Moonwake

Dhanmondi, Dhaka

Expected Completion Date

March 2025

Status Updated

January, 2025

SL. No Name of the work Progress details
1 Supper structure  100% DONE
2 Ceiling plaster 2nd to 13th floor 100%
3 Block work 2nd to 13th floor 100%
  Wall plaster A2- 100%, B-2 100 %, C2-100%, A3-100%. B3- 100%, C3-100%, A4- 100%, B4- 100%, C4- 100%, A5-100%, B-100%, C6- 100%. A7- 100%, B7 100%.C7-90%. A8 100%, B8 100% C8 100%. A9 100%, B9 100%, C9 100%. A10 100%, B10 100%, C10 100%, A11 100%, B11 100%, C11 100%, A12 100%, B12-100%, C12 100%, A13 100%, B13 100%  C13- 90 %.
4 Electrical conduiting work A2- 100%, B-2 100 %, C2-100%, A3-100%. B3- 100%, C3-100%, A4- 100%, B4- 100%, C4- 100%, A5-100%, B-100%, C6- 100%. A7- 100%, B7 100%.C7-90%. A8 100%, B8 100% C8 100%. A9 100%, B9 100%, C9 100%. A10 100%, B10 100%, C10 100%, A11 100%, B11 100%, C11 100%, A12 100%, B12-100%, C12 100%, A13 100%, B13 100%  C13- 90 %.
5 Door frame fitting work A2- 100%, B-2 100 %, C2-100%, A3-100%. B3- 100%, C3-100%, A4- 100%, B4- 100%, C4- 100%, A5-100%, B-100%, C6- 100%. A7- 100%, B7 100%.C7-90%. A8 100%, B8 100% C8 100%. A9 100%, B9 100%, C9 100%. A10 100%, B10 100%, C10 100%, A11 100%, B11 100%, C11 100%, A12 100%, B12-100%, C12 100%, A13 100%, B13 100%  C13- 90 %.
6 Sanitary & plumbing (INTERNAL WIRING) A2- 100%, B-2 100 %, C2-100%, A3-100%. B3- 100%, C3-100%, A4- 100%, B4- 100%, C4- 100%, A5-100%, B-100%, C6- 100%. A7- 100%, B7 100%.C7-90%. A8 100%, B8 100% C8 100%. A9 100%, B9 100%, C9 100%. A10 100%, B10 100%, C10 100%, A11 100%, B11 100%, C11 100%, A12 100%, B12-100%, C12 100%, A13 100%, B13 100%  C13- 70 %.
8 Electrical cable wiring work A2- 100%, B-2 100 %, C2-100%, A3-100%. B3- 100%, C3-100%, A4- 100%, B4- 100%, C4- 100%, A5-100%, B-100%, C6- 100%. A7- 100%, B7 100%.C7-90%. A8 100%, B8 100% C8 100%. A9 100%, B9 100%, C9 100%. A10 100%, B10 100%, C10 100%, A11 100%, B11 100%, C11 100%, A12 100%, B12-100%, C12 100%, A13 100%, B13 100%  C13- 70 %.
9 Wall tiles work A2- 100%, B-2 100 %, C2-100%, A3-100%. B3- 100%, C3-100%, A4- 100%, B4- 100%, C4- 100%, A5-100%, B-100%, C6- 100%. A7- 100%, B7 100%.C7-90%. A8 100%, B8 100% C8 100%. A9 100%, B9 100%, C9 100%. A10 100%, B10 100%, C10 100%, A11 100%, B11 100%, C11 100%, A12 100%, B12-100%, C12 100%, A13 100%, B13 100% .
10 Sanitary & Plumbing VERTICAL line work 95%
11 Outside plastering work 100%
12 Floor tiles/Marble work A2- 90%, B-2 100 %, C2-90%, A3-100%. B3- 100%, C3-100%, A4- 100%, B4- 100%, C4- 100%, A5-100%, B-100%, C6- 90%. A7- 90%, B7 100%.C7-90%. A8 100%, B8 100% C8 100%. A9 100%, B9 100%, C9 100%. A10 100%, B10 100%, C10 100%, A11 90%, B11 100%, C11 90%, A12 100%, B12-100%, C12 100%, A13 100%, B13 100% .
13 Facing Bricks (Outside) 95% done.
14

 

L.C.C work  
15 Grill & Railing work A2- 100%, B-2 100 %, C2-100%, A3-100%. B3- 100%, C3-100%, A4- 100%, B4- 100%, C4- 100%, A5-100%, B-100%, C6- 100%. A7- 100%, B7 100%.C7-90%. A8 100%, B8 100% C8 100%. A9 100%, B9 100%, C9 100%. A10 100%, B10 100%, C10 100%, A11 100%, B11 100%, C11 100%, A12 100%, B12-100%, C12 100%, A13 100%, B13 100% .
16 Inside paint & Polishing work 1ST COAT= A2- 100%, B-2 100 %, C2-100%, A3-100%. B3- 100%, C3-100%, A4- 100%, B4- 100%, C4- 100%, A5-100%, B-100%, C6- 100%. A7- 100%, B7 100%.C7-90%. A8 100%, B8 100% C8 100%. A9 100%, B9 100%, C9 100%. A10 100%, B10 100%, C10 100%, A11 100%, B11 100%, C11 100%, A12 100%, B12-100%, C12 100%, A13 100%, B13 100% .

 

17 Switch -Socket fitting work 1ST COAT= B2- 100%, B3- 70%, C3-70%, A4- 100%, B4- 100%, C4- 100%, A5-70%, C6- 100%. A8 100%, B8 100% C8 100%.  A10 100%, B10 100%, C10 100%, A11- 70%, B11 70%, C11 -70%, A12 100%, B12-100%, C12 100%,
18 Outside paint work 1ST COAT- 100%
19 Door shutter work A2- 100%, B-2 100 %, C2-100%, B3- 50%, C3-50%, A4- 100%, B4- 100%, C4- 100%, A5-50%, B5-50%,C5-50%,A6-100%,B6-100%,C6- 100%,C7-100%. A8 100%, B8 100% C8 100%. A9 100%, B9 100%, C9 100%. A10 100%, B10 100%, C10 100%, A11 100%, B11 100%, C11 100%, A12 100%, B12-100%, C12 100%, A13-50%, B13-50% .

 

20 Aluminum/Glazing work A2-90%, B2-90%, C2-90%, A4- 100%, B4- 100%, C4- 100%, A5-100%, B5-100%,C5-100%,A6-100%,B6-100%,C6- 100%,C7-100%. A8 100%, B8 100% C8 100%. A9 100%, B9 100%, C9 100%. A10 100%, B10 100%, C10 100%, A11 100%, B11 100%, C11 100%, A12 100%, B12-100%, C12 100%, A13-90%, B13-90%
20 Tiles Pointing work & Marble finishing work WALL TILES A4- 100%, B4- 100%, C4- 100%,A6-100%,B6-100%,C6- 100%,C7-100%. A8 100%, B8 100% C8 100%. A9 100%, B9 100%, C9 100%. A10 100%, B10 100%, C10 100%, A11 100%, B11 100%, C11 100%, A12 100%, B12-100%, C12 100%, A13-90%, B13-90%
21 Commode – Basin fitting work and C.P fittings work A4 90%,C4-90%, A6 90%,C6-90%, A8 90%,C8-90%, A10 90%,C10-90%, A12-90%,C12-90%,

 

 

 

 

 

22 Lift/Generator /Substation /Solar work Substation & Generator supply done.

LIFT INSTALLATION ON GOING

23 Boundary wall /Ground floor development work 80% done.
24 Roof top finishing work 10%
25 Roof top Gardening work  