New Horizon

Purana Paltan, Dhaka

Expected Completion Date

May 2025

Status Updated

May, 2025

SL. No Name of the work Progress details Remark
01 Foundation work 100% completed.  
02 Super Structure work 100% completed.  
03 Block Work 100% completed  
04 Electrical Conducting work 100% completed  
05 Door frame fitting work 100 % Completed  
06 Sanitary & plumbing line work 100% Completed  
07 In side Plastering work 100 % Completed  
08 Electrical cable wiring work 100% Completed  
09 Wall Tiles work 100% Completed  
10 Common sanitary & Plumbing line work 100% Completed  
11 Outside plastering work 100% Completed  
12 Floor tiles/Marble work Basement=100%

G.F=95%

A1= 100%, A2= 100%, A3= 100%,     A4= 100%,A5=100%, B5=100%,

A6=100%, B6=100%,A7=100%, B7=100%,A8=100%, B8=100%,

 
13 L.C.C work 100% Completed  
14 Grill & Railing work

 

100% Completed  
15 Inside paint &

Polishing work

100% Completed  
16 Switch -Socket fitting work 100% Completed  
17 Outside paint work 100 % Completed  
18 Door shutter work 100 % Completed  
19 Aluminum work 100 % Completed  
20 Tiles Pointing work & Marble finishing work 100 % Completed  
21 Commode – Basin fitting work and C.P fittings work 100 % Completed  
22 Lift/Generator /Substation /Solar work 90% Completed  
23 Boundary wall /Ground floor development work 95% Completed  
24 Roof top finishing work 95% Completed  
25 Roof top Gardening work G.F Garden work 95% Completed  