La Montana

Moghbazar, Dhaka

Expected Completion Date

December 2027

Status Updated

November, 2024

SL. No Name of the work Location Progress details Remarks
01 Foundation work Tower-1

Tower-2

0% completed

100% completed

 
02 Basement work Tower-1

Tower-2

0% completed

Basement floor Column, Retaining Wall, Ramp work is ongoing.

 

 
03 Ground Floor      
04 Super Structure work      
05 Block Work      
04 Electrical conduiting work      
05 Door frame fitting work      
06 Sanitary & plumbing line work      
07 In side Plastering work      
08 Electrical cable wiring work      
09 Wall tiles work      
10 Common sanitary & Plumbing line work      
11 Outside plastering work      
12 Floor tiles/Marble work      
13 L.C.C work      
14 Grill & Railing work      
15 Inside paint & Polishing work      
16 Switch -Socket fitting work      
17 Outside paint work      
18 Door shutter work      
19 Aluminum work      
20 Tiles Pointing work & Marble finishing work      
21 Commode – Basin fitting work and C.P fittings work      
22 Lift/Generator /Substation /Solar work      
23 Boundary wall /Ground floor development work      
24 Roof top finishing work      
25 Roof top Gardening work G.F Garden work      