Moondrift Manor

North Khulshi, Chattogram

Expected Completion Date

August 2026

Status Updated

October, 2025

SL. No Name of the work Progress details Remarks
01 Foundation work  Foundation work 100% completed.  
02 Basement work N/A  
03 Super Structure work  10th Floor Slab Casting Completed. Lift Machine room (OHWT) slab ,RCC work on-going  
04 Brick Work 1st Floor, 2nd Floor,3rd Floor ,4th Floor, 5th Floor ,6th floor – 100% ,

7th Floor,8th Floor – 80% .

 
05 Electrical work 3rd 4th ,5th Floor Groove Cutting work 100% done &6thfloor on going  
06 Door frame fitting work 3rd,4th,5th,6th 7th ,8th Floor Door Frame fitting work done.  
07 Sanitary & plumbing line  work Ver vertical 2” UPVC pipe & Internal Duckt 4” UPVC Line fitting work on-going.(60% done)  
08 In side Plastering work 6th ,7th ,8th Floor Ceiling Plaster done.

4th 5th floor wall Plaster done 6th On going.

 
09 Electrical cable wiring work    
10 Wall tiles  work    
11 Common sanitary & Plumbing line work    
12 Outside plastering work On Going  
13 Floor tiles/Marble work    
14 L.C.C work    
15 Grill & Railing work    
16 Inside paint & Polishing work  

 

 
17 Switch -Socket fitting work  

 

 
18 Outside paint work    
19 Door shutter work  

 

 
20 Aluminum/Glazing work  

 

 
21 Tiles Pointing work & Marble finishing work    
22 Commode – Basin fitting work and C.P fittings work    
23 Lift/Generator /Substation /Solar work    
24 Boundary wall /Ground floor development work    
25 Land escape /Logo work    
26 Roof top finishing work    
27 Roof top Gardening work    

16604