Expected Completion Date
August 2026
Status Updated
September, 2025
| SL. No | Name of the work | Progress details | Remarks |
| 01 | Foundation work | Foundation work 100% completed. | |
| 02 | Super Structure work | 9th Floor roof slab casing completed | |
| 03 | Brick Work | 1st Floor, 2nd Floor,3rd Floor ,4th Floor, 5th Floor ,6th floor – 95% ,
7th Floor,8th Floor – 75% done.
|
|
| 04
|
Electrical work | Groove Cutting work is on going | |
| 05
|
Door frame fitting work | 3rd,4th,5th,6th Floor Door Frame fitting work done. | |
| 06 | Sanitary & plumbing line work | Ver vertical 2” UPVC pipe & Internal Duct 4” UPVC Line fitting work on-going. | |
| 07 | In side Plastering work | 6th ,7th ,8th Floor Ceiling Plaster done.
4th floor wall Plaster On going. |
|
| 08 | Electrical cable wiring work | ||
| 09 | Wall tiles work | ||
| 10 | Common sanitary & Plumbing line work | ||
| 11 | Outside plastering work | ||
| 12 | Floor tiles/Marble work | ||
| 13 | L.C.C work | ||
| 14 | Grill & Railing work | ||
| 15 | Inside paint & Polishing work |
|
|
| 16 | Switch -Socket fitting work |
|
|
| 17 | Outside paint work | ||
| 18 | Door shutter work |
|
|
| 19 | Aluminum/Glazing work |
|
|
| 20 | Tiles Pointing work & Marble finishing work | ||
| 21 | Commode – Basin fitting work and C.P fittings work | ||
| 22 | Lift/Generator /Substation /Solar work | ||
| 23 | Boundary wall /Ground floor development work | ||
| 24 | Land escape /Logo work | ||
| 25 | Roof top finishing work | ||
| 26 | Roof top Gardening work |