Expected Completion Date
April 2027
Status Updated
September, 2025
| SL. No | Name of the work | Progress details |
| 01 | Foundation work | 100% completed. Pile work done. |
| 02 | Super Structure work | 55.55% Completed (Ground floor roof slab 100% completed, 1st floor roof slab 100% completed, 2nd floor roof slab 100% completed.3rd Floor roof Slab 100% completed. 4th floor roof slab 100% completed.) |
| 03 | Block Work | 7% completed. |
| 04 | Electrical conduiting work | Not yet started. |
| 05 | Door frame fitting work | Not yet started. |
| 06 | Sanitary & plumbing line work | Not yet started. |
| 07 | In side Plastering work | 10% completed. (Ceiling) |
| 08 | Electrical cable wiring work | Not yet started. |
| 09 | Wall tiles& floor tiles work | Not yet started. |
| 10 | Common sanitary & Plumbing line work | Not yet started. |
| 11 | Outside plastering work | Not yet started. |
| 12 | Floor tiles/Marble work | Not yet started. |
| 13 | L.C.C work | Not yet started. |
| 14 | Grill & Railing work | Not yet started. |
| 15 | Inside paint & Polishing work | Not yet started. |
| 16 | Switch -Socket fitting work | Not yet started. |
| 17 | Outside paint work | Not yet started. |
| 18 | Door shutter work | Not yet started. |
| 19 | Aluminum/Glazing work | Not yet started. |
| 20 | Tiles Pointing work & Marble finishing work | Not yet started. |
| 21 | Commode – Basin fitting work and C.P fittings work | Not yet started. |
| 22 | Lift/Generator /Substation /Solar work | Not yet started. |
| 23 | Boundary wall /Ground floor development work | Not yet started. |
| 24 | Roof top finishing work | Not yet started. |
| 25 | Roof top Gardening work | Not yet started. |
| 26 | Gardening work | Not yet started. |
| 27 | Kitchen ver. Railing | Not yet started. |
| 28 | Outside AC lover | Not yet started. |
| 29 | Fire work | Not yet started. |
| 30 | Pavement tiles | Not yet started. |
| 31 | Pvc false ceiling works | Not yet started. |