Expected Completion Date
February 2026
Status Updated
January, 2025
SL. No | Name of the work | Progress details |
01 | Foundation work | 100 % |
02 | Super Structure work | 100% |
03 | Block Work | A-2= 90%, A-3= 90%, A-4=90%, A-5=90%, A-6= 90%, A-8= 90%, A-9= 50%
B-2=90%, B-3 =90%, B-4=90%, B-5= 90%, B-5= 90%, B-6= 70%, B-7= 70% B-8= 40% C-2=90%, C-3 =90% , C-4= 90%, C-5=40%, C-6=70%, C-7= 70%, C-8=70%, C-9= 70% |
04 | Electrical conducting work | Over all 90% |
05 | Door frame fitting work | A-2= 100%, A-3= 100%, A-4=100%, A-5=100%, A-6= 100%, A-7= 100% ,A-8= 100%, B-2=100%, B-3 =100%, B-4=100%, B-5= 100%, B-5= 100%, B-6= 100%, B-7= 100%, B-8= 90%, B-9= 70%, C-2=100%, C-3 =100%, C-4= 100%, C-5=100%, C-6=100%, C-7= 90%, C-8= 70%, C-8= 70%, C-9= 70%, |
06 | Sanitary & plumbing line work | 20% |
07 | In side Plastering work | Ceiling plaster on going (100%) |
08 | Electrical cable wiring work | N/A |
09 | Wall tiles work | 40% |
10 | Common sanitary & Plumbing line work | N/A |
11 | Outside plastering work | 30% |
12 | Floor tiles/Marble work | N/A |
13 | L.C.C work | N/A |
14 | Grill & Railing work | N/A |
15 | Inside paint & Polishing work | N/A |
16 | Switch -Socket fitting work | N/A |
17 | Outside paint work | N/A |
18 | Door shutter work | N/A |
19 | Aluminum work | N/A |
20 | Tiles Pointing work & Marble finishing work | N/A |
21 | Commode – Basin fitting work and C.P fittings work | N/A |
22 | Lift/Generator /Substation /Solar work | N/A |
23 | Boundary wall /Ground floor development work | N/A |
24 | Roof top finishing work | 50% |
25 | Roof top Gardening work G.F Garden work | N/A |