-8= 90%, A-9= 90%,
07 In side Plastering work  A-1 = 100%, A-2= 100%, A-3= 100%, A-4= 100%, A-5= 100%, A-6= 100%, A-7= 100%, A8= 100%, A-9= 100%,
08 Electrical cable wiring work A-1 = 100% A-2= 100%, A-3= 100%, A-4= 100%, A-5= 100%, A-6= 100%, A-7= 100%, A8= 100%, A-9=100%,
09 Wall tiles work A-1 = 100%, A-2= 100%, A-3= 100%, A-4= 100%, A-5= 100%, A-6= 100%, A-7= 100%, A8= 100%, A-9=100%,
10 Common sanitary & Plumbing line work N/A
11 Outside plastering work 100%
12 Floor tiles/Marble work A-1 = 100%, A-2= 100%, A-3= 100%, A-4= 100%, A-5= 100%, A-6= 100%, A-7= 100%, A8= 100%, A-9=100%,
13 L.C.C work 100%
14 Grill & Railing work 80%
15 Inside paint & Polishing work N/A
16 Switch -Socket fitting work N/A
17 Outside paint work N/A
18 Door shutter work N/A
19 Aluminum work N/A
20 Tiles Pointing work & Marble finishing work N/A
21 Commode – Basin fitting work and C.P fittings work N/A
22 Lift/Generator /Substation /Solar work 10%
23 Boundary wall /Ground floor development work N/A
24 Roof top finishing work 90%
25 Roof top Gardening work G.F Garden work 30%