bti Celebration Point

Plot: 3 & 5, Road: 113/A, Gulshan-2, Dhaka-1212

Magenta

Bashundhara R/A, Dhaka
Expected Completion Date May 2026
Status Updated April, 2026
Back to all projects
Magenta

Construction progress details

The progress table comes directly from the WordPress post content.

SL. No Name of the work Progress details
01 Foundation work Foundation 100% completed
02 Super Structure work 100%
03 Block Work A1 = 100%, A2=100%,A3= 100%,A4=100% ,A5= 100%,A6= 100%
04 Electrical conducting work A1 = 100%, A2=100%,A3= 100%, A3= 100%, A4= 100%, A5= 100%, A6= 100%,
05 Door frame fitting work A1 = 100%, A2=100%, A3 = 100%, A4=100%, A5 = 100%, A6 = 100%,
06 Sanitary & plumbing line work 70%
07 In side Plastering work A1 = 100%, A2=100%, A3 = 100%, A4=100%, A5 = 100%,
08 Electrical cable wiring work 100%
09 Wall tiles work 90%
10 Common sanitary & Plumbing line work 60%
11 Outside plastering work 90%
12 Floor tiles/Marble work 90%
13 L.C.C work 100%
14 Grill & Railing work 80%
15 Inside paint & Polishing work 80%
16 Switch -Socket fitting work 90%
17 Outside paint work 50%
18 Door shutter work 80%
19 Aluminum work 90%
20 Tiles Pointing work & Marble finishing work N/A
21 Commode – Basin fitting work and C.P fittings work N/A
22 Lift/Generator /Substation /Solar work N/A
23 Boundary wall /Ground floor development work 90%
24 Roof top finishing work

 

90%
25 Roof top Gardening work G.F Garden work N/A

 