Moonwake

Dhanmondi, Dhaka

Expected Completion Date

August 2025

Status Updated

July, 2025

SL. No Name of the work Progress details
1 Supper structure  100% DONE
2 Ceiling plaster 2nd to 13th floor 100%
3 Block work 2nd to 13th floor 100%
  Wall plaster A2- 100%, B-2 100 %, C2-100%, A3-100%. B3- 100%, C3-100%, A4- 100%, B4- 100%, C4- 100%, A5-100%, B5-100%, C5,A6-100%,B6 100%, C6- 100%. A7- 100%, B7 100%.C7-90%. A8 100%, B8 100% C8 100%. A9 100%, B9 100%, C9 100%. A10 100%, B10 100%, C10 100%, A11 100%, B11 100%, C11 100%, A12 100%, B12-100%, C12 100%, A13 100%, B13 100%  C13- 100 %.
4 Electrical conduiting work A2- 100%, B-2 100 %, C2-100%, A3-100%. B3- 100%, C3-100%, A4- 100%, B4- 100%, C4- 100%, A5-100%, B5-100%, C5,A6-100%,B6 100%, C6- 100%. A7- 100%, B7 100%.C7-90%. A8 100%, B8 100% C8 100%. A9 100%, B9 100%, C9 100%. A10 100%, B10 100%, C10 100%, A11 100%, B11 100%, C11 100%, A12 100%, B12-100%, C12 100%, A13 100%, B13 100%  C13- 100 %.
5 Door frame fitting work A2- 100%, B-2 100 %, C2-100%, A3-100%. B3- 100%, C3-100%, A4- 100%, B4- 100%, C4- 100%, A5-100%, B5-100%, C5,A6-100%,B6 100%, C6- 100%. A7- 100%, B7 100%.C7-90%. A8 100%, B8 100% C8 100%. A9 100%, B9 100%, C9 100%. A10 100%, B10 100%, C10 100%, A11 100%, B11 100%, C11 100%, A12 100%, B12-100%, C12 100%, A13 100%, B13 100%  C13- 100 %.
6 Sanitary & plumbing (INTERNAL WIRING) A2- 100%, B-2 100 %, C2-100%, A3-100%. B3- 100%, C3-100%, A4- 100%, B4- 100%, C4- 100%, A5-100%, B5-100%, C5,A6-100%,B6 100%, C6- 100%. A7- 100%, B7 100%.C7-90%. A8 100%, B8 100% C8 100%. A9 100%, B9 100%, C9 100%. A10 100%, B10 100%, C10 100%, A11 100%, B11 100%, C11 100%, A12 100%, B12-100%, C12 100%, A13 100%, B13 100%  C13- 100 %.
8 Electrical cable wiring work A2- 100%, B-2 100 %, C2-100%, A3-100%. B3- 100%, C3-100%, A4- 100%, B4- 100%, C4- 100%, A5-100%, B5-100%, C5,A6-100%,B6 100%, C6- 100%. A7- 100%, B7 100%.C7-90%. A8 100%, B8 100% C8 100%. A9 100%, B9 100%, C9 100%. A10 100%, B10 100%, C10 100%, A11 100%, B11 100%, C11 100%, A12 100%, B12-100%, C12 100%, A13 100%, B13 100%  C13- 100 %.
9 Wall tiles work A2- 100%, B-2 100 %, C2-100%, A3-100%. B3- 100%, C3-100%, A4- 100%, B4- 100%, C4- 100%, A5-100%, B5-100%, C5,A6-100%,B6 100%, C6- 100%. A7- 100%, B7 100%.C7-90%. A8 100%, B8 100% C8 100%. A9 100%, B9 100%, C9 100%. A10 100%, B10 100%, C10 100%, A11 100%, B11 100%, C11 100%, A12 100%, B12-100%, C12 100%, A13 100%, B13 100%  C13- 100 %.
10 Sanitary & Plumbing  VERTICAL line work 100%
11 Outside plastering work 100%
12 Floor tiles/Marble work A2- 100%, B-2 100 %, C2-100%, A3-100%. B3- 100%, C3-100%, A4- 100%, B4- 100%, C4- 100%, A5-100%, B5-100%, C5,A6-100%,B6 100%, C6- 100%. A7- 100%, B7 100%.C7-90%. A8 100%, B8 100% C8 100%. A9 100%, B9 100%, C9 100%. A10 100%, B10 100%, C10 100%, A11 100%, B11 100%, C11 100%, A12 100%, B12-100%, C12 100%, A13 100%, B13 100%  C13- 100 %.
13 Facing Bricks (Outside) 100% done.
14 L.C.C work 100% done
15 Grill & Railing work A2- 100%, B-2 100 %, C2-100%, A3-100%. B3- 100%, C3-100%, A4- 100%, B4- 100%, C4- 100%, A5-100%, B-100%, C6- 100%. A7- 100%, B7 100%.C7-90%. A8 100%, B8 100% C8 100%. A9 100%, B9 100%, C9 100%. A10 100%, B10 100%, C10 100%, A11 100%, B11 100%, C11 100%, A12 100%, B12-100%, C12 100%, A13 100%, B13 100%, C-13 100% .
16 Inside paint & Polishing work A2- 100%, B-2 100 %, C2-100%, A3-100%. B3- 100%, C3-100%, A4- 100%, B4- 100%, C4- 100%, A5-100%, B5-100%, C5,A6-100%,B6 100%, C6- 100%. A7- 100%, B7 100%.C7-90%. A8 100%, B8 100% C8 100%. A9 100%, B9 100%, C9 100%. A10 100%, B10 100%, C10 100%, A11 100%, B11 100%, C11 100%, A12 100%, B12-100%, C12 100%, A13 100%, B13 100%  C13- 100 %.
17 Switch -Socket fitting work A2- 100%, B-2 100 %, C2-100%,  B3- 100%, C3-100%, A4- 100%, B4- 100%, C4- 100%, A5-100%, C5,A6-100%,B6 100%, C6- 100%. A7- 100%, B7 100%.C7-90%. A8 100%, B8 100% C8 100%. A9 100%, B9 100%, C9 100%. A10 100%, B10 100%, C10 100%, A11 100%, B11 100%, C11 100%, A12 100%, B12-100%, C12 100%, A13 100%, B13 100%
18 Outside paint work 100%
19 Door shutter work A2- 100%, B-2 100 %, C2-100%,  B3- 100%, C3-100%, A4- 100%, B4- 100%, C4- 100%, A5-100%, C5,A6-100%,B6 100%, C6- 100%. A7- 100%, B7 100%.C7-90%. A8 100%, B8 100% C8 100%. A9 100%, B9 100%, C9 100%. A10 100%, B10 100%, C10 100%, A11 100%, B11 100%, C11 100%, A12 100%, B12-100%, C12 100%, A13 100%, B13 100%
20 Aluminum/Glazing work A2- 100%, B-2 100 %, C2-100%, A3-100%. B3- 100%, C3-100%, A4- 100%, B4- 100%, C4- 100%, A5-100%, B5-100%, C5,A6-100%,B6 100%, C6- 100%. A7- 100%, B7 100%.C7-90%. A8 100%, B8 100% C8 100%. A9 100%, B9 100%, C9 100%. A10 100%, B10 100%, C10 100%, A11 100%, B11 100%, C11 100%, A12 100%, B12-100%, C12 100%, A13 100%, B13 100%  C13- 100 %.
20 Tiles Pointing work & Marble finishing work A2- 100%, B-2 100 %, C2-100%, A3-100%. B3- 100%, C3-100%, A4- 100%, B4- 100%, C4- 100%, A5-100%, B5-100%, C5,A6-100%,B6 100%, C6- 100%. A7- 100%, B7 100%.C7-90%. A8 100%, B8 100% C8 100%. A9 100%, B9 100%, C9 100%. A10 100%, B10 100%, C10 100%, A11 100%, B11 100%, C11 100%, A12 100%, B12-100%, C12 100%, A13 100%, B13 100%  C13- 100%.
21 Commode – Basin fitting work and C.P fittings work A2- 100%, B-2 100 %, C2-100%, . B3- 100%, C3-100%, A4- 100%, B4- 100%, C4- 100%, A5-100%, B5-100%, C5,A6-100%,B6 100%, C6- 100%. A7- 100%, B7 100%.C7-90%. A8 100%, B8 100% C8 100%. A9 100%, B9 100%, C9 100%. A10 100%, B10 100%, C10 100%, A11 100%, B11 100%, C11 100%, A12 100%, B12-100%, C12 100%, B13 100%  C13- 100 %.
22 Lift/Generator /Substation /Solar work Substation & Generator supply done.

LIFT INSTALLATION 90% completed

23 Boundary wall /Ground floor development work 98% done.
24 Roof top finishing work 95%
25 Roof top Gardening work On going
26 Gr floor false ceiling 100%

 