Moondrift Manor

North Khulshi, Chattogram

Expected Completion Date

August 2026

Status Updated

December, 2024

SL. No Name of the work Progress details Remarks
01 Pile work 100% completed.  
02 Foundation work 100% completed.  
03.1 Super Structure 2nd Floor Column Work is on Progress.  
03.2 2nd floor casting    
03.3 3rd floor casting    
04 Brick Work    
05 Electrical work (Slab Conduit)    
06 Door frame fitting work    
07 Sanitary & plumbing line  work    
08 In side Plastering work    
09 Electrical cable wiring work    
09 Wall tiles  work    
10 Common sanitary & Plumbing line work    
11 Outside plastering work    
12 Floor tiles/Marble work    
13 L.C.C work    
14 Grill & Railing work    
15 Inside paint & Polishing work    
16 Switch -Socket fitting work    
17 Outside paint work    
18 Door shutter work    
19 Aluminum/Glazing work    
20 Tiles Pointing work & Marble finishing work    
21 Commode – Basin fitting work and C.P fittings work    
22 Lift/Generator /Substation /Solar work    
23 Boundary wall /Ground floor development work    
24 Land escape /Logo work    
25 Roof top finishing work    
26 Roof top Gardening work    
       