bti Celebration Point

Plot: 3 & 5, Road: 113/A, Gulshan-2, Dhaka-1212

Fortune Homes

Bashundhara R/A, Dhaka
Expected Completion Date July 2027
Status Updated April, 2026
Back to all projects
Fortune Homes

Construction progress details

The progress table comes directly from the WordPress post content.

SL. No Name of the work Progress details
01 Foundation work Foundation Completed
02 Super Structure work 100%
03 Block Work A2 = 30%, B2= 30%, A3 = 80%, B3= 80% ,A4= 80%, B4= 80% ,A5 = 70%, B5= 70% A6= 70%, B6= 70%, A7= 60%, B7= 60%, A8= 50%, B8= 50%, A9=10%, B9= 10%,
04 Electrical conducting work A2 = 30%, B2= 30%, A3 = 80%, B3= 80% ,A4= 80%, B4= 80% ,A5 = 70%, B5= 70% A6= 70%, B6= 70%, A7= 60%, B7= 60%, A8= 50%, B8= 50%, A9=10%, B9= 10%,
05 Door frame fitting work 60%
06 Sanitary & plumbing line work 20%
07 In side Plastering work A2 = 30%, B2= 30%, A3 = 80%, B3= 80% ,A4= 80%, B4= 80% ,A5 = 70%,
08 Electrical cable wiring work N/A
09 Wall tiles work N/A
10 Common sanitary & Plumbing line work N/A
11 Outside plastering work 30%
12 Floor tiles/Marble work N/A
13 L.C.C work N/A
14 Grill & Railing work N/A
15 Inside paint & Polishing work N/A
16 Switch -Socket fitting work N/A
17 Outside paint work N/A
18 Door shutter work N/A
19 Aluminum work N/A
20 Tiles Pointing work & Marble finishing work N/A
21 Commode – Basin fitting work and C.P fittings work N/A
22 Lift/Generator /Substation /Solar work N/A
23 Boundary wall /Ground floor development work N/A
24 Roof top finishing work

 

N/A
25 Roof top Gardening work G.F Garden work N/A

 