Fortune Homes

Block K, Bashundhara R/A

Expected Completion Date

July 2027

Status Updated

January, 2026

SL. No Name of the work Progress details
01 Foundation work Foundation Completed
02 Super Structure work 95%
03 Block Work A2 = 30%, B2= 30%, A3 = 80%, B3= 80% ,A4= 80%, B4= 80% ,A5 = 70%, B5= 70% A6= 70%, B6= 70%, A7= 60%, B7= 60%, A8= 50%, B8= 50%, A9=10%, B9= 10%,
04 Electrical conducting work A2 = 30%, B2= 30%, A3 = 80%, B3= 80% ,A4= 80%, B4= 80% ,A5 = 70%, B5= 70% A6= 70%, B6= 70%, A7= 60%, B7= 60%, A8= 50%, B8= 50%, A9=10%, B9= 10%,
05 Door frame fitting work N/A
06 Sanitary & plumbing line work N/A
07 In side Plastering work N/A
08 Electrical cable wiring work N/A
09 Wall tiles work N/A
10 Common sanitary & Plumbing line work N/A
11 Outside plastering work N/A
12 Floor tiles/Marble work N/A
13 L.C.C work N/A
14 Grill & Railing work N/A
15 Inside paint & Polishing work N/A
16 Switch -Socket fitting work N/A
17 Outside paint work N/A
18 Door shutter work N/A
19 Aluminum work N/A
20 Tiles Pointing work & Marble finishing work N/A
21 Commode – Basin fitting work and C.P fittings work N/A
22 Lift/Generator /Substation /Solar work N/A
23 Boundary wall /Ground floor development work N/A
24 Roof top finishing work

 

N/A
25 Roof top Gardening work G.F Garden work N/A