Happy Days

Bashundhara R/A, Dhaka

Expected Completion Date

January 2025

Status Updated

December, 2024

SL. No Name of the work Location Progress details Remarks
01 Foundation work   100% completed.  
02 Super Structure work   100% completed.  
03 Block Work Apartment =A1

Apartment =A2

Apartment =A3

Apartment =A4

Apartment =A5

Apartment =A6

Apartment =A7

Apartment =A8

Roof Top

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

 
04 Electrical conduiting work Apartment =A1

Apartment =A2

Apartment =A3

Apartment =A4

Apartment =A5

Apartment =A6

Apartment =A7

Apartment =A8

Roof Top

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

98% Complete

 

 
05 Door frame fitting work Apartment =A1

Apartment =A2

Apartment =A3

Apartment =A4

Apartment =A5

Apartment =A6

Apartment =A7

Apartment =A8

Roof Top

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

 
06 Sanitary & plumbing line work Apartment =A1

Apartment =A2

Apartment =A3

Apartment =A4

Apartment =A5

Apartment =A6

Apartment =A7

Apartment =A8

Roof Top

 

95% Complete

97% Complete

95% Complete

96% Complete

100% Complete

99% Complete

99% Complete

96% Complete

95% Complete

 
07 In side Plastering work Apartment =A1

Apartment =A2

Apartment =A3

Apartment =A4

Apartment =A5

Apartment =A6

Apartment =A7

Apartment =A8

Roof Top

 

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

98% Complete

 

 
08 Electrical cable wiring work Apartment =A1

Apartment =A2

Apartment =A3

Apartment =A4

Apartment =A5

Apartment =A6

Apartment =A7

Apartment =A8

Roof Top

 

 98% Complete

95% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

70% Complete

 

 
09 Wall tiles work Apartment =A1

Apartment =A2

Apartment =A3

Apartment =A4

Apartment =A5

Apartment =A6

Apartment =A7

Apartment =A8

Roof Top

 

95% Complete

95% Complete

95% Complete

95% Complete

100% Complete

97% Complete

97% Complete

97% Complete

80%

 

 
10 Common sanitary & Plumbing line work      
11 Outside plastering work   95% Complete  
12 Floor tiles/Marble work Apartment =A1

Apartment =A2

Apartment =A3

Apartment =A4

Apartment =A5

Apartment =A6

Apartment =A7

Apartment =A8

Roof Top

 

95% Complete

97% Complete

97 %Complete

97% Complete

100% Complete

97% Complete

97% Complete

97% Complete

40%

 

 
13 L.C.C work    

100%

 
14 Grill & Railing work Apartment =A1

Apartment =A2

Apartment =A3

Apartment =A4

Apartment =A5

Apartment =A6

Apartment =A7

Apartment =A8

Roof Top

 

95%

95%

95%

97%

10%

97%

97%

95%

60%

 

 
15 Inside paint & Polishing work Apartment =A1

Apartment =A2

Apartment =A3

Apartment =A4

Apartment =A5

Apartment =A6

Apartment =A7

Apartment =A8

Roof Top

 

80%

70%

50%

50%

100%

80%

80%

70%

0%

 

 
16 Switch -Socket fitting work Apartment =A1

Apartment =A2

Apartment =A3

Apartment =A4

Apartment =A5

Apartment =A6

Apartment =A7

Apartment =A8

Roof Top

 

95%

95%

95%

95%

100%

95%

98%

90%

0%

 

 
17 Outside paint work   10%  
18 Door shutter work Apartment =A1

Apartment =A2

Apartment =A3

Apartment =A4

Apartment =A5

Apartment =A6

Apartment =A7

Apartment =A8

Roof Top

 

96%

96%

96%

96%

100%

96%

96%

95%

0%

 

 
19 Aluminum work Apartment =A1

Apartment =A2

Apartment =A3

Apartment =A4

Apartment =A5

Apartment =A6

Apartment =A7

Apartment =A8

Roof Top

 

95%

90%

95%

90%

100%

96%

98%

90%

0%

 

 
20 Tiles Pointing work & Marble finishing work Apartment =A1

Apartment =A2

Apartment =A3

Apartment =A4

Apartment =A5

Apartment =A6

Apartment =A7

Apartment =A8

Roof Top

 

40%

60%

50%

50%

100%

90%

80%

60%

0%

 

 
21 Commode – Basin fitting work and C.P fittings work Apartment =A1

Apartment =A2

Apartment =A3

Apartment =A4

Apartment =A5

Apartment =A6

Apartment =A7

Apartment =A8

Roof Top

 

90%

95%

95%

95%

100%

90%

90%

80%

0%

 

 
22 Lift/Generator /Substation /Solar work   50%  
23 Boundary wall /Ground floor development work   70%  
24 Roof top finishing work   60%  
25 Roof top Gardening work G.F Garden work   40%  

 