Expected Completion Date
November 2024
Status Updated
August, 2024
| SL. No | Name of the work | Progress details |
| 01 | Foundation work | 100% |
| 02 | Super Structure work | BASEMENT ROOF SLAB TO 9TH FLOOR ROOF( LAST SLAB) CASTING -100%, COMPLETED |
| 03 | Block Work | A2 FLAT-100%, A3 FLAT- 100%, A4 FLAT- 100%, A5 FLAT- 100%, A6 FLAT- 100%, A7 FLAT- 100%, A8 FLAT- 100%, A9 FLAT- 100% completed |
| 04 | Electrical conduit work | Gf, 1st,2nd 3RD 4TH 5TH 6TH 7TH 8TH 9TH floor conduit work 100% completed. |
| 05 | Door frame fitting work | 2nd 3rd 4TH 5TH 6TH 7TH 8th 9th floor 100% completed. |
| 06 | Sanitary & plumbing line work | 100 % complete |
| 07 | In side Plastering work | 100 % completed. |
| 08 | Electrical cable wiring work | 100 % completed. |
| 09 | Wall tiles& floor tiles work | 100 % completed.
|
| 10 | Common sanitary & Plumbing line work | 99% completed. |
| 11 | Outside plastering work | Outside plaster 100% completed. |
| 12 | Floor tiles/Marble work | 1st ,2nd ,3rd ,4th ,5th 6th ,7th 8th ,9th floor, 100% completed.
Ground floor work 100% completed. |
| 13 | L.C.C work | N/A |
| 14 | Grill & Railing work | 100% complete |
| 15 | Inside paint & Polishing work | 100 % complete |
| 16 | Switch -Socket fitting work | 100% completed. |
| 17 | Outside paint work | 98% complete |
| 18 | Door shutter work & polish | 100 % complete |
| 19 | Aluminum/Glazing work | 2nd -9th floor 100% completed.
1st floor 100 % completed. |
| 20 | Tiles Pointing work & Marble finishing work | 98% completed. |
| 21 | Commode – Basin fitting work and C.P fittings work | 98 % completed. |
| 22 | Lift/Generator /Substation /Solar work | 95% completed. |
| 23 | Boundary wall /Ground floor development work | 95% completed. |
| 24 | Roof top finishing work | 98% complete |
| 25 | Roof top Gardening work | 90% complete |
| 26 | Gardening work | 90% complete |
| 27 | Fair face finishing | 98% complete |
| 28 | Artificial fair face | 98% complete |
| 29 | Kitchen ver. Railing | 100% complete |
| 30 | Outside AC lover | 100% complete |
| 31 | Firefighting work | 90% complete |
| 32 | Swimming pool works | 100% complete |
| 32 | Pavement tiles | 100% complete |
| 33 | PVC false ceiling works | 100% complete |
| 34 | Ramp tiles | 98% complete |
16604