Montrose

Bashundhara R/A, Dhaka

Completion Date

May 2025

Status Updated

March, 2024

SL. No Name of the work Progress details
  Foundation work 100% Completed
  Super Structure work 35% completed
  Block work N/A
  Electrical conduit work 6%
  Door frame fitting work N/A
  Sanitary & plumbing line work N/A
  In side Plastering work N/A
  Electrical cable wiring work N/A
  Wall tiles work N/A
  Common sanitary & Plumbing line work N/A
  Outside plastering work N/A
  Floor tiles/Marble work N/A
  L.C.C work N/A
  Grill & Railing work N/A
  Inside paint & Polishing work N/A
  Switch -Socket fitting work N/A
  Outside paint work N/A
  Door shutter work N/A
  Aluminum/Glazing work N/A
  Tiles Pointing work & Marble finishing work N/A
  Commode – Basin fitting work and C.P fittings work N/A
  Lift/Generator /Substation /Solar work N/A
  Boundary wall /Ground floor development work N/A
  Roof top finishing work N/A
  Roof top Gardening work N/A