Completion Date
February 2025
Status Updated
March, 2024
SL. No | Name of the work | Location | Progress details |
01 | Foundation work | 100% completed. | |
02 | Super Structure work | Up to 8th floor roof slab completed & 9th floor roof slab & beam re-bar works ongoing. | |
03 | Block Work | Community Hall
Apartment =A2 Apartment =C2 Apartment =D2 Apartment =A3 Apartment =B3 Apartment =A4 Apartment =B4 Apartment =A5 Apartment =B5 Apartment =A6 Apartment =B6 Apartment =A7 Apartment =B7 Apartment =A8 |
80% completed
95% Completed 95% Completed 95% Completed 95% Completed 95% Completed 95% Completed 95% Completed 95% Completed 95% Completed 95% Completed 95% Completed 80% Completed 80% Completed 10% Completed |
04 | Electrical conduiting work | Community Hall
Apartment =A2 Apartment =C2 Apartment =D2 Apartment =A3 Apartment =B3 Apartment =A4 Apartment =B4 Apartment =A5 Apartment =B5 Apartment =A6 Apartment =B6 Apartment =A7 Apartment =B7 Apartment =A8 Apartment =B8 Apartment =A9 Apartment =B9 |
95% Completed
95% Completed 95% Completed 95% Completed 95% Completed 95% Completed 95% Completed 95% Completed 95% Completed 95% Completed 95% Completed 95% Completed 95% Completed 80% Completed 80% Completed 50% Completed 50% Completed 50% Completed |
05 | Door frame fitting work | Apartment =A2
Apartment =C2 Apartment =D2 Apartment =A3 Apartment =B3 Apartment =A4 Apartment =B4 Apartment =A5 Apartment =B5 Apartment =A6 Apartment =B6 |
80% Completed
80% Completed 100% Completed 80% Completed 100% Completed 100% Completed 80% Completed 100% Completed 80% Completed 90% Completed 80% Completed |
06 | Sanitary & plumbing line work | Apartment =A2
Apartment =C2 Apartment =D2 Apartment =A3 Apartment =B3 Apartment =A4 Apartment =B4 Apartment =A5 Apartment =B5 Apartment =A6 Apartment =B6 |
80% Completed
80% Completed 80% Completed 80% Completed 80% Completed 80% Completed 80% Completed 80% Completed 80% Completed 80% Completed 60% Completed |
07 | In side Plastering work | Community Hall
Apartment =A2 Apartment =C2 Apartment =D2 Apartment =A3 Apartment =B3 Apartment =A4 Apartment =B4 Apartment =A5 Apartment =B5 Apartment =A6 Apartment =B6 Apartment =A7 Apartment =B7 Apartment =A8 Apartment =B8
|
50 % Completed
90% Completed 90% Completed 90% Completed 90% Completed 90% Completed 90% Completed 90% Completed 90% Completed 90% Completed 90% Completed 90% Completed 40% Completed 40% Completed 40% Completed 40% Completed |
08 | Electrical cable wiring work |
Apartment =A2 Apartment =C2 Apartment =D2 Apartment =A3 Apartment =B3 Apartment =A4 Apartment =B4 Apartment =A5 Apartment =B5 |
10% Completed 10% Completed 10% Completed 10% Completed 10% Completed 10% Completed 10% Completed 10% Completed 10% Completed |
09 | Wall tiles work | Apartment =A2
Apartment =C2 Apartment =D2 Apartment =A3 Apartment =B3 Apartment =A4 Apartment =B4 Apartment =A5 Apartment =B5 |
40% Completed
40% Completed 40% Completed 40% Completed 40% Completed 40% Completed 40% Completed 40% Completed 40% Completed |
10 | Common sanitary & Plumbing line work | ||
11 | Outside plastering work | ||
12 | Floor tiles/Marble work | ||
13 | L.C.C work | ||
14 | Grill & Railing work | ||
15 | Inside paint & Polishing work | ||
16 | Switch -Socket fitting work | ||
17 | Outside paint work | ||
18 | Door shutter work | ||
19 | Aluminum work | ||
20 | Tiles Pointing work & Marble finishing work | ||
21 | Commode – Basin fitting work and C.P fittings work | ||
22 | Lift/Generator /Substation /Solar work | ||
23 | Boundary wall /Ground floor development work | ||
24 | Roof top finishing work | ||
25 | Roof top Gardening work G.F Garden work |