Expected Completion Date
December 2027
Status Updated
September, 2025
| SL. No | Name of the work | Location | Progress details | Remarks |
| 01 | Foundation
work |
Tower-1
Tower-2 |
100%completed
100%completed |
|
| 02 | Basement work | Tower-1
Tower-2 |
100%completed
100%completed
|
|
| 03 | Super Structure | Tower-1
Tower-2 |
1st floor roof slab & beam work is on process
3rd floor roof slab & beam work is on process |
|
| 04
|
Block Work | |||
| 05 | Electrical conduiting work | |||
| 06 | Door frame fitting work | |||
| 07 | Sanitary & plumbing line work | |||
| 08 | In side Plastering work | |||
| 09 | Electrical cable wiring work | |||
| 10 | Wall tiles work | |||
| 11 | Common sanitary & Plumbing line work | |||
| 12 | Outside plastering work | |||
| 13 | Floor tiles/Marble work | |||
| 14 | L.C.C work | |||
| 15 | Grill & Railing work | |||
| 16 | Inside paint & Polishing work | |||
| 17 | Switch -Socket fitting work | |||
| 18 | Outside paint work | |||
| 19 | Door shutter work | |||
| 20 | Aluminum work | |||
| 21 | Tiles Pointing work & Marble finishing work | |||
| 22 | Commode – Basin fitting work and C.P fittings work | |||
| 23 | Lift/Generator /Substation /Solar work | |||
| 24 | Boundary wall /Ground floor development work | |||
| 25 | Roof top finishing work | |||
| 26 | Roof top Gardening work G.F Garden work |