Park Royale

Gulshan, Dhaka

Completion Date

July 2024

Status Updated

August, 2024

SL. No Name of the work Progress details
01 Foundation work 100%
02 Super Structure work BASEMENT ROOF  SLAB TO 9TH FLOOR ROOF( LAST SLAB) CASTING -100%,   COMPLETED
03 Block Work A2 FLAT-100%, A3 FLAT- 100%, A4 FLAT- 100%, A5 FLAT- 100%, A6 FLAT- 100%, A7 FLAT- 100%, A8 FLAT- 100%, A9 FLAT- 100% completed
04 Electrical conduit work  Gf, 1st,2nd 3RD  4TH 5TH 6TH 7TH  8TH 9TH floor conduit work 100% completed.
05 Door frame fitting work 2nd 3rd   4TH  5TH  6TH 7TH 8th 9th floor 100% completed.
06 Sanitary & plumbing line work 100 % complete
07 In side Plastering work 100 % completed.
08 Electrical cable wiring work 100 % completed.
09 Wall tiles& floor tiles work 100 % completed.

 

10 Common sanitary & Plumbing line work 99% completed.
11 Outside plastering work Outside plaster 100% completed.
12 Floor tiles/Marble work 1st ,2nd ,3rd ,4th ,5th 6th ,7th 8th ,9th floor, 100% completed.

Ground floor work 100% completed.

13 L.C.C work N/A
14 Grill & Railing work 100% complete
15 Inside paint & Polishing work 100 % complete
16 Switch -Socket fitting work 100% completed.
17 Outside paint work 98% complete
18 Door shutter work & polish 100 % complete
19 Aluminum/Glazing work 2nd -9th floor 100% completed.

1st floor 100 % completed.

20 Tiles Pointing work & Marble finishing work 98% completed.
21 Commode – Basin fitting work and C.P fittings work 98 % completed.
22 Lift/Generator /Substation /Solar work 95% completed.
23 Boundary wall /Ground floor development work 95% completed.
24 Roof top finishing work 98% complete
25 Roof top Gardening work 90% complete
26 Gardening work 90% complete
27 Fair face finishing 98% complete
28 Artificial fair face 98% complete
29 Kitchen ver. Railing 100% complete
30 Outside AC lover 100% complete
31 Firefighting work 90% complete
32 Swimming pool works 100% complete
32 Pavement tiles 100% complete
33 PVC false ceiling works 100% complete
34 Ramp tiles 98% complete

16604