Completion Date
November 2024
Status Updated
March, 2024
SL. No | Name of the work | Progress details |
01 | Foundation work | 100% |
02 | Super Structure work | BASEMENT ROOF SLAB TO 9TH FLOOR ROOF( LAST SLAB) CASTING -100%, COMPLETED |
03 | Block Work | A2 FLAT-100%,A3 FLAT- 100%,A4 FLAT- 100%,A5 FLAT- 100%, A6 FLAT- 100%,A7 FLAT- 100% , A8 FLAT- 100% . .A9 FLAT- 100% |
04 | Electrical conductingwork | 2nd 3RD 4TH 5TH 6TH 7TH 8TH 9TH FLOOR CONDUITING WARING-100% COMPLETE |
05 | Door frame fitting work | 2nd 3rd 4TH 5TH 6TH 7TH 8th 9th floor 100% complete |
06 | Sanitary & plumbing line work | 4’’ vatical duck waring 95% complete |
07 | In side Plastering work | GF to 9TH FLOOR CELLING PLASTER 100% COMPLETE, .
1st 2nd 3rd 4th 5th 6th 7th 8th 9thn floor inside wall plaster 99% complete. |
08 | Electrical cable wiring work | 1ST 2nd 3rd 4th 5th 6th 7th 8th 9th floor 98% complete |
09 | Wall tiles& floor tiles work | 2nd ’3rd ,4th ,5th ,6th ,7th ,8th ,9th ,floor wall tiles 98% done.
|
10 | Common sanitary & Plumbing line work | 40% complete |
11 | Outside plastering work | Outside plaster 98% complete |
12 | Floor tiles/Marble work | 2nd ,3rd ,4th ,5th 6th ,7th 8th ,9thfloor, 98% done. |
13 | L.C.C work | N/A |
14 | Grill & Railing work | 2nd-9th floor Grill work 100% complete |
15 | Inside paint & Polishing work | 65% complete |
16 | Switch -Socket fitting work | 2nd 3rd 5th 7th 9th floor 90% complete |
17 | Outside paint work | 60% complete |
18 | Door shutter work | 80% complete |
19 | Aluminum/Glazing work | 2nd -9th floor 90% complete |
20 | Tiles Pointing work & Marble finishing work | 3rd 5th 7th 9th 50% complete
9th 8th 7th 6th 5th 4th floor 50% complete |
21 | Commode – Basin fitting work and C.P fittings work | N/A |
22 | Lift/Generator /Substation /Solar work | N/A |
23 | Boundary wall /Ground floor development work | 60% complete |
24 | Roof top finishing work | 70% complete |
25 | Roof top Gardening work | 50% complete |
26 | Gardening work | 12% complete |
27 | Fair face finishing | 90% complete |
28 | Artificial fair face | 95% complete |
29 | Kitchen ver. Railing | 100% complete |
30 | Outside AC lover | 100% complete |
31 | Fir work | 30% complete |
32 | Swimming pool works | 60% complete |
32 | Pavement tiles | 50% complete |
33 | Pvc false ceiling works | 50% complete |
16604