Moondrift Manor

North Khulshi, Chattogram

Expected Completion Date

August 2026

Status Updated

September, 2025

SL. No Name of the work Progress details Remarks
01 Foundation work  Foundation work 100% completed.  
02 Super Structure work  9th Floor roof slab casing completed  
03 Brick Work 1st Floor, 2nd Floor,3rd Floor ,4th Floor, 5th Floor ,6th floor – 95% ,

7th Floor,8th Floor – 75% done.

 

 
04

 

Electrical work Groove Cutting work is on going  
05

 

Door frame fitting work 3rd,4th,5th,6th Floor Door Frame fitting work done.  
06 Sanitary & plumbing line  work Ver vertical 2” UPVC pipe & Internal Duct 4” UPVC Line fitting work on-going.  
07 In side Plastering work 6th ,7th ,8th Floor Ceiling Plaster done.

4th floor wall Plaster On going.

 
08 Electrical cable wiring work    
09 Wall tiles  work    
10 Common sanitary & Plumbing line work    
11 Outside plastering work    
12 Floor tiles/Marble work    
13 L.C.C work    
14 Grill & Railing work    
15 Inside paint & Polishing work  

 

 
16 Switch -Socket fitting work  

 

 
17 Outside paint work    
18 Door shutter work  

 

 
19 Aluminum/Glazing work  

 

 
20 Tiles Pointing work & Marble finishing work    
21 Commode – Basin fitting work and C.P fittings work    
22 Lift/Generator /Substation /Solar work    
23 Boundary wall /Ground floor development work    
24 Land escape /Logo work    
25 Roof top finishing work    
26 Roof top Gardening work    

 