Moondrift Manor

North Khulshi, Chattogram

Expected Completion Date

August 2026

Status Updated

December, 2025

SL. No Name of the work Progress details Remarks
01 Foundation work  Foundation work 100% completed.  
02 Basement work    
03 Super Structure work Lift Machine room (OHWT) top slab casting done. Front side design wall work on-going  
04 Brick Work 1st Floor, 2nd Floor,3rd Floor ,4th Floor, 5th Floor ,6th floor 100% ,7th Floor,8th Floor 100% ,9th floor   100% done.

 

 
05 Electrical work 2nd,3rd 4th ,5th ,6th 7th,8th,9th Floor Groove Cutting work 100% done .  
06 Door frame fitting work 2nd ,3rd,4th,5th,6th 7th ,8th 9th Floor Door Frame fitting work 100%  done.  
07 Sanitary & plumbing line  work Ver vertical 2” UPVC pipe100% Done & Internal Duckt 4” UPVC Line fitting 100%  Done.Out side Duck work on-going.  
08 In side Plastering work 2nd ,3rd 4th, 5th, 6th ,7th ,8th ,9th Floor Ceiling Plaster 100% done.

2nd ,3rd,4th 5th 6th 7th 8th floor wall Plaster done 9th On going.

 
09 Electrical cable wiring work Kitchen Bath On Going.  
10 Wall tiles  work 2nd .3rd,4th ,5th,6th floor Kitchin & bath wall tiles on going  
11 Common sanitary & Plumbing line work    
12 Outside plastering work  North side Plaster  90% East & south On Going  
13 Floor tiles/Marble work    
14 L.C.C work    
15 Grill & Railing work  Window Gril making on going.  
16 Inside paint & Polishing work  

 

 
17 Switch -Socket fitting work  

 

 
18 Outside paint work    
19 Door shutter work  

 

 
20 Aluminum/Glazing work  

 

 
21 Tiles Pointing work & Marble finishing work    
22 Commode – Basin fitting work and C.P fittings work    
23 Lift/Generator /Substation /Solar work    
24 Boundary wall /Ground floor development work    
25 Land escape /Logo work    
26 Roof top finishing work Roof top 70% done.  
27 Roof top Gardening work    

16604