Expected Completion Date
August 2025
Status Updated
February, 2025
SL. No | Name of the work | Progress details |
1 | Foundation work | 100% completed |
2 | Basement work | N/A |
3 | Super Structure work | 100% completed. (Roof slab casting completed) |
4 | Block Work | A1-100% completed, A2-100% completed, A3-100% completed, A4-100% completed, A5-100% completed, A6-100% completed, A7-100% completed, A8- 90% completed. |
5 | Electrical conduiting work | A1-100% completed, A2-100% completed, A3-100% completed, A4-100% completed, A5-100% completed, A6-100% completed, A7 – 100% completed, A8 – 80% completed. |
6 | Door frame fitting work | A1-100% completed, A2-100% completed, A3-100% completed, A4-100% completed, A5-90% completed. A6-100% completed, A7- 100% completed, A8- 100% completed. |
7 | Sanitary & plumbing line work | 45% Completed. |
8 | Inside Plastering work | A1-90% completed, A2-90% completed, A3-90% completed, A4-90% completed, A5- 90% completed, A6- 90% completed, A7- 90% completed, A8- 90% completed, |
9 | Electrical cable wiring work | A4- 90% completed. A8- 90% completed |
10 | Wall tiles work | |
11 | Common sanitary & Plumbing line work | |
12 | Outside plastering work | 60% Completed. |
13 | Floor tiles/Marble work | |
14 | L.C.C work | |
15 | Grill & Railing work | |
16 | Inside paint & Polishing work | |
17 | Switch -Socket fitting work | |
18 | Outside paint work | |
19 | Door shutter work | |
20 | Aluminum work | |
21 | Tiles Pointing work & Marble finishing work | |
22 | Commode – Basin fitting work and C.P fittings work | |
23 | Lift/Generator /Substation /Solar work | |
24 | Boundary wall /Ground floor development work | |
25 | Roof top finishing work | |
26 | Roof top Gardening work G.F Garden work | |
27 | Land escape /Logo work |