Northern Light

Block K, Bashundhara R/A

Expected Completion Date

February 2026

Status Updated

May, 2025

SL. No Name of the work Progress details
01 Foundation work 100 %
02 Super Structure work 100%
03 Block Work A-2= 100%, A-3= 100%, A-4=100%, A-5=100%, A-6= 100%, A-8= 100%, A-9= 100%

B-2=100%, B-3 =100%, B-4=100%, B-5= 100%, B-5= 100%, B-6=100%, B-7= 100% B-8=100% ,B-9=100%

C-2=100%, C-3 =100% , C-4= 100%, C-5=100%, C-6=100%, C-7= 100%, C-8=100%, C-9= 100%

04 Electrical conducting work Over all 90%
05 Door frame fitting work A-2= 100%, A-3= 100%, A-4=100%, A-5=100%, A-6= 100%, A-7= 100% ,A-8= 100%, A-9= 100%, B-2=100%, B-3 =100%, B-4=100%, B-5= 100%, B-5= 100%, B-6= 100%, B-7= 100%, B-8= 100%, B-9= 100%,  C-2=100%, C-3 =100%, C-4= 100%, C-5=100%, C-6=100%, C-7= 100%, C-8= 100%, C-8= 100%, C-9= 100%,
06 Sanitary & plumbing line work 50%
07 In side Plastering work Ceiling plaster on going (100%)
08 Electrical cable wiring work A-2= 100%, A-3= 100%, A-4=100%, A-5=100%, A-6= 100%, A-7= 100% ,A-8= 100%, A-9= 100%, B-2=100%, B-3 =100%, B-4=100%, B-5= 100%, B-5= 100%, B-6= 100%, B-7= 100%, B-8= 100%, B-9= 100%,  C-2=100%, C-3 =100%, C-4= 100%, C-5=100%, C-6=100%, C-7= 100%, C-8= 100%, C-8= 100%, C-9= 100%,
09 Wall tiles work Oval all 80%
10 Common sanitary & Plumbing line work N/A
11 Outside plastering work 80%
12 Floor tiles/Marble work 50%
13 L.C.C work N/A
14 Grill & Railing work N/A
15 Inside paint & Polishing work N/A
16 Switch -Socket fitting work N/A
17 Outside paint work N/A
18 Door shutter work N/A
19 Aluminum work N/A
20 Tiles Pointing work & Marble finishing work N/A
21 Commode – Basin fitting work and C.P fittings work N/A
22 Lift/Generator /Substation /Solar work N/A
23 Boundary wall /Ground floor development work N/A
24 Roof top finishing work 60%
25 Roof top Gardening work G.F Garden work N/A