Expected Completion Date
August 2025
Status Updated
May, 2025
SL. No | Name of the work | Progress details | ||
Foundation work | 100% Completed | |||
Super Structure work | 98% completed | |||
Block work | A-1=100%
A-2=100% A-3=100% A-4=100% A-5=100% A-6=100%
|
|
|
|
Electrical conduit work | A-1=100%
A-2=100% A-3=100% A-4=100% A-5=85% A-6=80%
|
|
|
|
Door frame fitting work | A-1=100%
A-2=100% A-3=100% A-4=100% A-5=100% A-6=100%
|
|
||
Sanitary & plumbing line work | A-1=90%
A-2=90% A-3=90% A-4=90% A-5=55% A-6=50% |
|
||
In side Plastering work | A-1=100%
A-2=100% A-3=100% A-4=100% A-5=100% A-6=100%
|
|
||
Electrical cable wiring work | A-1=100%
A-2=00% A-3=00% A-4=100% A-5=00% A-6=00%
|
|||
Wall tiles work | A-1=300%
A-2=30% A-3=30% A-4=30% A-5=30% A-6=30%
|
|||
Floor tiles/Marble work | A-1=80%
A-2=00% A-3=00% A-4=80% A-5=00% A-6=00%
|
|||
Outside plastering work | 70% | |||
Common sanitary & Plumbing line work | 60% | |||
L.C.C work | 00% | |||
Grill & Railing work | A-1=00%
A-2=00% A-3=00% A-4=00% A-5=00% A-6=00%
|
|||
Inside paint & Polishing work |
00% |
|||
Switch -Socket fitting work | 00% | |||
Outside paint work | 00% | |||
Door shutter work | 00% | |||
Aluminum/Glazing work | 00% | |||
Tiles Pointing work & Marble finishing work | 00% | |||
Commode – Basin fitting work and C.P fittings work | 00% | |||
Lift/Generator /Substation /Solar work | 00% | |||
Boundary wall /Ground floor development work | 00% | |||
Roof top finishing work | 00% | |||
Roof top Gardening work | 50% |