La Montana

Moghbazar, Dhaka

Expected Completion Date

December 2027

Status Updated

November, 2025

SL. No Name of the work Location Progress details Remarks
01 Foundation

work

Tower-1

Tower-2

100%completed

100%completed

 
02 Basement work Tower-1

Tower-2

100%completed

100%completed

 

 
03 Ground Floor Tower-1

Tower-2

100%Completed

100%Completed

 
04 1st Floor Tower-1

Tower-2

100% completed

100%Completed

 
05 2nd floor Tower-1

Tower-2

100% completed

100%Completed

 
06 3rd floor Tower-1

Tower-2

0% completed

100%Completed

 
07 4th floor Tower-1

Tower-2

0% completed

100%Completed

 
08 5th floor Tower-1

Tower-2

0% Completed

100% Completed

 

 
09 Block Work Apartment =A1

Apartment =B1

Apartment =C1

Apartment =D1

Apartment =A2

Apartment =B2

Apartment =C2

Apartment =D2

Apartment =A3

Apartment =B3

Apartment =C3

Apartment =D3

Apartment =A4

Apartment =B4

Apartment =C4

Apartment =D4

Apartment =A5

Apartment =B5

Apartment =C5

Apartment =D5

Apartment =A6

Apartment =B6

Apartment =C6

Apartment =D6

Apartment =A7

Apartment =B7

Apartment =C7

Apartment =D7

Apartment =A8

Apartment =B8

Apartment =C8

Apartment =D8

Apartment =A9

Apartment =B9

Apartment =C9

Apartment =D9

Apartment =A10

Apartment =B10

Apartment =C10

Apartment =D10

Apartment =A11

Apartment =B11

Apartment =C11

Apartment =D11

Apartment =A12

Apartment =B12

Apartment =C12

Apartment =D12

 

0% Complete

0% Complete

0% Complete

0% Complete

60% Complete

60% Complete

60% Complete

60% Complete

30% Complete

30% Complete

30% Complete

30% Complete

 

 

 
04 Electrical conduiting work Apartment =A2

Apartment =B2

Apartment =C2

Apartment =D2

Apartment =A3

Apartment =B3

Apartment =C3

Apartment =D3

Apartment =A4

Apartment =B4

Apartment =C4

Apartment =D4

Apartment =A5

Apartment =B5

Apartment =C5

Apartment =D5

Apartment =A6

Apartment =B6

Apartment =C6

Apartment =D6

Apartment =A7

Apartment =B7

Apartment =C7

Apartment =D7

Apartment =A8

Apartment =B8

Apartment =C8

Apartment =D8

Apartment =A9

Apartment =B9

Apartment =C9

Apartment =D9

Apartment =A10

Apartment =B10

Apartment =C10

Apartment =D10

Apartment =A11

Apartment =B11

Apartment =C11

Apartment =D11

Apartment =A12

Apartment =B12

Apartment =C12

Apartment =D12

30% Complete

30% Complete

30% Complete

30% Complete

20% Complete

20% Complete

20% Complete

20% Complete

 

 
05 Door frame fitting work    

 

 
06 Sanitary & plumbing line work      
07 In side Plastering work Apartment =A2

Apartment =B2

Apartment =C2

Apartment =D2

Apartment =A3

Apartment =B3

Apartment =C3

Apartment =D3

Apartment =A4

Apartment =B4

Apartment =C4

Apartment =D4

Apartment =A5

Apartment =B5

Apartment =C5

Apartment =D5

Apartment =A6

Apartment =B6

Apartment =C6

Apartment =D6

Apartment =A7

Apartment =B7

Apartment =C7

Apartment =D7

Apartment =A8

Apartment =B8

Apartment =C8

Apartment =D8

Apartment =A9

Apartment =B9

Apartment =C9

Apartment =D9

Apartment =A10

Apartment =B10

Apartment =C10

Apartment =D10

Apartment =A11

Apartment =B11

Apartment =C11

Apartment =D11

Apartment =A12

Apartment =B12

Apartment =C12

Apartment =D12

40% Complete

40% Complete

40% Complete

40% Complete

40% Complete

40% Complete

40% Complete

 

40% Complete

 

 
08 Electrical cable wiring work  

 

   
09 Wall tiles work      
10 Common sanitary & Plumbing line work      
11 Outside plastering work      
12 Floor tiles/Marble work      
13 L.C.C work      
14 Grill & Railing work      
15 Inside paint & Polishing work      
16 Switch -Socket fitting work      
17 Outside paint work      
18 Door shutter work      
19 Aluminum work      
20 Tiles Pointing work & Marble finishing work      
21 Commode – Basin fitting work and C.P fittings work      
22 Lift/Generator /Substation /Solar work      
23 Boundary wall /Ground floor development work      
24 Roof top finishing work      
25 Roof top Gardening work G.F Garden work      

16604