Montage

Block J, Bashundhara R/A

Expected Completion Date

June 2025

Status Updated

May, 2025

SL. No Name of the work Progress details
  Foundation work 100% Completed
  Super Structure work 100% completed
  Block work A-1=100%, A-2=100%, A-3=100%,           A-4=100%, A-5=100%, A-6=100%,                  A-7=100%
  Electrical conduit work A-1=100%, A-2=100%, A-3=100%,            A-4=100%  A-5=100%, A-6=100%,            A-7=100%
  Door frame fitting work A-1=100%, A-2=100%, A-3=100%,            A-4=100%  A-5=100%, A-6=100%,           A-7=100%
  Sanitary & plumbing line work A-1=60%, A-2=70%, A-3=100%, A-4=70%                   A-5=70%, A-6=100%, A-7=95%
  In side Plastering work A-1=100%, A-2=100%, A-3=100%, A-4=100% A-5=100%, A-6=100%, A-   7=100%
  Electrical cable wiring work 95%
  Wall tiles work 95%
  Common sanitary & Plumbing line work 45%
  Outside plastering work 95%
  Floor tiles/Marble work 100%
  L.C.C work 100%
  Grill & Railing work 95%
  Inside paint & Polishing work 85%
  Switch -Socket fitting work 85%
  Outside paint work 50%
  Door shutter work 90%
  Aluminum/Glazing work 90%
  Tiles Pointing work & Marble finishing work 70%
  Commode – Basin fitting work and C.P fittings work 45%
  Lift/Generator /Substation /Solar work 80%
  Boundary wall /Ground floor development work 90%
  Roof top finishing work 100%
  Roof top Gardening work 95%

 

16604