Expected Completion Date
August 2025
Status Updated
March, 2025
S/N | Name of the work | Progress details | ||
Foundation work | 100% Completed | |||
Super Structure work | 98% completed | |||
Block work | A-1=98%
A-2=98% A-3=98% A-4=98% A-5=98% A-6=98%
|
|
|
|
Electrical conduit work | A-1=65%
A-2=65% A-3=65% A-4=65% A-5=65% A-6=50%
|
|
|
|
Door frame fitting work | A-1=100%
A-2=100% A-3=100% A-4=100% A-5=100% A-6=100%
|
|
||
Sanitary & plumbing line work | A-1=20%
A-2=25% A-3=25% A-4=25% A-5=25% A-6=25% |
|
||
In side Plastering work | A-1=90%
A-2=95% A-3=95% A-4=95% A-5=95% A-6=95%
|
|
||
Electrical cable wiring work | A-1=00%
A-2=00% A-3=00% A-4=00% A-5=00% A-6=00%
|
|||
Wall tiles work | A-1=00%
A-2=00% A-3=00% A-4=00% A-5=00% A-6=00%
|
|||
Floor tiles/Marble work | A-1=00%
A-2=00% A-3=00% A-4=00% A-5=00% A-6=00%
|
|||
Outside plastering work | 50% | |||
Common sanitary & Plumbing line work | 30% | |||
L.C.C work | 00% | |||
Grill & Railing work | A-1=00%
A-2=00% A-3=00% A-4=00% A-5=00% A-6=00%
|
|||
Inside paint & Polishing work |
00% |
|||
Switch -Socket fitting work | 00% | |||
Outside paint work | 00% | |||
Door shutter work | 00% | |||
Aluminum/Glazing work | 00% | |||
Tiles Pointing work & Marble finishing work | 00% | |||
Commode – Basin fitting work and C.P fittings work | 00% | |||
Lift/Generator /Substation /Solar work | 00% | |||
Boundary wall /Ground floor development work | 00% | |||
Roof top finishing work | 00% | |||
Roof top Gardening work | 30% |
16604