Lakeside Serenade

Uttara, Dhaka

Expected Completion Date

April 2027

Status Updated

September, 2025

SL. No Name of the work Progress details
01 Foundation work 100% completed. Pile work completed. Pile Cap work completed, Grade beam completed.
02 Super Structure work 88.89 % Completed. (Ground Floor Roof Slab 100% Completed. 1F Roof Slab 100% completed, 2F Roof Slab 100% completed, 3F Roof Slab 100% completed. 4F roof slab 100% completed, 5th floor roof slab 100% completed, 6th Floor Roof Slab 100% Completed. 7th floor roof slab 100% completed.)
03 Block Work 30% Completed
04 Electrical conducting work 20% completed
05 Door frame fitting work Not yet started.
06 Sanitary & plumbing line work Not yet started.
07 In side Plastering work 20% Completed (Ceiling).
08 Electrical cable wiring work Not yet started.
09 Wall tiles& floor tiles work Not yet started.
10 Common sanitary & Plumbing line work Not yet started.
11 Outside plastering work Not yet started.
12 Floor tiles/Marble work Not yet started.
13 L.C.C work Not yet started.
14 Grill & Railing work Not yet started.
15 Inside paint & Polishing work Not yet started.
16 Switch -Socket fitting work Not yet started.
17 Outside paint work Not yet started.
18 Door shutter work Not yet started.
19 Aluminum/Glazing work Not yet started.
20 Tiles Pointing work & Marble finishing work Not yet started.
21 Commode – Basin fitting work and C.P fittings work Not yet started.
22 Lift/Generator /Substation /Solar work Not yet started.
23 Boundary wall /Ground floor development work 65% Completed.
24 Roof top finishing work Not yet started.
25 Roof top Gardening work Not yet started.
26 Gardening work Not yet started.
27 Artificial fair face Not yet started.
28 Kitchen ver. Railing Not yet started.
29 Outside AC lover Not yet started.
30 Fire work Not yet started.
31 Pavement tiles Not yet started.
32 Pvc false ceiling works Not yet started.