Montage

Bashundhara R/A, Dhaka

Expected Completion Date

March 2025

Status Updated

February, 2025

SL. No Name of the work Progress details
  Foundation work 100% Completed
  Super Structure work 98% completed
  Block work A-1=100%, A-2=100%, A-3=100%,           A-4=100%, A-5=100%, A-6=100%,                  A-7=100%
  Electrical conduit work A-1=100%, A-2=100%, A-3=100%,            A-4=100%  A-5=100%, A-6=100%,            A-7=100%
  Door frame fitting work A-1=100%, A-2=100%, A-3=100%,            A-4=100%  A-5=100%, A-6=100%,           A-7=100%
  Sanitary & plumbing line work A-1=50%, A-2=50%, A-3=80%, A-4=65%                   A-5=65%, A-6=80%, A-7=65%
  In side Plastering work A-1=100%, A-2=100%, A-3=100%, A-4=100% A-5=100%, A-6=100%, A-   7=100%
  Electrical cable wiring work 90%
  Wall tiles work 85%
  Common sanitary & Plumbing line work N/A
  Outside plastering work 95%
  Floor tiles/Marble work 90%
  L.C.C work 100%
  Grill & Railing work 90%
  Inside paint & Polishing work 50%
  Switch -Socket fitting work 20%
  Outside paint work 30%
  Door shutter work 40%
  Aluminum/Glazing work 50%
  Tiles Pointing work & Marble finishing work 20%
  Commode – Basin fitting work and C.P fittings work N/A
  Lift/Generator /Substation /Solar work 75%
  Boundary wall /Ground floor development work 75%
  Roof top finishing work 90%
  Roof top Gardening work 90%

 