Expected Completion Date
June 2024
Status Updated
August, 2024
| SL. No | Name of the work | Progress details |
| 01 | Foundation work | 100% completed. |
| 02 | Super Structure work | 100% completed. |
| 03 | Block Work | 95% completed. |
| 04 | Electrical conducting work | 80 % completed. |
| 05 | Door frame fitting work | 90% completed. |
| 06 | Sanitary & plumbing line work | 70 % completed. |
| 07 | In side Plastering work | 90 % completed. |
| 08 | Electrical cable wiring work | 40 % completed. |
| 09 | Wall tiles work | 80 % completed. |
| 10 | Common sanitary & Plumbing line work | 0 % completed. |
| 11 | Outside plastering work | 40% completed. |
| 12 | Floor tiles/Marble work | 70 % completed |
| 13 | L.C.C work | 0% completed |
| 14 | Grill & Railing work | 0% completed |
| 15 | Inside paint & Polishing work | 0% completed |
| 16 | Switch -Socket fitting work | N/A |
| 17 | Outside paint work | 0% completed |
| 18 | Door shutter work | 0% completed |
| 19 | Aluminum work | 0% completed |
| 20 | Tiles Pointing work & Marble finishing work | 0% completed |
| 21 | Commode – Basin fitting work and C.P fittings work | 0% completed |
| 22 | Lift/Generator /Substation /Solar work | 0% completed |
| 23 | Boundary wall /Ground floor development work | 0% completed. |
| 24 | Roof top finishing work | 0% completed. |
| 25 | Roof top Gardening work G.F Garden work | 0% completed. |