Pine Hurst

Uttara, Dhaka

Expected Completion Date

February 2025

Status Updated

February, 2025

SL. No Name of the work Progress details
1 Foundation work 100% completed.
2 Basement work N/A
3 Super Structure work 100% completed (8th Floor Roof slab casting completed)
4 Block Work 100% completed
5 Electrical conduiting work 100% completed
6 Door frame fitting work 100% completed
7 Sanitary & plumbing line work 100% completed

 

8 Inside Plastering work 100% completed
9 Electrical cable wiring work 100% completed
10 Wall tiles work 100% Completed
11 Common sanitary & Plumbing line work 100% completed.
12 Outside plastering work 100% Completed
13 Floor tiles/Marble work 100% Completed
14 L.C.C work 100%
15 Grill & Railing work 100%
16 Inside paint & Polishing work 100%
17 Switch -Socket fitting work 100%
18 Outside paint work 100%
19 Door shutter work 100%
20 Aluminum work 100%
21 Tiles Pointing work & Marble finishing work 100%
22 Commode – Basin fitting work and C.P fittings work 100%
23 Lift/Generator /Substation /Solar work 98%
24 Boundary wall /Ground floor development work 100%
25 Roof top finishing work 100%
26 Roof top Gardening work G.F Garden work 90%
27 Land escape /Logo work 90%