Meadow View

Bashundhara R/A, Dhaka

Completion Date

June 2025

Status Updated

March, 2024

SL. No Name of the work Progress details
01 Foundation work 100% completed.
02 Super Structure work 90%
03 Block Work A-2= 100%, A-3= 100%, A-4 = 100%, A-5 = 100%, A-6 = 80%, A-7 =70%

B-2=100%, B-3=100%, B-4=100% , B-5=100%, B-6=80%, B-7=70%

04 Electrical conducting work Over All 30%
05 Door frame fitting work A-2= 100%, B-2=100%, A-3= 100%, B-3=100%, A-4 = 100%, A-5 = 100%, B-4=100% , B-5=100%,
06 Sanitary & plumbing line work N/A
07 In side Plastering work A-2= 100% , B-2=100%, A-3= 100% , B-3=80%, A-4= 100% , A-5 = 50%, B-5 = 100%
08 Electrical cable wiring work N/A
09 Wall tiles work N/A
10 Common sanitary & Plumbing line work N/A
11 Outside plastering work N/A
12 Floor tiles/Marble work N/A
13 L.C.C work N/A
14 Grill & Railing work N/A
15 Inside paint & Polishing work N/A
16 Switch -Socket fitting work N/A
17 Outside paint work N/A
18 Door shutter work N/A
19 Aluminum work N/A
20 Tiles Pointing work & Marble finishing work N/A
21 Commode – Basin fitting work and C.P fittings work N/A
22 Lift/Generator /Substation /Solar work N/A
23 Boundary wall /Ground floor development work N/A
24 Roof top finishing work N/A
25 Roof top Gardening work G.F Garden work N/A