La Montana

Moghbazar, Dhaka

Expected Completion Date

December 2027

Status Updated

July, 2025

SL. No Name of the work Location Progress details Remarks
01 Foundation

work

Tower-1

Tower-2

100%completed

100%completed

 
02 Basement work Tower-1

Tower-2

100%completed

100%completed

 

 
03 Super Structure Tower-1

Tower-2

1st floor roof slab completed

Gr. Floor column work is ongoing

 

 
04 Block Work      
05 Electrical conduiting work      
06 Door frame fitting work      
07 Sanitary & plumbing line work      
08 In side Plastering work      
09 Electrical cable wiring work      
10 Wall tiles work      
11 Common sanitary & Plumbing line work      
12 Outside plastering work      
13 Floor tiles/Marble work      
14 L.C.C work      
15 Grill & Railing work      
16 Inside paint & Polishing work      
17 Switch -Socket fitting work      
18 Outside paint work      
19 Door shutter work      
20 Aluminum work      
21 Tiles Pointing work & Marble finishing work      
22 Commode – Basin fitting work and C.P fittings work      
23 Lift/Generator /Substation /Solar work      
24 Boundary wall /Ground floor development work      
25 Roof top finishing work      
26 Roof top Gardening work G.F Garden work      