Expected Completion Date
January 2025
Status Updated
January, 2025
SL. No | Name of the work | Location | Progress details | Remarks |
01 | Foundation work | 100% completed. | ||
02 | Super Structure work | 100% completed. | ||
03 | Block Work | Apartment =A1
Apartment =A2 Apartment =A3 Apartment =A4 Apartment =A5 Apartment =A6 Apartment =A7 Apartment =A8 Roof Top |
100% Complete
100% Complete 100% Complete 100% Complete 100% Complete 100% Complete 100% Complete 100% Complete 100% Complete |
|
04 | Electrical conduiting work | Apartment =A1
Apartment =A2 Apartment =A3 Apartment =A4 Apartment =A5 Apartment =A6 Apartment =A7 Apartment =A8 Roof Top |
100% Complete
100% Complete 100% Complete 100% Complete 100% Complete 100% Complete 100% Complete 100% Complete 98% Complete
|
|
05 | Door frame fitting work | Apartment =A1
Apartment =A2 Apartment =A3 Apartment =A4 Apartment =A5 Apartment =A6 Apartment =A7 Apartment =A8 Roof Top |
100% Complete
100% Complete 100% Complete 100% Complete 100% Complete 100% Complete 100% Complete 100% Complete 100% Complete |
|
06 | Sanitary & plumbing line work | Apartment =A1
Apartment =A2 Apartment =A3 Apartment =A4 Apartment =A5 Apartment =A6 Apartment =A7 Apartment =A8 Roof Top
|
98% Complete
98% Complete 98% Complete 98% Complete 100% Complete 100% Complete 100% Complete 98% Complete 97% Complete |
|
07 | In side Plastering work | Apartment =A1
Apartment =A2 Apartment =A3 Apartment =A4 Apartment =A5 Apartment =A6 Apartment =A7 Apartment =A8 Roof Top
|
100% Complete
100% Complete 100% Complete 100% Complete 100% Complete 100% Complete 100% Complete 100% Complete 98% Complete
|
|
08 | Electrical cable wiring work | Apartment =A1
Apartment =A2 Apartment =A3 Apartment =A4 Apartment =A5 Apartment =A6 Apartment =A7 Apartment =A8 Roof Top
|
98% Complete
98% Complete 100% Complete 100% Complete 100% Complete 100% Complete 100% Complete 100% Complete 95% Complete
|
|
09 | Wall tiles work | Apartment =A1
Apartment =A2 Apartment =A3 Apartment =A4 Apartment =A5 Apartment =A6 Apartment =A7 Apartment =A8 Roof Top
|
95% Complete
95% Complete 95% Complete 95% Complete 100% Complete 100% Complete 100% Complete 99% Complete 95%
|
|
10 | Common sanitary & Plumbing line work | 80%
|
||
11 | Outside plastering work | 98% Complete | ||
12 | Floor tiles/Marble work | Apartment =A1
Apartment =A2 Apartment =A3 Apartment =A4 Apartment =A5 Apartment =A6 Apartment =A7 Apartment =A8 Roof Top
|
95% Complete
97% Complete 97 %Complete 97% Complete 100% Complete 100% Complete 100% Complete 97% Complete 60%
|
|
13 | L.C.C work |
100% |
||
14 | Grill & Railing work | Apartment =A1
Apartment =A2 Apartment =A3 Apartment =A4 Apartment =A5 Apartment =A6 Apartment =A7 Apartment =A8 Roof Top
|
95%
95% 95% 97% 10% 100% 100% 98% 60%
|
|
15 | Inside paint & Polishing work | Apartment =A1
Apartment =A2 Apartment =A3 Apartment =A4 Apartment =A5 Apartment =A6 Apartment =A7 Apartment =A8 Roof Top
|
80%
90% 95% 96% 100% 100% 100% 96% 0%
|
|
16 | Switch -Socket fitting work | Apartment =A1
Apartment =A2 Apartment =A3 Apartment =A4 Apartment =A5 Apartment =A6 Apartment =A7 Apartment =A8 Roof Top
|
98%
98% 98% 98% 100% 100% 100% 98% 50%
|
|
17 | Outside paint work | 35% | ||
18 | Door shutter work | Apartment =A1
Apartment =A2 Apartment =A3 Apartment =A4 Apartment =A5 Apartment =A6 Apartment =A7 Apartment =A8 Roof Top
|
96%
96% 96% 96% 100% 100% 100% 98% 0%
|
|
19 | Aluminum work | Apartment =A1
Apartment =A2 Apartment =A3 Apartment =A4 Apartment =A5 Apartment =A6 Apartment =A7 Apartment =A8 Roof Top
|
95%
90% 95% 90% 100% 100% 100% 96% 0%
|
|
20 | Tiles Pointing work & Marble finishing work | Apartment =A1
Apartment =A2 Apartment =A3 Apartment =A4 Apartment =A5 Apartment =A6 Apartment =A7 Apartment =A8 Roof Top
|
60%
60% 50% 70% 100% 100% 100% 90% 0%
|
|
21 | Commode – Basin fitting work and C.P fittings work | Apartment =A1
Apartment =A2 Apartment =A3 Apartment =A4 Apartment =A5 Apartment =A6 Apartment =A7 Apartment =A8 Roof Top
|
90%
95% 95% 95% 100% 100% 100% 80% 0%
|
|
22 | Lift/Generator /Substation /Solar work | 90% | ||
23 | Boundary wall /Ground floor development work | 85% | ||
24 | Roof top finishing work | 90% | ||
25 | Roof top Gardening work G.F Garden work | 80% |