Expected Completion Date
May 2025
Status Updated
November, 2024
SL. No | Name of the work | Location | Progress details | Remarks |
01 | Foundation work | 100% completed. | ||
02 | Super Structure work | 97% | ||
03 | Block Work | Community Hall
Apartment =A2 Apartment =C2 Apartment =D2 Apartment =A3 Apartment =B3 Apartment =A4 Apartment =B4 Apartment =A5 Apartment =B5 Apartment =A6 Apartment =B6 Apartment =A7 Apartment =B7 Apartment =A8 Apartment =B8 Apartment =A9 Apartment =B9 Roof Top |
89% Complete
98% Complete 98% Complete 98% Complete 98% Complete 98% Complete 98% Complete 98% Complete 98% Complete 98% Complete 98% Complete 98% Complete 98% Complete 98% Complete 98% Complete 98% Complete 98% Complete 98% Complete 00% Complete
|
|
04 | Electrical conduiting work | Community Hall
Apartment =A2 Apartment =C2 Apartment =D2 Apartment =A3 Apartment =B3 Apartment =A4 Apartment =B4 Apartment =A5 Apartment =B5 Apartment =A6 Apartment =B6 Apartment =A7 Apartment =B7 Apartment =A8 Apartment =B8 Apartment =A9 Apartment =B9 Roof Top
|
95% Complete
97% Complete 97% Complete 97% Complete 97% Complete 97% Complete 97% Complete 97% Complete 97% Complete 97% Complete 97% Complete 97% Complete 97% Complete 97% Complete 97% Complete 97% Complete 97% Complete 97% Complete |
|
05 | Door frame fitting work | Community Hall
Apartment =A2 Apartment =C2 Apartment =D2 Apartment =A3 Apartment =B3 Apartment =A4 Apartment =B4 Apartment =A5 Apartment =B5 Apartment =A6 Apartment =B6 Apartment =A7 Apartment =B7 Apartment =A8 Apartment =B8 Apartment =A9 Apartment =B9 Roof top |
00% Complete
100% Complete 100% Complete 100% Complete 100% Complete 100% Complete 100% Complete 100% Complete 100% Complete 100% Complete 100% Complete 100% Complete 100% Complete 100% Complete 100% Complete 100% Complete 100% Complete 95% Complete 00% Complete
|
|
06 | Sanitary & plumbing line work | Community Hall
Apartment =A2 Apartment =C2 Apartment =D2 Apartment =A3 Apartment =B3 Apartment =A4 Apartment =B4 Apartment =A5 Apartment =B5 Apartment =A6 Apartment =B6 Apartment =A7 Apartment =B7 Apartment =A8 Apartment =B8 Apartment =A9 Apartment =B9 Roof top |
00% Complete
95% Complete 95% Complete 95% Complete 95% Complete 95% Complete 95% Complete 95% Complete 95% Complete 95% Complete 95% Complete 95% Complete 95% Complete 90% Complete 95% Complete 90% Complete 95% Complete 45% Complete 10% Complete
|
|
07 | In side Plastering work | Community Hall
Apartment =A2 Apartment =C2 Apartment =D2 Apartment =A3 Apartment =B3 Apartment =A4 Apartment =B4 Apartment =A5 Apartment =B5 Apartment =A6 Apartment =B6 Apartment =A7 Apartment =B7 Apartment =A8 Apartment =B8 Apartment =A9 Apartment =B9 Roof top
|
50 % Complete
95% Complete 95% Complete 95% Complete 95% Complete 95% Complete 95% Complete 95% Complete 95% Complete 95% Complete 95% Complete 95% Complete 95% Complete 95% Complete 95% Complete 95% Complete 95% Complete 80% Complete 00% Complete
|
|
08 | Electrical cable wiring work |
Community Hall Apartment =A2 Apartment =C2 Apartment =D2 Apartment =A3 Apartment =B3 Apartment =A4 Apartment =B4 Apartment =A5 Apartment =B5 Apartment =A6 Apartment =B6 Apartment =A7 Apartment =B7 Apartment =A8 Apartment =B8 Apartment =A9 Apartment =B9 Roof top |
00% Complete 95% Complete 30% Complete 30% Complete 95% Complete 80% Complete 95% Complete 80% Complete 95% Complete 80% Complete 95% Complete 30% Complete 95% Complete 30% Complete 95% Complete 30% Complete 95% Complete 30% Complete 00% Complete
|
|
09 | Wall tiles work |
Community Hall Apartment =A2 Apartment =C2 Apartment =D2 Apartment =A3 Apartment =B3 Apartment =A4 Apartment =B4 Apartment =A5 Apartment =B5 Apartment =A6 Apartment =B6 Apartment =A7 Apartment =B7 Apartment =A8 Apartment =B8 Apartment =A9 Apartment =B9 Roof top |
00% Complete 90% Complete 70% Complete 70% Complete 90% Complete 70% Complete 90% Complete 70% Complete 90% Complete 70% Complete 90% Complete 70% Complete 90% Complete 70% Complete 90% Complete 70% Complete 90% Complete 00% Complete 00% Complete
|
|
10 | Common sanitary & Plumbing line work | |||
11 | Outside plastering work | 42% Complete | ||
12 | Floor tiles/Marble work | 40%
|
||
13 | L.C.C work | |||
14 | Grill & Railing work | 6% | ||
15 | Inside paint & Polishing work | |||
16 | Switch -Socket fitting work | |||
17 | Outside paint work | |||
18 | Door shutter work | |||
19 | Aluminum work | |||
20 | Tiles Pointing work & Marble finishing work | |||
21 | Commode – Basin fitting work and C.P fittings work | |||
22 | Lift/Generator /Substation /Solar work | |||
23 | Boundary wall /Ground floor development work | |||
24 | Roof top finishing work | |||
25 | Roof top Gardening work G.F Garden work |
16604