Gold Star

Bashundhara R/A, Dhaka

Completion Date

May 2025

Status Updated

September, 2024

SL. No Name of the work Location Progress details Remarks
01 Foundation work   100% completed.  
02 Super Structure work   97%  
03 Block Work Community Hall

Apartment =A2

Apartment =C2

Apartment =D2

Apartment =A3

Apartment =B3

Apartment =A4

Apartment =B4

Apartment =A5

Apartment =B5

Apartment =A6

Apartment =B6

Apartment =A7

Apartment =B7

Apartment =A8

Apartment =B8

Apartment =A9

Apartment =B9

Roof Top

85% Complete

97% Complete

97% Complete

97% Complete

97% Complete

97% Complete

97% Complete

97% Complete

97% Complete

97% Complete

97% Complete

97% Complete

97% Complete

97% Complete

97% Complete

97% Complete

95% Complete

90% Complete

00% Complete

 

 
04 Electrical conduiting work Community Hall

Apartment =A2

Apartment =C2

Apartment =D2

Apartment =A3

Apartment =B3

Apartment =A4

Apartment =B4

Apartment =A5

Apartment =B5

Apartment =A6

Apartment =B6

Apartment =A7

Apartment =B7

Apartment =A8

Apartment =B8

Apartment =A9

Apartment =B9

Roof Top

95% Complete

95% Complete

95% Complete

95% Complete

95% Complete

95% Complete

97% Complete

97% Complete

97% Complete

97% Complete

97% Complete

97% Complete

95% Complete

95% Complete

95% Complete

95% Complete

95% Complete

95% Complete

 
05 Door frame fitting work Community Hall

Apartment =A2

Apartment =C2

Apartment =D2

Apartment =A3

Apartment =B3

Apartment =A4

Apartment =B4

Apartment =A5

Apartment =B5

Apartment =A6

Apartment =B6

Apartment =A7

Apartment =B7

Apartment =A8

Apartment =B8

Apartment =A9

Apartment =B9

Roof top

00% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

95% Complete

95% Complete

75% Complete

00% Complete

00% Complete

 
06 Sanitary & plumbing line work Community Hall

Apartment =A2

Apartment =C2

Apartment =D2

Apartment =A3

Apartment =B3

Apartment =A4

Apartment =B4

Apartment =A5

Apartment =B5

Apartment =A6

Apartment =B6

Apartment =A7

Apartment =B7

Apartment =A8

Apartment =B8

Apartment =A9

Apartment =B9

Roof top

00% Complete

85% Complete

85% Complete

85% Complete

85% Complete

85% Complete

95% Complete

95% Complete

90% Complete

90% Complete

85% Complete

85% Complete

85% Complete

80% Complete

80% Complete

80% Complete

40% Complete

30% Complete

10% Complete

 
07 In side Plastering work Community Hall

Apartment =A2

Apartment =C2

Apartment =D2

Apartment =A3

Apartment =B3

Apartment =A4

Apartment =B4

Apartment =A5

Apartment =B5

Apartment =A6

Apartment =B6

Apartment =A7

Apartment =B7

Apartment =A8

Apartment =B8

Apartment =A9

Apartment =B9

Roof top

 

50 % Complete

95% Complete

95% Complete

95% Complete

95% Complete

95% Complete

95% Complete

95% Complete

95% Complete

95% Complete

95% Complete

95% Complete

95% Complete

90% Complete

90% Complete

90% Complete

65% Complete

40% Complete

00% Complete

 
08 Electrical cable wiring work Community Hall

Apartment =A2

Apartment =C2

Apartment =D2

Apartment =A3

Apartment =B3

Apartment =A4

Apartment =B4

Apartment =A5

Apartment =B5

Apartment =A6

Apartment =B6

Apartment =A7

Apartment =B7

Apartment =A8

Apartment =B8

Apartment =A9

Apartment =B9

Roof top

00% Complete

20% Complete

20% Complete

20% Complete

20% Complete

20% Complete

80% Complete

80% Complete

80% Complete

80% Complete

80% Complete

20% Complete

30% Complete

30% Complete

30% Complete

30% Complete

00% Complete

00% Complete

00% Complete

 
09 Wall tiles work Community Hall

Apartment =A2

Apartment =C2

Apartment =D2

Apartment =A3

Apartment =B3

Apartment =A4

Apartment =B4

Apartment =A5

Apartment =B5

Apartment =A6

Apartment =B6

Apartment =A7

Apartment =B7

Apartment =A8

Apartment =B8

Apartment =A9

Apartment =B9

Roof top

00% Complete

60% Complete

60% Complete

60% Complete

60% Complete

60% Complete

60% Complete

60% Complete

60% Complete

60% Complete

60% Complete

60% Complete

60% Complete

40% Complete

00% Complete

00% Complete

00% Complete

00% Complete

00% Complete

 

 
10 Common sanitary & Plumbing line work   0%

 

 
11 Outside plastering work   25% Complete  
12 Floor tiles/Marble work      
13 L.C.C work      
14 Grill & Railing work      
15 Inside paint & Polishing work      
16 Switch -Socket fitting work      
17 Outside paint work      
18 Door shutter work      
19 Aluminum work      
20 Tiles Pointing work & Marble finishing work      
21 Commode – Basin fitting work and C.P fittings work      
22 Lift/Generator /Substation /Solar work      
23 Boundary wall /Ground floor development work      
24 Roof top finishing work      
25 Roof top Gardening work G.F Garden work      