Northern Light

Bashundhara R/A, Dhaka

Completion Date

February 2026

Status Updated

September, 2024

SL. No Name of the work Progress details
01 Foundation work 100 %
02 Super Structure work 100%
03 Block Work A-2= 90%, A-3= 90%, A-4=90%, A-5=90%,

B-2=90%, B-3 =90%, B-4=90%, B-5= 40%,

C-2=90%, C-3 =90% , C-4= 90%, C-5=40%

04 Electrical conducting work Over all 30%
05 Door frame fitting work A-2= 90%, B-2=90%, C-2=90%,
06 Sanitary & plumbing line work N/A
07 In side Plastering work Ceiling plaster on going (60%)
08 Electrical cable wiring work N/A
09 Wall tiles work N/A
10 Common sanitary & Plumbing line work N/A
11 Outside plastering work N/A
12 Floor tiles/Marble work N/A
13 L.C.C work N/A
14 Grill & Railing work N/A
15 Inside paint & Polishing work N/A
16 Switch -Socket fitting work N/A
17 Outside paint work N/A
18 Door shutter work N/A
19 Aluminum work N/A
20 Tiles Pointing work & Marble finishing work N/A
21 Commode – Basin fitting work and C.P fittings work N/A
22 Lift/Generator /Substation /Solar work N/A
23 Boundary wall /Ground floor development work N/A
24 Roof top finishing work N/A
25 Roof top Gardening work G.F Garden work N/A