Meadow View

Bashundhara R/A, Dhaka
Expected Completion Date December 2026
Status Updated October, 2025
Back to all projects
Meadow View

Construction progress details

The progress table comes directly from the WordPress post content.

SL. No Name of the work Progress details
01 Foundation work 100% completed.
02 Super Structure work 100%
03 Block Work A-2= 100%, A-3= 100%, A-4 = 100%, A-5 = 100%, A-6 = 100%, A-7 =100%, A-8= 90%, A-9= 90%,

B-2=100%, B-3=100%, B-4=100% , B-5=100%, B-6=100%, B-7=100%, B-8= 100% , B-9= 100%

04 Electrical conducting work Over All 90%
05 Door frame fitting work A-2= 100%, B-2=100%, A-3= 100%, B-3=100%, A-4 = 100%, A-5 = 100%, A-6= 100%,  A- 7= 100%, A-8= 100%, A-9= 100%,

B-4=100% , B-5=100%, A-6= 100%, A-7 = 100%, B-6=100%, B-7=100%, B-8= 100% , B-9= 100%

06 Sanitary & plumbing line work N/A
07 In side Plastering work A-2= 100% , B-2=100%, A-3= 100% , B-3=100%, A-4= 100% , A-5 = 100%, B-5 = 100% A-6 = 100%, B-6 = 100%, A-7=100%, B-7= 100%, A- 8= 100%, B-8= 100%, A-9= 100%, B-9= 100%
08 Electrical cable wiring work 100%
09 Wall tiles work A-2= 100%, B-2=100%, A-3= 100%, B-3=100%, A-4 = 100%, A-5 = 100%, A-6= 100%,  A- 7= 100%, A-8= 100%, A-9= 100%,

B-4=100% , B-5=100%, A-6= 100%, A-7 = 100%, B-6=100%, B-7=100%, B-8= 100% , B-9= 100%

10 Common sanitary & Plumbing line work N/A
11 Outside plastering work 100%
12 Floor tiles/Marble work 100%
13 L.C.C work 100%
14 Grill & Railing work 100%
15 Inside paint & Polishing work 90%
16 Switch -Socket fitting work N/A
17 Outside paint work 90%
18 Door shutter work 100%
19 Aluminum work 100%
20 Tiles Pointing work & Marble finishing work N/A
21 Commode – Basin fitting work and C.P fittings work N/A
22 Lift/Generator /Substation /Solar work N/A
23 Boundary wall /Ground floor development work 95%
24 Roof top finishing work 100%
25 Roof top Gardening work G.F Garden work N/A