Montrose

Bashundhara R/A, Dhaka

Expected Completion Date

August 2025

Status Updated

February, 2025

SL. No Name of the work Progress details
  Foundation work 100% Completed
  Super Structure work 98% completed
  Block work A-1=98%

A-2=98%

A-3=98%

A-4=98%

A-5=98%

A-6=98%

 

 

 

 

 

  Electrical conduit work A-1=65%

A-2=65%

A-3=65%

A-4=65%

A-5=65%

A-6=50%

 

 

 

 

 

  Door frame fitting work A-1=70%

A-2=100%

A-3=100%

A-4=90%

A-5=100%

A-6=95%

 

   

 

  Sanitary & plumbing line work A-1=15%

A-2=15%

A-3=15%

A-4=15%

A-5=15%

A-6=15%

   

 

  In side Plastering work A-1=80%

A-2=95%

A-3=95%

A-4=95%

A-5=95%

A-6=80%

 

 

 

 

 
  Electrical cable wiring work A-1=00%

A-2=00%

A-3=00%

A-4=00%

A-5=00%

A-6=00%

 

   
  Wall tiles work A-1=00%

A-2=00%

A-3=00%

A-4=00%

A-5=00%

A-6=00%

 

   
  Floor tiles/Marble work A-1=00%

A-2=00%

A-3=00%

A-4=00%

A-5=00%

A-6=00%

 

   
  Outside plastering work 30%
  Common sanitary & Plumbing line work 0%    
  L.C.C work 00%    
  Grill & Railing work A-1=00%

A-2=00%

A-3=00%

A-4=00%

A-5=00%

A-6=00%

 

   
  Inside paint & Polishing work  

00%

   
  Switch -Socket fitting work 00%    
  Outside paint work 00%    
  Door shutter work 00%    
  Aluminum/Glazing work 00%    
  Tiles Pointing work & Marble finishing work 00%    
  Commode – Basin fitting work and C.P fittings work 00%
  Lift/Generator /Substation /Solar work 00%
  Boundary wall /Ground floor development work 00%
  Roof top finishing work 00%
  Roof top Gardening work 30%