Expected Completion Date
January 2025
Status Updated
December, 2024
SL. No | Name of the work | Location | Progress details | Remarks |
01 | Foundation work | 100% completed. | ||
02 | Super Structure work | 100% completed. | ||
03 | Block Work | Apartment =A1
Apartment =A2 Apartment =A3 Apartment =A4 Apartment =A5 Apartment =A6 Apartment =A7 Apartment =A8 Roof Top |
100% Complete
100% Complete 100% Complete 100% Complete 100% Complete 100% Complete 100% Complete 100% Complete 100% Complete |
|
04 | Electrical conduiting work | Apartment =A1
Apartment =A2 Apartment =A3 Apartment =A4 Apartment =A5 Apartment =A6 Apartment =A7 Apartment =A8 Roof Top |
100% Complete
100% Complete 100% Complete 100% Complete 100% Complete 100% Complete 100% Complete 100% Complete 98% Complete
|
|
05 | Door frame fitting work | Apartment =A1
Apartment =A2 Apartment =A3 Apartment =A4 Apartment =A5 Apartment =A6 Apartment =A7 Apartment =A8 Roof Top |
100% Complete
100% Complete 100% Complete 100% Complete 100% Complete 100% Complete 100% Complete 100% Complete 100% Complete |
|
06 | Sanitary & plumbing line work | Apartment =A1
Apartment =A2 Apartment =A3 Apartment =A4 Apartment =A5 Apartment =A6 Apartment =A7 Apartment =A8 Roof Top
|
95% Complete
97% Complete 95% Complete 96% Complete 100% Complete 99% Complete 99% Complete 96% Complete 95% Complete |
|
07 | In side Plastering work | Apartment =A1
Apartment =A2 Apartment =A3 Apartment =A4 Apartment =A5 Apartment =A6 Apartment =A7 Apartment =A8 Roof Top
|
100% Complete
100% Complete 100% Complete 100% Complete 100% Complete 100% Complete 100% Complete 100% Complete 98% Complete
|
|
08 | Electrical cable wiring work | Apartment =A1
Apartment =A2 Apartment =A3 Apartment =A4 Apartment =A5 Apartment =A6 Apartment =A7 Apartment =A8 Roof Top
|
98% Complete
95% Complete 100% Complete 100% Complete 100% Complete 100% Complete 100% Complete 100% Complete 70% Complete
|
|
09 | Wall tiles work | Apartment =A1
Apartment =A2 Apartment =A3 Apartment =A4 Apartment =A5 Apartment =A6 Apartment =A7 Apartment =A8 Roof Top
|
95% Complete
95% Complete 95% Complete 95% Complete 100% Complete 97% Complete 97% Complete 97% Complete 80%
|
|
10 | Common sanitary & Plumbing line work | |||
11 | Outside plastering work | 95% Complete | ||
12 | Floor tiles/Marble work | Apartment =A1
Apartment =A2 Apartment =A3 Apartment =A4 Apartment =A5 Apartment =A6 Apartment =A7 Apartment =A8 Roof Top
|
95% Complete
97% Complete 97 %Complete 97% Complete 100% Complete 97% Complete 97% Complete 97% Complete 40%
|
|
13 | L.C.C work |
100% |
||
14 | Grill & Railing work | Apartment =A1
Apartment =A2 Apartment =A3 Apartment =A4 Apartment =A5 Apartment =A6 Apartment =A7 Apartment =A8 Roof Top
|
95%
95% 95% 97% 10% 97% 97% 95% 60%
|
|
15 | Inside paint & Polishing work | Apartment =A1
Apartment =A2 Apartment =A3 Apartment =A4 Apartment =A5 Apartment =A6 Apartment =A7 Apartment =A8 Roof Top
|
80%
70% 50% 50% 100% 80% 80% 70% 0%
|
|
16 | Switch -Socket fitting work | Apartment =A1
Apartment =A2 Apartment =A3 Apartment =A4 Apartment =A5 Apartment =A6 Apartment =A7 Apartment =A8 Roof Top
|
95%
95% 95% 95% 100% 95% 98% 90% 0%
|
|
17 | Outside paint work | 10% | ||
18 | Door shutter work | Apartment =A1
Apartment =A2 Apartment =A3 Apartment =A4 Apartment =A5 Apartment =A6 Apartment =A7 Apartment =A8 Roof Top
|
96%
96% 96% 96% 100% 96% 96% 95% 0%
|
|
19 | Aluminum work | Apartment =A1
Apartment =A2 Apartment =A3 Apartment =A4 Apartment =A5 Apartment =A6 Apartment =A7 Apartment =A8 Roof Top
|
95%
90% 95% 90% 100% 96% 98% 90% 0%
|
|
20 | Tiles Pointing work & Marble finishing work | Apartment =A1
Apartment =A2 Apartment =A3 Apartment =A4 Apartment =A5 Apartment =A6 Apartment =A7 Apartment =A8 Roof Top
|
40%
60% 50% 50% 100% 90% 80% 60% 0%
|
|
21 | Commode – Basin fitting work and C.P fittings work | Apartment =A1
Apartment =A2 Apartment =A3 Apartment =A4 Apartment =A5 Apartment =A6 Apartment =A7 Apartment =A8 Roof Top
|
90%
95% 95% 95% 100% 90% 90% 80% 0%
|
|
22 | Lift/Generator /Substation /Solar work | 50% | ||
23 | Boundary wall /Ground floor development work | 70% | ||
24 | Roof top finishing work | 60% | ||
25 | Roof top Gardening work G.F Garden work | 40% |