Park Royale

Gulshan, Dhaka

Completion Date

November 2024

Status Updated

March, 2024

SL. No Name of the work Progress details
01 Foundation work 100%
02 Super Structure work BASEMENT ROOF  SLAB TO 9TH FLOOR ROOF( LAST SLAB) CASTING -100%,   COMPLETED
03 Block Work A2 FLAT-100%,A3 FLAT- 100%,A4 FLAT- 100%,A5 FLAT- 100%, A6 FLAT- 100%,A7 FLAT- 100% , A8 FLAT- 100% . .A9 FLAT- 100%
04 Electrical conductingwork  2nd 3RD  4TH 5TH 6TH 7TH  8TH 9TH  FLOOR CONDUITING  WARING-100% COMPLETE
05 Door frame fitting work 2nd 3rd   4TH  5TH  6TH 7TH 8th 9th  floor 100% complete
06 Sanitary & plumbing line  work 4’’ vatical duck waring 95% complete
07 In side Plastering work GF to 9TH FLOOR CELLING PLASTER 100% COMPLETE, .

1st 2nd 3rd 4th 5th 6th 7th 8th 9thn floor inside wall plaster 99% complete.

08 Electrical cable wiring work 1ST 2nd 3rd 4th   5th 6th 7th  8th 9th floor  98% complete
09 Wall tiles& floor tiles  work 2nd  ’3rd  ,4th ,5th ,6th  ,7th ,8th ,9th ,floor wall tiles 98% done.

 

10 Common sanitary & Plumbing line work 40% complete
11 Outside plastering work Outside plaster 98% complete
12 Floor tiles/Marble work 2nd ,3rd ,4th ,5th 6th  ,7th 8th  ,9thfloor,   98% done.
13 L.C.C work N/A
14 Grill & Railing work 2nd-9th floor Grill work 100% complete
15 Inside paint & Polishing work 65% complete
16 Switch -Socket fitting work  2nd 3rd 5th 7th 9th floor 90% complete
17 Outside paint work 60% complete
18 Door shutter work 80% complete
19 Aluminum/Glazing work 2nd -9th  floor 90% complete
20 Tiles Pointing work & Marble finishing work 3rd 5th 7th 9th  50% complete

9th 8th 7th 6th 5th 4th  floor 50% complete

21 Commode – Basin fitting work and C.P fittings work N/A
22 Lift/Generator /Substation /Solar work N/A
23 Boundary wall /Ground floor development work 60% complete
24 Roof top finishing work 70% complete
25 Roof top Gardening work 50%  complete
26 Gardening work 12%  complete
27 Fair face finishing 90%  complete
28 Artificial fair face 95%  complete
29 Kitchen ver. Railing 100% complete
30 Outside AC lover 100% complete
31 Fir work 30% complete
32 Swimming pool works 60% complete
32 Pavement tiles 50%  complete
33 Pvc false ceiling works 50% complete