Magnifico

Gulshan, Dhaka

Expected Completion Date

October 2027

Status Updated

January, 2026

SL. No Name of the work Progress details
01 Foundation work Footing 100% completed,
02 Super Structure work Up to 13th floor roof slab 100% done. OHWT RCC work 80%, Parapet wall 60% done.
03 Block Work A1- 10%, B1-10%, A2- 80%, B2-80%, A3-80%, B3-80%, A4-80%, B4-80%, A5-10%, B5-80%, A6-30 %, B6-80%, A7-70%, B7-80%, A9-10%, B9-10%, A10-10%, B10-10%, A11-10%, B11-10%,
04 Electrical conduiting work A3-80%, B3-80%, A4-80%, B4-80%,
05 Door frame fitting work  
06 Sanitary & plumbing line work. Vertical duct (9 no’s) line 50% done
07 In side Plastering work Ceiling plaster, Basement to 12th floor 85% complete.
08 Electrical cable wiring work  
09 Wall tiles work  
10 Common sanitary & Plumbing line work  
11 Outside plastering work  
12 Floor tiles/Marble work  
13 L.C.C work  
14 Grill & Railing work  
15 Inside paint & Polishing work  
16 Switch -Socket fitting work  
17 Outside paint work  
18 Door shutter work  
19 Aluminum/Glazing work  
20 Tiles Pointing work & Marble finishing work  
21 Commode – Basin fitting work and C.P fittings work  
22 Lift/Generator /Substation /Solar work  
23 Boundary wall /Ground floor development work  
24 Roof top finishing work  
25 Roof top Gardening work  

 