Expected Completion Date
July 2027
Status Updated
January, 2026
| SL. No | Name of the work | Progress details |
| 01 | Foundation work | Foundation Completed |
| 02 | Super Structure work | 95% |
| 03 | Block Work | A2 = 30%, B2= 30%, A3 = 80%, B3= 80% ,A4= 80%, B4= 80% ,A5 = 70%, B5= 70% A6= 70%, B6= 70%, A7= 60%, B7= 60%, A8= 50%, B8= 50%, A9=10%, B9= 10%, |
| 04 | Electrical conducting work | A2 = 30%, B2= 30%, A3 = 80%, B3= 80% ,A4= 80%, B4= 80% ,A5 = 70%, B5= 70% A6= 70%, B6= 70%, A7= 60%, B7= 60%, A8= 50%, B8= 50%, A9=10%, B9= 10%, |
| 05 | Door frame fitting work | N/A |
| 06 | Sanitary & plumbing line work | N/A |
| 07 | In side Plastering work | N/A |
| 08 | Electrical cable wiring work | N/A |
| 09 | Wall tiles work | N/A |
| 10 | Common sanitary & Plumbing line work | N/A |
| 11 | Outside plastering work | N/A |
| 12 | Floor tiles/Marble work | N/A |
| 13 | L.C.C work | N/A |
| 14 | Grill & Railing work | N/A |
| 15 | Inside paint & Polishing work | N/A |
| 16 | Switch -Socket fitting work | N/A |
| 17 | Outside paint work | N/A |
| 18 | Door shutter work | N/A |
| 19 | Aluminum work | N/A |
| 20 | Tiles Pointing work & Marble finishing work | N/A |
| 21 | Commode – Basin fitting work and C.P fittings work | N/A |
| 22 | Lift/Generator /Substation /Solar work | N/A |
| 23 | Boundary wall /Ground floor development work | N/A |
| 24 | Roof top finishing work
|
N/A |
| 25 | Roof top Gardening work G.F Garden work | N/A |
16604