Expected Completion Date
December 2025
Status Updated
September, 2025
| SL. No | Name of the work | Progress details | ||
| Foundation work | 100% Completed | |||
| Super Structure work | 98% completed | |||
| Block work | A-1=100%
A-2=100% A-3=100% A-4=100% A-5=100% A-6=100%
|
|
|
|
| Electrical conduit work | A-1=100%
A-2=100% A-3=100% A-4=100% A-5=100% A-6=100%
|
|
|
|
| Door frame fitting work | A-1=100%
A-2=100% A-3=100% A-4=100% A-5=100% A-6=100%
|
|
||
| Sanitary & plumbing line work | A-1=95%
A-2=95% A-3=90% A-4=95% A-5=95% A-6=95% |
|
||
| In side Plastering work | A-1=100%
A-2=100% A-3=100% A-4=100% A-5=100% A-6=100%
|
|
||
| Electrical cable wiring work | A-1=100%
A-2=100% A-3=100% A-4=100% A-5=100% A-6=100%
|
|||
| Wall tiles work | A-1=80%
A-2=70% A-3=80% A-4=80% A-5=70% A-6=70%
|
|||
| Floor tiles/Marble work | A-1=90%
A-2=90% A-3=90% A-4=90% A-5=90% A-6=90%
|
|||
| Outside plastering work | 100% | |||
| Common sanitary & Plumbing line work | 60% | |||
| L.C.C work | 00% | |||
| Grill & Railing work | A-1=100%
A-2=100% A-3=90% A-4=90% A-5=90% A-6=90%
|
|||
| Inside paint & Polishing work |
00% |
|||
| Switch -Socket fitting work | 00% | |||
| Outside paint work | 00% | |||
| Door shutter work | 00% | |||
| Aluminum/Glazing work | 00% | |||
| Tiles Pointing work & Marble finishing work | 30% | |||
| Commode – Basin fitting work and C.P fittings work | 00% | |||
| Lift/Generator /Substation /Solar work | 00% | |||
| Boundary wall /Ground floor development work | 00% | |||
| Roof top finishing work | 60% | |||
| Roof top Gardening work | 50% | |||