Completion Date
June 2025
Status Updated
March, 2024
SL. No | Name of the work | Progress details |
01 | Foundation work | 100% completed. |
02 | Super Structure work | 90% |
03 | Block Work | A-2= 100%, A-3= 100%, A-4 = 100%, A-5 = 100%, A-6 = 80%, A-7 =70%
B-2=100%, B-3=100%, B-4=100% , B-5=100%, B-6=80%, B-7=70% |
04 | Electrical conducting work | Over All 30% |
05 | Door frame fitting work | A-2= 100%, B-2=100%, A-3= 100%, B-3=100%, A-4 = 100%, A-5 = 100%, B-4=100% , B-5=100%, |
06 | Sanitary & plumbing line work | N/A |
07 | In side Plastering work | A-2= 100% , B-2=100%, A-3= 100% , B-3=80%, A-4= 100% , A-5 = 50%, B-5 = 100% |
08 | Electrical cable wiring work | N/A |
09 | Wall tiles work | N/A |
10 | Common sanitary & Plumbing line work | N/A |
11 | Outside plastering work | N/A |
12 | Floor tiles/Marble work | N/A |
13 | L.C.C work | N/A |
14 | Grill & Railing work | N/A |
15 | Inside paint & Polishing work | N/A |
16 | Switch -Socket fitting work | N/A |
17 | Outside paint work | N/A |
18 | Door shutter work | N/A |
19 | Aluminum work | N/A |
20 | Tiles Pointing work & Marble finishing work | N/A |
21 | Commode – Basin fitting work and C.P fittings work | N/A |
22 | Lift/Generator /Substation /Solar work | N/A |
23 | Boundary wall /Ground floor development work | N/A |
24 | Roof top finishing work | N/A |
25 | Roof top Gardening work G.F Garden work | N/A |