Get in touch

img

bti Celebration Point

Plot: 3 & 5, Road: 113/A, Gulshan-2, Dhaka-1212

Greenville Homes

Bashundhara R/A, Dhaka
Expected Completion Date April 2028
Status Updated April, 2026
Back to all projects
Greenville Homes

Construction progress details

The progress table comes directly from the WordPress post content.

SL. No Name of the work Progress details
1 Sub Structure work 95% Completed
2 Super Structure work 65% Completed
3 Block work N/A
4 Electrical conduit work 30%
5 Door frame fitting work N/A
6 Sanitary & plumbing line work N/A
7 In side Plastering work 10% Completed
8 Electrical cable wiring work N/A
9 Wall tiles work N/A
10 Common sanitary & Plumbing line work N/A
11 Outside plastering work N/A
12 Floor tiles/Marble work N/A
13 L.C.C work N/A
14 Grill & Railing work N/A
15 Inside paint & Polishing work N/A
16 Switch -Socket fitting work N/A
17 Outside paint work N/A
18 Door shutter work N/A
19 Aluminum/Glazing work N/A
20 Tiles Pointing work & Marble finishing work N/A
21 Commode – Basin fitting work and C.P fittings work N/A
22 Lift/Generator /Substation /Solar work N/A
23 Boundary wall /Ground floor development work 85% Completed
24 Roof top finishing work N/A
25 Roof top Gardening work N/A

 

Contact Call WhatsApp