Magnifico

Gulshan, Dhaka

Expected Completion Date

October 2027

Status Updated

March, 2026

SL. No Name of the work Progress details
01 Foundation work Footing 100% completed,
02 Super Structure work Up to 13th floor roof slab 100% done. OHWT RCC work 100%, Parapet wall 90 % done. Swimming pool RCC Work 90 % done
03 Block Work A1- 10%, B1-10%, A2- 90%, B2-90%, A3-90%, B3-90%, A4-90%, B4-90%, A5-10%, B5-90%, A6-30 %, B6-90%, A7-90%, B7-90 %, A8 -80%, B8-80%, A9-80%, B9-80%, A10-70%, B10-70%, A11-10%, B11-10%,
04 Electrical conduiting work A3-90%, B3-90%, A4-90%, B4-90%, A5-10%, B5-90%, A6-30 %, B6-90%
05 Door frame fitting work A3-60%, B3-

60%, A4-50%, B4-50%,

06 Sanitary & plumbing line work. Vertical duct (9 no’s) line 80% done
07 In side Plastering work Ceiling plaster, Basement to 13th floor 85% complete.
08 Electrical cable wiring work  
09 Wall tiles work  
10 Common sanitary & Plumbing line work  
11 Outside plastering work  
12 Floor tiles/Marble work  
13 L.C.C work  
14 Grill & Railing work  
15 Inside paint & Polishing work  
16 Switch -Socket fitting work  
17 Outside paint work  
18 Door shutter work  
19 Aluminum/Glazing work  
20 Tiles Pointing work & Marble finishing work  
21 Commode – Basin fitting work and C.P fittings work  
22 Lift/Generator /Substation /Solar work  
23 Boundary wall /Ground floor development work  
24 Roof top finishing work  
25 Roof top Gardening work  