Expected Completion Date
August 2026
Status Updated
October, 2024
SL. No | Name of the work | Progress details | Remarks |
01 | Pile work | 100% completed. | |
02 | Foundation work | 100% completed. | |
03 | Super Structure Work | Ground floor roof Slab casting completed | |
04 | Brick Work | ||
05 | Electrical work (Slab Conduit) | ||
06 | Door frame fitting work | ||
07 | Sanitary & plumbing line work | ||
08 | In side Plastering work | ||
09 | Electrical cable wiring work | ||
09 | Wall tiles work | ||
10 | Common sanitary & Plumbing line work | ||
11 | Outside plastering work | ||
12 | Floor tiles/Marble work | ||
13 | L.C.C work | ||
14 | Grill & Railing work | ||
15 | Inside paint & Polishing work | ||
16 | Switch -Socket fitting work | ||
17 | Outside paint work | ||
18 | Door shutter work | ||
19 | Aluminum/Glazing work | ||
20 | Tiles Pointing work & Marble finishing work | ||
21 | Commode – Basin fitting work and C.P fittings work | ||
22 | Lift/Generator /Substation /Solar work | ||
23 | Boundary wall /Ground floor development work | ||
24 | Land escape /Logo work | ||
25 | Roof top finishing work | ||
26 | Roof top Gardening work | ||
16604