Gold Star

Bashundhara R/A, Dhaka

Completion Date

February 2025

Status Updated

March, 2024

SL. No Name of the work Location Progress details
01 Foundation work   100% completed.
02 Super Structure work   Up to 8th floor roof slab completed & 9th floor roof slab & beam re-bar works ongoing.
03 Block Work Community Hall

Apartment =A2

Apartment =C2

Apartment =D2

Apartment =A3

Apartment =B3

Apartment =A4

Apartment =B4

Apartment =A5

Apartment =B5

Apartment =A6

Apartment =B6

Apartment =A7

Apartment =B7

Apartment =A8

80% completed

95% Completed

95% Completed

95% Completed

95% Completed

95% Completed

95% Completed

95% Completed

95% Completed

95% Completed

95% Completed

95% Completed

80% Completed

80% Completed

10% Completed

04 Electrical conduiting work Community Hall

Apartment =A2

Apartment =C2

Apartment =D2

Apartment =A3

Apartment =B3

Apartment =A4

Apartment =B4

Apartment =A5

Apartment =B5

Apartment =A6

Apartment =B6

Apartment =A7

Apartment =B7

Apartment =A8

Apartment =B8

Apartment =A9

Apartment =B9

95% Completed

95% Completed

95% Completed

95% Completed

95% Completed

95% Completed

95% Completed

95% Completed

95% Completed

95% Completed

95% Completed

95% Completed

95% Completed

80% Completed

80% Completed

50% Completed

50% Completed

50% Completed

05 Door frame fitting work Apartment =A2

Apartment =C2

Apartment =D2

Apartment =A3

Apartment =B3

Apartment =A4

Apartment =B4

Apartment =A5

Apartment =B5

Apartment =A6

Apartment =B6

80% Completed

80% Completed

100% Completed

80% Completed

100% Completed

100% Completed

80% Completed

100% Completed

80% Completed

90% Completed

80% Completed

06 Sanitary & plumbing line work Apartment =A2

Apartment =C2

Apartment =D2

Apartment =A3

Apartment =B3

Apartment =A4

Apartment =B4

Apartment =A5

Apartment =B5

Apartment =A6

Apartment =B6

80% Completed

80% Completed

80% Completed

80% Completed

80% Completed

80% Completed

80% Completed

80% Completed

80% Completed

80% Completed

60% Completed

07 In side Plastering work Community Hall

Apartment =A2

Apartment =C2

Apartment =D2

Apartment =A3

Apartment =B3

Apartment =A4

Apartment =B4

Apartment =A5

Apartment =B5

Apartment =A6

Apartment =B6

Apartment =A7

Apartment =B7

Apartment =A8

Apartment =B8

 

50 % Completed

90% Completed

90% Completed

90% Completed

90% Completed

90% Completed

90% Completed

90% Completed

90% Completed

90% Completed

90% Completed

90% Completed

40% Completed

40% Completed

40% Completed

40% Completed

08 Electrical cable wiring work  

Apartment =A2

Apartment =C2

Apartment =D2

Apartment =A3

Apartment =B3

Apartment =A4

Apartment =B4

Apartment =A5

Apartment =B5

 

10% Completed

10% Completed

10% Completed

10% Completed

10% Completed

10% Completed

10% Completed

10% Completed

10% Completed

09 Wall tiles work Apartment =A2

Apartment =C2

Apartment =D2

Apartment =A3

Apartment =B3

Apartment =A4

Apartment =B4

Apartment =A5

Apartment =B5

40% Completed

40% Completed

40% Completed

40% Completed

40% Completed

40% Completed

40% Completed

40% Completed

40% Completed

10 Common sanitary & Plumbing line work    
11 Outside plastering work    
12 Floor tiles/Marble work    
13 L.C.C work    
14 Grill & Railing work    
15 Inside paint & Polishing work    
16 Switch -Socket fitting work    
17 Outside paint work    
18 Door shutter work    
19 Aluminum work    
20 Tiles Pointing work & Marble finishing work    
21 Commode – Basin fitting work and C.P fittings work    
22 Lift/Generator /Substation /Solar work    
23 Boundary wall /Ground floor development work    
24 Roof top finishing work    
25 Roof top Gardening work G.F Garden work    