Moondrift Manor

North Khulshi, Chattogram

Expected Completion Date

August 2026

Status Updated

February, 2026

SL. No Name of the work Progress details
01 Foundation work  Foundation work 100% completed.
02 Basement work  
03 Super Structure work  10th Floor Slab Casting Completed. Lift Machine room (OHWT) top slab casting  100% done. Frond side design wall work on-going
  Brick Work 1st Floor, 2nd Floor,3rd Floor ,4th Floor, 5th Floor ,6th floor 100% ,7th Floor,8th Floor 100% ,9th floor   100% done.

 

05 Electrical work 2nd,3rd 4th ,5th ,6th 7th,8th,9th Floor Groove Cutting work 100% done .
06 Door frame fitting work 2nd ,3rd,4th,5th,6th 7th ,8th 9th Floor Door Frame fitting work 100%  done.
07 Sanitary & plumbing line  work Ver vertical 2” UPVC pipe100% Done & Internal Duct 4” UPVC Line fitting 100%  Done. Out side Duck work 100 % done
08 In side Plastering work 2nd ,3rd 4th, 5th, 6th ,7th ,8th ,9th Floor Ceiling Plaster 100% done.

2nd ,3rd,4th 5th 6th 7th 8th 9th floor & Roof top wall Plaster done  100 % done.

09 Electrical cable wiring work 9th ,8th ,5th Cable wiring 100 % done
10 Wall tiles  work 2nd .3rd,4th ,5th,6th  ,7th,8th,9th,floor Kitchin & bath wall tiles 80 % done
11 Common sanitary & Plumbing line work  
12 Outside plastering work  North East & south side Plaster  100%   & west 50 % done
13 Floor tiles/Marble work 9th, 8th, 7th ,6th,5th,4th floor tiles 500 % done
14 L.C.C work On going.
15 Grill & Railing work  Window Gril making 70 % done
16 Inside paint & Polishing work  

 

17 Switch -Socket fitting work  

 

18 Outside paint work  
19 Door shutter work  

 

20 Aluminum/Glazing work  

 

21 Tiles Pointing work & Marble finishing work  
22 Commode – Basin fitting work and C.P fittings work  
23 Lift/Generator /Substation /Solar work  
24 Boundary wall /Ground floor development work Ground floor development work on going.
25 Land escape /Logo work  
26 Roof top finishing work Roof top 80% done.
27 Roof top Gardening work  

 