Expected Completion Date
March 2025
Status Updated
February, 2025
SL. No | Name of the work | Progress details |
Foundation work | 100% Completed | |
Super Structure work | 98% completed | |
Block work | A-1=100%, A-2=100%, A-3=100%, A-4=100%, A-5=100%, A-6=100%, A-7=100% | |
Electrical conduit work | A-1=100%, A-2=100%, A-3=100%, A-4=100% A-5=100%, A-6=100%, A-7=100% | |
Door frame fitting work | A-1=100%, A-2=100%, A-3=100%, A-4=100% A-5=100%, A-6=100%, A-7=100% | |
Sanitary & plumbing line work | A-1=50%, A-2=50%, A-3=80%, A-4=65% A-5=65%, A-6=80%, A-7=65% | |
In side Plastering work | A-1=100%, A-2=100%, A-3=100%, A-4=100% A-5=100%, A-6=100%, A- 7=100% | |
Electrical cable wiring work | 90% | |
Wall tiles work | 85% | |
Common sanitary & Plumbing line work | N/A | |
Outside plastering work | 95% | |
Floor tiles/Marble work | 90% | |
L.C.C work | 100% | |
Grill & Railing work | 90% | |
Inside paint & Polishing work | 50% | |
Switch -Socket fitting work | 20% | |
Outside paint work | 30% | |
Door shutter work | 40% | |
Aluminum/Glazing work | 50% | |
Tiles Pointing work & Marble finishing work | 20% | |
Commode – Basin fitting work and C.P fittings work | N/A | |
Lift/Generator /Substation /Solar work | 75% | |
Boundary wall /Ground floor development work | 75% | |
Roof top finishing work | 90% | |
Roof top Gardening work | 90% |