bti Celebration Point

Plot: 3 & 5, Road: 113/A, Gulshan-2, Dhaka-1212

Magnifico

Gulshan, Dhaka
Expected Completion Date October 2027
Status Updated April, 2026
Back to all projects
Magnifico

Construction progress details

The progress table comes directly from the WordPress post content.

SL. No Name of the work Progress details
01 Foundation work Footing 100% completed,
02 Super Structure work Up to 13th floor roof slab 100% done. OHWT RCC work 100%, Parapet wall 90 % done. Swimming pool RCC Work 90 % done
03 Block Work A1- 10%, B1-10%, A2- 90%, B2-90%, A3-90%, B3-90%, A4-90%, B4-90%, A5-10%, B5-90%, A6-30 %, B6-90%, A7-90%, B7-90 %, A8 -80%, B8-80%, A9-80%, B9-80%, A10-70%, B10-70%, A11-10%, B11-10%,
04 Electrical conduiting work A3-90%, B3-90%, A4-90%, B4-90%, A5-10%, B5-90%, A6-30 %, B6-90%
05 Door frame fitting work A3-60%, B3-

60%, A4-50%, B4-50%,

06 Sanitary & plumbing line work. Vertical duct (9 no’s) line 80% done
07 In side Plastering work Ceiling plaster, Basement to 13th floor 85% complete.
08 Electrical cable wiring work  
09 Wall tiles work  
10 Common sanitary & Plumbing line work  
11 Outside plastering work  
12 Floor tiles/Marble work  
13 L.C.C work  
14 Grill & Railing work  
15 Inside paint & Polishing work  
16 Switch -Socket fitting work  
17 Outside paint work  
18 Door shutter work  
19 Aluminum/Glazing work  
20 Tiles Pointing work & Marble finishing work  
21 Commode – Basin fitting work and C.P fittings work  
22 Lift/Generator /Substation /Solar work  
23 Boundary wall /Ground floor development work  
24 Roof top finishing work  
25 Roof top Gardening work  

 