Magnifico

Gulshan, Dhaka

Expected Completion Date

October 2027

Status Updated

December, 2025

SL. No Name of the work Progress details
01 Foundation work Footing 100% completed,
02 Super Structure work Up to 13th floor roof slab 100% done.
03 Block Work A1- 10%, B1-10%, A2- 80%, B2-80%, A3-80%, B3-80%, A4-80%, B4-80%, A5-10%, B5-80%, A6-80%, B6-80%, A7-70%, B7-80%, A9-30%, B9-35%, A10-20%, B10-20%, A11-20%, B11-20%,
04 Electrical conduiting work 12% Completed
05 Door frame fitting work Not Yet Started.
06 Sanitary & plumbing line work. 10% Completed
07 In side Plastering work Ceiling plaster, Basement to 12th floor 80% complete.
08 Electrical cable wiring work Not Yet Started.
09 Wall tiles work Not Yet Started.
10 Common sanitary & Plumbing line work Not Yet Started.
11 Outside plastering work Not Yet Started.
12 Floor tiles/Marble work Not Yet Started.
13 L.C.C work Not Yet Started.
14 Grill & Railing work Not Yet Started.
15 Inside paint & Polishing work Not Yet Started.
16 Switch -Socket fitting work Not Yet Started.
17 Outside paint work Not Yet Started.
18 Door shutter work Not Yet Started.
19 Aluminum/Glazing work Not Yet Started.
20 Tiles Pointing work & Marble finishing work Not Yet Started.
21 Commode – Basin fitting work and C.P fittings work Not Yet Started.
22 Lift/Generator /Substation /Solar work Not Yet Started.
23 Boundary wall /Ground floor development work Not Yet Started.
24 Roof top finishing work Not Yet Started.
25 Roof top Gardening work Not Yet Started.

16604