Expected Completion Date
October 2027
Status Updated
September, 2025
| SL. No | Name of the work | Progress details |
| 01 | Foundation work | Foundation 100% completed, Basement -2, 100% completed, Basement 1 Roof slab 100% completed. |
| 02 | Super Structure work | 86 % Completed. (GF roof slab 100% completed, 1F roof slab 100% completed, 2F roof slab 100% completed, 3F roof slab 100% completed, 4F roof slab 100% completed, 5F roof slab 100% completed, 6F roof slab 100% completed, 7th floor roof slab completed. 8th floor roof slab 100% completed, 9th floor roof slab 100% completed. 10F roof slab 100% completed, 11th floor roof slab 100% completed.) |
| 03 | Block Work | Fixing 23% completed. |
| 04 | Electrical conduiting work | 5 % Completed. |
| 05 | Door frame fitting work | Not yet started. |
| 06 | Sanitary & plumbing line work. | Not yet started. |
| 07 | In side Plastering work | 22% completed. |
| 08 | Electrical cable wiring work | Not yet started. |
| 09 | Wall tiles work | Not yet started. |
| 10 | Common sanitary & Plumbing line work | Not yet started. |
| 11 | Outside plastering work | Not yet started. |
| 12 | Floor tiles/Marble work | Not yet started. |
| 13 | L.C.C work | Not yet started. |
| 14 | Grill & Railing work | Not yet started. |
| 15 | Inside paint & Polishing work | Not yet started. |
| 16 | Switch -Socket fitting work | Not yet started. |
| 17 | Outside paint work | Not yet started. |
| 18 | Door shutter work | Not yet started. |
| 19 | Aluminum/Glazing work | Not yet started. |
| 20 | Tiles Pointing work & Marble finishing work | Not yet started. |
| 21 | Commode – Basin fitting work and C.P fittings work | Not yet started. |
| 22 | Lift/Generator /Substation /Solar work | Not yet started. |
| 23 | Boundary wall /Ground floor development work | Not yet started. |
| 24 | Roof top finishing work | Not yet started. |
| 25 | Roof top Gardening work | Not yet started. |