Montage

Bashundhara R/A, Dhaka
Expected Completion Date August 2025
Status Updated September, 2025
Back to all projects
Montage

Construction progress details

The progress table comes directly from the WordPress post content.

SL. No Name of the work Progress details
  Foundation work 100% Completed
  Super Structure work 100% completed
  Block work A-1=100%, A-2=100%, A-3=100%,           A-4=100%, A-5=100%, A-6=100%,                  A-7=100%
  Electrical conduit work A-1=100%, A-2=100%, A-3=100%,            A-4=100%  A-5=100%, A-6=100%,            A-7=100%
  Door frame fitting work A-1=100%, A-2=100%, A-3=100%,            A-4=100%  A-5=100%, A-6=100%,           A-7=100%
  Sanitary & plumbing line work A-1=100%, A-2=100%, A-3=100%, A-4=100%  A-5=100%, A-6=100%, A-7=100%
  In side Plastering work A-1=100%, A-2=100%, A-3=100%, A-4=100% A-5=100%, A-6=100%, A-   7=100%
  Electrical cable wiring work 100%
  Wall tiles work 100%
  Common sanitary & Plumbing line work 100%
  Outside plastering work 100%
  Floor tiles/Marble work 100%
  L.C.C work 100%
  Grill & Railing work 100%
  Inside paint & Polishing work 100%
  Switch -Socket fitting work 100%
  Outside paint work 95%
  Door shutter work 100%
  Aluminum/Glazing work 100%
  Tiles Pointing work & Marble finishing work 98%
  Commode – Basin fitting work and C.P fittings work 100%
  Lift/Generator /Substation /Solar work 100%
  Boundary wall /Ground floor development work 100%
  Roof top finishing work 100%
  Roof top Gardening work 100%