Completion Date
November 2024
Status Updated
February, 2024
SL. No | Name of the work | Progress details |
Foundation work | 100% Completed | |
Super Structure work | 95% completed | |
Block work | A-1=95%, A-2=95%, A-3=80%, A-4=80%, A-5=85%, A-6=45%, A-7=00% | |
Electrical conduit work | A-1=90%, A-2=70%, A-3=70%, A-4=70% A-5=50%, A-6=50%, A-7=00% | |
Door frame fitting work | A-1=80%, A-2=70%, A-3=00%, A-4=50% A-5=00%, A-6=00%, A-7=00% | |
Sanitary & plumbing line work | A-1=30%, A-2=30%, A-3=25%, A-4=30% A-5=25%, A-6=25%, A-7=25% | |
In side Plastering work | A-1=90%, A-2=20%, A-3=00%, A-4=00% A-5=00%, A-6=00%, A-7=00% | |
Electrical cable wiring work | N/A | |
Wall tiles work | N/A | |
Common sanitary & Plumbing line work | N/A | |
Outside plastering work | N/A | |
Floor tiles/Marble work | N/A | |
L.C.C work | N/A | |
Grill & Railing work | N/A | |
Inside paint & Polishing work | N/A | |
Switch -Socket fitting work | N/A | |
Outside paint work | N/A | |
Door shutter work | N/A | |
Aluminum/Glazing work | N/A | |
Tiles Pointing work & Marble finishing work | N/A | |
Commode – Basin fitting work and C.P fittings work | N/A | |
Lift/Generator /Substation /Solar work | N/A | |
Boundary wall /Ground floor development work | N/A | |
Roof top finishing work | N/A | |
Roof top Gardening work | N/A |