Prime View

Uttara, Dhaka

Expected Completion Date

August 2025

Status Updated

February, 2025

SL. No Name of the work Progress details
1 Foundation work 100% completed
2 Basement work N/A
3 Super Structure work 100% completed. (Roof slab casting completed)
4 Block Work A1-100% completed, A2-100% completed, A3-100% completed, A4-100% completed, A5-100% completed, A6-100% completed, A7-100% completed, A8- 90% completed.
5 Electrical conduiting work A1-100% completed, A2-100% completed, A3-100% completed, A4-100% completed, A5-100% completed, A6-100% completed, A7 – 100% completed, A8 – 80% completed.
6 Door frame fitting work A1-100% completed, A2-100% completed, A3-100% completed, A4-100% completed, A5-90% completed. A6-100% completed, A7- 100% completed, A8- 100% completed.
7 Sanitary & plumbing line work 45% Completed.
8 Inside Plastering work A1-90% completed, A2-90% completed, A3-90% completed, A4-90% completed, A5- 90% completed, A6- 90% completed, A7- 90% completed, A8- 90% completed,
9 Electrical cable wiring work A4- 90% completed. A8- 90% completed
10 Wall tiles work  
11 Common sanitary & Plumbing line work  
12 Outside plastering work 60% Completed.
13 Floor tiles/Marble work  
14 L.C.C work  
15 Grill & Railing work  
16 Inside paint & Polishing work  
17 Switch -Socket fitting work  
18 Outside paint work  
19 Door shutter work  
20 Aluminum work  
21 Tiles Pointing work & Marble finishing work  
22 Commode – Basin fitting work and C.P fittings work  
23 Lift/Generator /Substation /Solar work  
24 Boundary wall /Ground floor development work  
25 Roof top finishing work  
26 Roof top Gardening work G.F Garden work  
27 Land escape /Logo work  

16604