bti Celebration Point

Plot: 3 & 5, Road: 113/A, Gulshan-2, Dhaka-1212

Montrose

Bashundhara R/A, Dhaka
Expected Completion Date February 2026
Status Updated April, 2026
Back to all projects
Montrose

Construction progress details

The progress table comes directly from the WordPress post content.

SL. No Name of the work Progress details
  Foundation work 100% Completed
  Super Structure work 98% completed
  Block work A-1=100%

A-2=100%

A-3=100%

A-4=100%

A-5=100%

A-6=100%

 

 

 

 

 

  Electrical conduit work A-1=100%

A-2=100%

A-3=100%

A-4=100%

A-5=100%

A-6=100%

 

 

 

 

 

  Door frame fitting work A-1=100%

A-2=100%

A-3=100%

A-4=100%

A-5=100%

A-6=100%

 

   

 

  Sanitary & plumbing line work A-1=100%

A-2=100%

A-3=100%

A-4=100%

A-5=100%

A-6=100%

   

 

  In side Plastering work A-1=100%

A-2=100%

A-3=100%

A-4=100%

A-5=100%

A-6=100%

 

 

 

 

 
  Electrical cable wiring work A-1=100%

A-2=100%

A-3=100%

A-4=100%

A-5=100%

A-6=100%

 

   
  Wall tiles work A-1=100%

A-2=100%

A-3=100%

A-4=100%

A-5=100%

A-6=100%

 

   
  Floor tiles/Marble work A-1=100%

A-2=100%

A-3=100%

A-4=100%

A-5=100%

A-6=100%

 

   
  Outside plastering work 100%
  Common sanitary & Plumbing line work 100%    
  L.C.C work 100%    
  Grill & Railing work A-1=100%

A-2=100%

A-3=100%

A-4=100%

A-5=100%

A-6=100%

 

   
  Inside paint & Polishing work  

100%

   
  Switch -Socket fitting work 100%    
  Outside paint work 100%    
  Door shutter work 100%    
  Aluminum/Glazing work 100%    
  Tiles Pointing work & Marble finishing work 100%    
  Commode – Basin fitting work and C.P fittings work 100%
  Lift/Generator /Substation /Solar work 100%
  Boundary wall /Ground floor development work 100%
  Roof top finishing work 100%
  Roof top Gardening work 100%

 