Magnifico

Gulshan, Dhaka

Expected Completion Date

October 2027

Status Updated

January, 2025

SL. No Name of the work Progress details
01 Foundation work Foundation 100% completed, Basement -2, 100% completed, Basement 1 Roof slab 100% completed.
02 Super Structure work 43% completed. 5th floor roof slab casting completed.
03 Block Work
04 Electrical conduiting work
05 Door frame fitting work
06 Sanitary & plumbing line work.
07 In side Plastering work
08 Electrical cable wiring work
09 Wall tiles work
10 Common sanitary & Plumbing line work
11 Outside plastering work
12 Floor tiles/Marble work
13 L.C.C work
14 Grill & Railing work
15 Inside paint & Polishing work
16 Switch -Socket fitting work
17 Outside paint work
18 Door shutter work
19 Aluminum/Glazing work
20 Tiles Pointing work & Marble finishing work
21 Commode – Basin fitting work and C.P fittings work
22 Lift/Generator /Substation /Solar work
23 Boundary wall /Ground floor development work
24 Roof top finishing work
25 Roof top Gardening work