Montage

Bashundhara R/A, Dhaka

Completion Date

November 2024

Status Updated

February, 2024

SL. No Name of the work Progress details
  Foundation work 100% Completed
  Super Structure work 95% completed
  Block work A-1=95%, A-2=95%, A-3=80%, A-4=80%, A-5=85%, A-6=45%, A-7=00%
  Electrical conduit work A-1=90%, A-2=70%, A-3=70%, A-4=70%                   A-5=50%, A-6=50%, A-7=00%
  Door frame fitting work A-1=80%, A-2=70%, A-3=00%, A-4=50%                   A-5=00%, A-6=00%, A-7=00%
  Sanitary & plumbing line work A-1=30%, A-2=30%, A-3=25%, A-4=30%                   A-5=25%, A-6=25%, A-7=25%
  In side Plastering work A-1=90%, A-2=20%, A-3=00%, A-4=00%                   A-5=00%, A-6=00%, A-7=00%
  Electrical cable wiring work N/A
  Wall tiles work N/A
  Common sanitary & Plumbing line work N/A
  Outside plastering work N/A
  Floor tiles/Marble work N/A
  L.C.C work N/A
  Grill & Railing work N/A
  Inside paint & Polishing work N/A
  Switch -Socket fitting work N/A
  Outside paint work N/A
  Door shutter work N/A
  Aluminum/Glazing work N/A
  Tiles Pointing work & Marble finishing work N/A
  Commode – Basin fitting work and C.P fittings work N/A
  Lift/Generator /Substation /Solar work N/A
  Boundary wall /Ground floor development work N/A
  Roof top finishing work N/A
  Roof top Gardening work N/A