Montrose

Block K, Bashundhara R/A

Expected Completion Date

February 2026

Status Updated

April, 2026

SL. No Name of the work Progress details
  Foundation work 100% Completed
  Super Structure work 98% completed
  Block work A-1=100%

A-2=100%

A-3=100%

A-4=100%

A-5=100%

A-6=100%

 

 

 

 

 

  Electrical conduit work A-1=100%

A-2=100%

A-3=100%

A-4=100%

A-5=100%

A-6=100%

 

 

 

 

 

  Door frame fitting work A-1=100%

A-2=100%

A-3=100%

A-4=100%

A-5=100%

A-6=100%

 

   

 

  Sanitary & plumbing line work A-1=100%

A-2=100%

A-3=100%

A-4=100%

A-5=100%

A-6=100%

   

 

  In side Plastering work A-1=100%

A-2=100%

A-3=100%

A-4=100%

A-5=100%

A-6=100%

 

 

 

 

 
  Electrical cable wiring work A-1=100%

A-2=100%

A-3=100%

A-4=100%

A-5=100%

A-6=100%

 

   
  Wall tiles work A-1=100%

A-2=100%

A-3=100%

A-4=100%

A-5=100%

A-6=100%

 

   
  Floor tiles/Marble work A-1=100%

A-2=100%

A-3=100%

A-4=100%

A-5=100%

A-6=100%

 

   
  Outside plastering work 100%
  Common sanitary & Plumbing line work 100%    
  L.C.C work 100%    
  Grill & Railing work A-1=100%

A-2=100%

A-3=100%

A-4=100%

A-5=100%

A-6=100%

 

   
  Inside paint & Polishing work  

100%

   
  Switch -Socket fitting work 100%    
  Outside paint work 100%    
  Door shutter work 100%    
  Aluminum/Glazing work 100%    
  Tiles Pointing work & Marble finishing work 100%    
  Commode – Basin fitting work and C.P fittings work 100%
  Lift/Generator /Substation /Solar work 100%
  Boundary wall /Ground floor development work 100%
  Roof top finishing work 100%
  Roof top Gardening work 100%

 