Happy Days

Bashundhara R/A, Dhaka

Expected Completion Date

January 2025

Status Updated

January, 2025

SL. No Name of the work Location Progress details Remarks
01 Foundation work   100% completed.  
02 Super Structure work   100% completed.  
03 Block Work Apartment =A1

Apartment =A2

Apartment =A3

Apartment =A4

Apartment =A5

Apartment =A6

Apartment =A7

Apartment =A8

Roof Top

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

 
04 Electrical conduiting work Apartment =A1

Apartment =A2

Apartment =A3

Apartment =A4

Apartment =A5

Apartment =A6

Apartment =A7

Apartment =A8

Roof Top

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

98% Complete

 

 
05 Door frame fitting work Apartment =A1

Apartment =A2

Apartment =A3

Apartment =A4

Apartment =A5

Apartment =A6

Apartment =A7

Apartment =A8

Roof Top

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

 
06 Sanitary & plumbing line work Apartment =A1

Apartment =A2

Apartment =A3

Apartment =A4

Apartment =A5

Apartment =A6

Apartment =A7

Apartment =A8

Roof Top

 

98% Complete

98% Complete

98% Complete

98% Complete

100% Complete

100% Complete

100% Complete

98% Complete

97% Complete

 
07 In side Plastering work Apartment =A1

Apartment =A2

Apartment =A3

Apartment =A4

Apartment =A5

Apartment =A6

Apartment =A7

Apartment =A8

Roof Top

 

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

98% Complete

 

 
08 Electrical cable wiring work Apartment =A1

Apartment =A2

Apartment =A3

Apartment =A4

Apartment =A5

Apartment =A6

Apartment =A7

Apartment =A8

Roof Top

 

 98% Complete

98% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

100% Complete

95% Complete

 

 
09 Wall tiles work Apartment =A1

Apartment =A2

Apartment =A3

Apartment =A4

Apartment =A5

Apartment =A6

Apartment =A7

Apartment =A8

Roof Top

 

95% Complete

95% Complete

95% Complete

95% Complete

100% Complete

100% Complete

100% Complete

99% Complete

95%

 

 
10 Common sanitary & Plumbing line work   80%

 

 
11 Outside plastering work   98% Complete  
12 Floor tiles/Marble work Apartment =A1

Apartment =A2

Apartment =A3

Apartment =A4

Apartment =A5

Apartment =A6

Apartment =A7

Apartment =A8

Roof Top

 

95% Complete

97% Complete

97 %Complete

97% Complete

100% Complete

100% Complete

100% Complete

97% Complete

60%

 

 
13 L.C.C work    

100%

 
14 Grill & Railing work Apartment =A1

Apartment =A2

Apartment =A3

Apartment =A4

Apartment =A5

Apartment =A6

Apartment =A7

Apartment =A8

Roof Top

 

95%

95%

95%

97%

10%

100%

100%

98%

60%

 

 
15 Inside paint & Polishing work Apartment =A1

Apartment =A2

Apartment =A3

Apartment =A4

Apartment =A5

Apartment =A6

Apartment =A7

Apartment =A8

Roof Top

 

80%

90%

95%

96%

100%

100%

100%

96%

0%

 

 
16 Switch -Socket fitting work Apartment =A1

Apartment =A2

Apartment =A3

Apartment =A4

Apartment =A5

Apartment =A6

Apartment =A7

Apartment =A8

Roof Top

 

98%

98%

98%

98%

100%

100%

100%

98%

50%

 

 
17 Outside paint work   35%  
18 Door shutter work Apartment =A1

Apartment =A2

Apartment =A3

Apartment =A4

Apartment =A5

Apartment =A6

Apartment =A7

Apartment =A8

Roof Top

 

96%

96%

96%

96%

100%

100%

100%

98%

0%

 

 
19 Aluminum work Apartment =A1

Apartment =A2

Apartment =A3

Apartment =A4

Apartment =A5

Apartment =A6

Apartment =A7

Apartment =A8

Roof Top

 

95%

90%

95%

90%

100%

100%

100%

96%

0%

 

 
20 Tiles Pointing work & Marble finishing work Apartment =A1

Apartment =A2

Apartment =A3

Apartment =A4

Apartment =A5

Apartment =A6

Apartment =A7

Apartment =A8

Roof Top

 

60%

60%

50%

70%

100%

100%

100%

90%

0%

 

 
21 Commode – Basin fitting work and C.P fittings work Apartment =A1

Apartment =A2

Apartment =A3

Apartment =A4

Apartment =A5

Apartment =A6

Apartment =A7

Apartment =A8

Roof Top

 

90%

95%

95%

95%

100%

100%

100%

80%

0%

 

 
22 Lift/Generator /Substation /Solar work   90%  
23 Boundary wall /Ground floor development work   85%  
24 Roof top finishing work   90%  
25 Roof top Gardening work G.F Garden work   80%  