Expected Completion Date
October 2028
Status Updated
April, 2026
| SL. No | Name of the work | Location | Progress details | Remarks |
| 01 | Foundation work | 100% completed | ||
| 02 | Super Structure work | 65% completed | ||
| 03 | Block Work | Apartment =T1A2
Apartment =T1B2 Apartment =T1C2 Apartment =T1D2 Apartment =T1A3 Apartment =T1B3 Apartment =T1C3 Apartment =T1D3 Apartment =T1A4 Apartment =T1B4 Apartment =T1C4 Apartment =T1D4 Apartment =T2A2 Apartment =T2B2 Apartment =T2C2 Apartment =T2D2 Apartment =T2A3 Apartment =T2B3 Apartment =T2C3 Apartment =T2D3 Apartment =T2A4 Apartment =T2B4 Apartment =T2C4 Apartment =T2D4 Apartment =T2A5 Apartment =T2B5 Apartment =T2C5 Apartment =T2D5 |
70% Complete
70% Complete 70% Complete 70% Complete 70% Complete 70% Complete 70% Complete 70% Complete 40% Complete 40% Complete 40% Complete 40% Complete 70% Complete 70% Complete 70% Complete 70% Complete 70% Complete 70% Complete 70% Complete 70% Complete 65% Complete 65% Complete 65% Complete 65% Complete 60% Complete 60% Complete 60% Complete 60% Complete |
|
| 04 | Electrical conduiting work | Apartment =T1A2
Apartment =T1B2 Apartment =T1C2 Apartment =T1D2 Apartment =T1A3 Apartment =T1B3 Apartment =T1C3 Apartment =T1D3 Apartment =T2A2 Apartment =T2B2 Apartment =T2C2 Apartment =T2D2 Apartment =T2A3 Apartment =T2B3 Apartment =T2C3 Apartment =T2D3 Apartment =T2A4 Apartment =T2B4 Apartment =T2C4 Apartment =T2D4 |
50% Complete
50% Complete 50% Complete 50% Complete 50% Complete 50% Complete 50% Complete 50% Complete 45% Complete 45% Complete 45% Complete 45% Complete 40% Complete 40% Complete 40% Complete 40% Complete 45% Complete 45% Complete 45% Complete 45% Complete |
|
| 05 | Door frame fitting work | |||
| 06 | Sanitary & plumbing line work | |||
| 07 | In side Plastering work | Apartment =T1A2
Apartment =T1B2 Apartment =T1C2 Apartment =T1D2 Apartment =T1A3 Apartment =T1B3 Apartment =T1C3 Apartment =T1D3 Apartment =T2A2 Apartment =T2B2 Apartment =T2C2 Apartment =T2D2 Apartment =T2A3 Apartment =T2B3 Apartment =T2C3 Apartment =T2D3 Apartment =T2A4 Apartment =T2B4 Apartment =T2C4 Apartment =T2D4 |
30% Complete
30% Complete 30% Complete 30% Complete 30% Complete 30% Complete 30% Complete 30% Complete 30% Complete 30% Complete 30% Complete 30% Complete 30% Complete 30% Complete 30% Complete 30% Complete 30% Complete 30% Complete 30% Complete 30% Complete |
|
| 08 | Electrical cable wiring work | |||
| 09 | Wall tiles work | |||
| 10 | Common sanitary & Plumbing line work | |||
| 11 | Outside plastering work | |||
| 12 | Floor tiles/Marble work | |||
| 13 | L.C.C work | |||
| 14 | Grill & Railing work | |||
| 15 | Inside paint & Polishing work | |||
| 16 | Switch -Socket fitting work | |||
| 17 | Outside paint work | |||
| 18 | Door shutter work | |||
| 19 | Aluminum work | |||
| 20 | Tiles Pointing work & Marble finishing work | |||
| 21 | Commode-Basin fitting work and CP fittings work | |||
| 22 | Lift/Generator /Substation /Solar work | |||
| 23 | Boundary wall /Ground floor development work | |||
| 24 | Roof top finishing work | |||
| 25 | Roof top Gardening work G.F Garden work |