Expected Completion Date
December 2027
Status Updated
November, 2025
| SL. No | Name of the work | Location | Progress details | Remarks |
| 01 | Foundation
work |
Tower-1
Tower-2 |
100%completed
100%completed |
|
| 02 | Basement work | Tower-1
Tower-2 |
100%completed
100%completed
|
|
| 03 | Ground Floor | Tower-1
Tower-2 |
100%Completed
100%Completed |
|
| 04 | 1st Floor | Tower-1
Tower-2 |
100% completed
100%Completed |
|
| 05 | 2nd floor | Tower-1
Tower-2 |
100% completed
100%Completed |
|
| 06 | 3rd floor | Tower-1
Tower-2 |
0% completed
100%Completed |
|
| 07 | 4th floor | Tower-1
Tower-2 |
0% completed
100%Completed |
|
| 08 | 5th floor | Tower-1
Tower-2 |
0% Completed
100% Completed
|
|
| 09 | Block Work | Apartment =A1
Apartment =B1 Apartment =C1 Apartment =D1 Apartment =A2 Apartment =B2 Apartment =C2 Apartment =D2 Apartment =A3 Apartment =B3 Apartment =C3 Apartment =D3 Apartment =A4 Apartment =B4 Apartment =C4 Apartment =D4 Apartment =A5 Apartment =B5 Apartment =C5 Apartment =D5 Apartment =A6 Apartment =B6 Apartment =C6 Apartment =D6 Apartment =A7 Apartment =B7 Apartment =C7 Apartment =D7 Apartment =A8 Apartment =B8 Apartment =C8 Apartment =D8 Apartment =A9 Apartment =B9 Apartment =C9 Apartment =D9 Apartment =A10 Apartment =B10 Apartment =C10 Apartment =D10 Apartment =A11 Apartment =B11 Apartment =C11 Apartment =D11 Apartment =A12 Apartment =B12 Apartment =C12 Apartment =D12
|
0% Complete
0% Complete 0% Complete 0% Complete 60% Complete 60% Complete 60% Complete 60% Complete 30% Complete 30% Complete 30% Complete 30% Complete
|
|
| 04 | Electrical conduiting work | Apartment =A2
Apartment =B2 Apartment =C2 Apartment =D2 Apartment =A3 Apartment =B3 Apartment =C3 Apartment =D3 Apartment =A4 Apartment =B4 Apartment =C4 Apartment =D4 Apartment =A5 Apartment =B5 Apartment =C5 Apartment =D5 Apartment =A6 Apartment =B6 Apartment =C6 Apartment =D6 Apartment =A7 Apartment =B7 Apartment =C7 Apartment =D7 Apartment =A8 Apartment =B8 Apartment =C8 Apartment =D8 Apartment =A9 Apartment =B9 Apartment =C9 Apartment =D9 Apartment =A10 Apartment =B10 Apartment =C10 Apartment =D10 Apartment =A11 Apartment =B11 Apartment =C11 Apartment =D11 Apartment =A12 Apartment =B12 Apartment =C12 Apartment =D12 |
30% Complete
30% Complete 30% Complete 30% Complete 20% Complete 20% Complete 20% Complete 20% Complete
|
|
| 05 | Door frame fitting work |
|
||
| 06 | Sanitary & plumbing line work | |||
| 07 | In side Plastering work | Apartment =A2
Apartment =B2 Apartment =C2 Apartment =D2 Apartment =A3 Apartment =B3 Apartment =C3 Apartment =D3 Apartment =A4 Apartment =B4 Apartment =C4 Apartment =D4 Apartment =A5 Apartment =B5 Apartment =C5 Apartment =D5 Apartment =A6 Apartment =B6 Apartment =C6 Apartment =D6 Apartment =A7 Apartment =B7 Apartment =C7 Apartment =D7 Apartment =A8 Apartment =B8 Apartment =C8 Apartment =D8 Apartment =A9 Apartment =B9 Apartment =C9 Apartment =D9 Apartment =A10 Apartment =B10 Apartment =C10 Apartment =D10 Apartment =A11 Apartment =B11 Apartment =C11 Apartment =D11 Apartment =A12 Apartment =B12 Apartment =C12 Apartment =D12 |
40% Complete
40% Complete 40% Complete 40% Complete 40% Complete 40% Complete 40% Complete
40% Complete
|
|
| 08 | Electrical cable wiring work |
|
||
| 09 | Wall tiles work | |||
| 10 | Common sanitary & Plumbing line work | |||
| 11 | Outside plastering work | |||
| 12 | Floor tiles/Marble work | |||
| 13 | L.C.C work | |||
| 14 | Grill & Railing work | |||
| 15 | Inside paint & Polishing work | |||
| 16 | Switch -Socket fitting work | |||
| 17 | Outside paint work | |||
| 18 | Door shutter work | |||
| 19 | Aluminum work | |||
| 20 | Tiles Pointing work & Marble finishing work | |||
| 21 | Commode – Basin fitting work and C.P fittings work | |||
| 22 | Lift/Generator /Substation /Solar work | |||
| 23 | Boundary wall /Ground floor development work | |||
| 24 | Roof top finishing work | |||
| 25 | Roof top Gardening work G.F Garden work |