bti Celebration Point

Plot: 3 & 5, Road: 113/A, Gulshan-2, Dhaka-1212

Familia

Bashundhara R/A, Dhaka
Expected Completion Date November 2026
Status Updated April, 2026
Back to all projects
Familia

Construction progress details

The progress table comes directly from the WordPress post content.

SL. No Name of the work Progress details
01 Foundation work 100% Completed
02 Super Structure work 98% Completed
03 Block work 90%  Completed
04 Electrical  conduit  work 70% completed
05 Door frame fitting work 50%
06 Sanitary & plumbing line  work 25% complete
07 In side Plastering work 10%
08 Electrical cable wiring work 00 %
09 Wall tiles  work N/A
10 Common sanitary & Plumbing line work N/A
11 Outside plastering work N/A
12 Floor tiles/Marble work N/A
13 L.C.C work N/A
14 Grill & Railing work N/A
15 Inside paint & Polishing work N/A
16 Switch -Socket fitting work N/A
17 Outside paint work N/A
18 Door shutter work N/A
19 Aluminum/Glazing work N/A
20 Tiles Pointing work & Marble finishing work N/A
21 Commode – Basin fitting work and C.P fittings work N/A
22 Lift/Generator /Substation /Solar work N/A
23 Boundary wall /Ground floor development work N/A
24 Roof top finishing work N/A
25 Roof top Gardening work N/A