La Maison

Bashundhara R/A, Dhaka

Expected Completion Date

January 2025

Status Updated

December, 2024

SL. No Name of the work Progress details
01 Foundation work 100 % completed.
02 Super Structure work 100% completed.
03 Block Work A-1 = 100% , A-2= 100%, A-3= 100%, A-4= 100%, A-5= 100%, A-6= 100%, A-7= 100%, A-8= 100%,
04 Electrical conducting work A-1 = 100% , A-2= 100%, A-3= 100%, A-4= 100%, A-5= 100%, A-6= 100%, A-7= 100%, A-8= 100%,
05 Door frame fitting work A-1 = 100% , A-2= 100%, A-3= 100%, A-4= 100%, A-5= 100%, A-6= 100%, A-7= 100%, A-8=100%
06 Sanitary & plumbing line work A-1 = 100%, A-2= 100%, A-3= 100%, A-4= 100%, A-5= 100%, A-6= 100%, A-7= 100%, A-8= 100%
07 In side Plastering work A-1 = 100%, A-2= 100%, A-3= 100%, A-4= 100%, A-5= 100%, A-6= 100%, A-7= 100%, A-8= 100%,
08 Electrical cable wiring work A-1 = 100%, A-2= 100%, A-3= 100%, A-4= 100%, A-5= 100%, A-6= 100% ,A-7= 100%, A-8= 100%
09 Wall tiles work A-1 = 100% , A-2= 100%, A-3= 100%, A-4= 100%, A-5= 100%, A-6= 100%, A-7= 100%, A-8= 100%,
10 Common sanitary & Plumbing line work 100%
11 Outside plastering work 100% Completed
12 Floor tiles/Marble work A-1 = 100% , A-2= 100%, A-3= 100%, A-4= 100%, A-5= 100%, A-6= 100%, A-7= 100%, A-8= 100%,
13 L.C.C work 100%
14 Grill & Railing work 100%
15 Inside paint & Polishing work A-1 =90% , A-2= 90%, A-3= 90%, A-4= 90%, A-5= 90%, A-6= 90%, A-7=90%, A-8= 90%,
16 Switch -Socket fitting work A-1 =100% , A-2= 100%, A-3= 100%, A-4= 100%, A-5= 100%, A-6= 100%, A-7=100%, A-8= 100%,
17 Outside paint work 70%
18 Door shutter work 100%
19 Aluminum work 100%
20 Tiles Pointing work & Marble finishing work 70%
21 Commode – Basin fitting work and C.P fittings work 100%
22 Lift/Generator /Substation /Solar work 90%
23 Boundary wall /Ground floor development work 95%
24 Roof top finishing work 95%
25 Roof top Gardening work G.F Garden work 85%

 