Expected Completion Date
August 2026
Status Updated
April, 2026
| SL. No | Name of the work | Location | Progress details | Remarks |
| 01 | Foundation work | 100% completed | ||
| 02 | Super Structure work | 100% completed | ||
| 03 | Block Work | Apartment =A2
Apartment =A3 Apartment =A4 Apartment =A5 Apartment =A6 Apartment =A7 Apartment =A8 Apartment=A9 |
100% Complete
100% Complete 100% Complete 100% Complete 100% Complete 100% Complete 100% Complete 100% Complete
|
|
| 04 | Electrical conduiting work | Apartment =A2
Apartment =A3 Apartment =A4 Apartment =A5 Apartment =A6 Apartment =A7 Apartment =A8 Apartment=A9 |
100% Complete
100% Complete 100% Complete 100% Complete 100% Complete 100% Complete 100% Complete 100% Complete
|
|
| 05 | Door frame fitting work | Apartment =A2
Apartment =A3 Apartment =A4 Apartment =A5 Apartment =A6 Apartment =A7 Apartment =A8 Apartment=A9 |
100% Complete
100% Complete 100% Complete 100% Complete 100% Complete 100% Complete 100% Complete 100% Complete
|
|
| 06 | Sanitary & plumbing line work | 80% Complete | ||
| 07 | In side Plastering work | Apartment =A2
Apartment =A3 Apartment =A4 Apartment =A5 Apartment =A6 Apartment =A7 Apartment =A8 Apartment=A9 |
100% Complete
100% Complete 100% Complete 100% Complete 100% Complete 100% Complete 100% Complete 100% Complete |
|
| 08 | Electrical cable wiring work | Apartment =A2
Apartment =A3 Apartment =A4 Apartment =A5 Apartment =A6 Apartment =A7 Apartment =A8 Apartment=A9 |
100% Complete
100% Complete 100% Complete 100% Complete 100% Complete 100% Complete 100% Complete 100% Complete
|
|
| 09 | Wall tiles work | Apartment =A2
Apartment =A3 Apartment =A4 Apartment =A5 Apartment =A6 Apartment =A7 Apartment =A8 Apartment=A9 |
100% Complete
100% Complete 100% Complete 100% Complete 100% Complete 100% Complete 100% Complete 100% Complete
|
|
| 10 | Common sanitary & Plumbing line work | |||
| 11 | Outside plastering work | |||
| 12 | Floor tiles/Marble work | Apartment =A2
Apartment =A3 Apartment =A4 Apartment =A5 Apartment =A6 Apartment =A7 Apartment =A8 Apartment=A9 |
90% Complete
95% Complete 96% Complete 93% Complete 94% Complete 96% Complete 96% Complete 96% Complete
|
|
| 13 | L.C.C work | Roof | 100% Complete | |
| 14 | Grill & Railing work | Apartment =A2
Apartment =A3 Apartment =A4 Apartment =A5 Apartment =A6 Apartment =A7 Apartment =A8 Apartment=A9 |
80% Complete
75% Complete 70% Complete 70% Complete 70% Complete 70% Complete 70% Complete 70% Complete
|
|
| 15 | Inside paint & Polishing work | Apartment =A2
Apartment =A3 Apartment =A4 Apartment =A5 Apartment =A6 Apartment =A7 Apartment =A8 Apartment=A9 |
On Going | |
| 16 | Switch -Socket fitting work | |||
| 17 | Outside paint work | |||
| 18 | Door shutter work | |||
| 19 | Aluminum work | On Going | ||
| 20 | Tiles Pointing work & Marble finishing work | |||
| 21 | Commode-Basin fitting work and CP fittings work | |||
| 22 | Lift/Generator /Substation /Solar work | |||
| 23 | Boundary wall /Ground floor development work | 40 % Complete | ||
| 24 | Roof top finishing work | 60 % Complete | ||
| 25 | Roof top Gardening work G.F Garden work | 45 % Complete |