Magnifico

Gulshan, Dhaka

Expected Completion Date

October 2027

Status Updated

June, 2025

SL. No Name of the work Progress details
01 Foundation work Foundation 100% completed, Basement -2, 100% completed, Basement 1 Roof slab 100% completed.
02 Super Structure work 71 % Completed. (GF roof slab 100% completed, 1F roof slab 100% completed, 2F roof slab 100% completed, 3F roof slab 100% completed, 4F roof slab 100% completed, 5F roof slab 100% completed, 6F roof slab 100% completed, 7th floor roof slab completed. 8th floor roof slab 100% completed, 9th floor roof slab 100% completed. 10F roof slab 30 % completed)
03 Block Work Panel casting going on.
04 Electrical conduiting work Not yet started.
05 Door frame fitting work Not yet started.
06 Sanitary & plumbing line work. Not yet started.
07 In side Plastering work 20% completed.
08 Electrical cable wiring work Not yet started.
09 Wall tiles work Not yet started.
10 Common sanitary & Plumbing line work Not yet started.
11 Outside plastering work Not yet started.
12 Floor tiles/Marble work Not yet started.
13 L.C.C work Not yet started.
14 Grill & Railing work Not yet started.
15 Inside paint & Polishing work Not yet started.
16 Switch -Socket fitting work Not yet started.
17 Outside paint work Not yet started.
18 Door shutter work Not yet started.
19 Aluminum/Glazing work Not yet started.
20 Tiles Pointing work & Marble finishing work Not yet started.
21 Commode – Basin fitting work and C.P fittings work Not yet started.
22 Lift/Generator /Substation /Solar work Not yet started.
23 Boundary wall /Ground floor development work Not yet started.
24 Roof top finishing work Not yet started.
25 Roof top Gardening work Not yet started.