Magnifico

Gulshan, Dhaka

Expected Completion Date

October 2027

Status Updated

February, 2026

SL. No Name of the work Progress details
01 Foundation work Footing 100% completed,
02 Super Structure work Up to 13th floor roof slab 100% done. OHWT RCC work 90%, Parapet wall 90% done.
03 Block Work A1- 10%, B1-10%, A2- 80%, B2-80%, A3-80%, B3-80%, A4-80%, B4-80%, A5-10%, B5-80%, A6-30 %, B6-80%, A7-70%, B7-80%, A9-60%, B9-80%, A10-50%, B10-50%, A11-10%, B11-10%,
04 Electrical conduiting work A3-80%, B3-80%, A4-80%, B4-80%,
05 Door frame fitting work 10% Completed
06 Sanitary & plumbing line work. Vertical duct (9 no’s) line 80% done
07 In side Plastering work Ceiling plaster, Basement to 13th floor 85% complete.
08 Electrical cable wiring work Not Yet Started
09 Wall tiles work Not Yet Started
10 Common sanitary & Plumbing line work Not Yet Started
11 Outside plastering work Not Yet Started
12 Floor tiles/Marble work Not Yet Started
13 L.C.C work Not Yet Started
14 Grill & Railing work Not Yet Started
15 Inside paint & Polishing work Not Yet Started
16 Switch -Socket fitting work Not Yet Started
17 Outside paint work Not Yet Started
18 Door shutter work Not Yet Started
19 Aluminum/Glazing work Not Yet Started
20 Tiles Pointing work & Marble finishing work Not Yet Started
21 Commode – Basin fitting work and C.P fittings work Not Yet Started
22 Lift/Generator /Substation /Solar work Not Yet Started
23 Boundary wall /Ground floor development work Not Yet Started
24 Roof top finishing work Not Yet Started
25 Roof top Gardening work Not Yet Started

16604