Prime View

Uttara, Dhaka

Expected Completion Date

September 2025

Status Updated

September, 2025

SL. No Name of the work Progress details
1 Foundation work 100% completed
2 Basement work N/A
3 Super Structure work 100% completed. (Roof slab casting completed)
4 Block Work A1-100% completed, A2-100% completed, A3-100% completed, A4-100% completed, A5-100% completed, A6-100% completed, A7-100% completed, A8- 100% completed.
5 Electrical conduiting work A1-100% completed, A2-100% completed, A3-100% completed, A4-100% completed, A5-100% completed, A6-100% completed, A7 – 100% completed, A8 – 100% completed.
6 Door frame fitting work A1-100% completed, A2-100% completed, A3-100% completed, A4-100% completed, A5-90% completed. A6-100% completed, A7- 100% completed, A8- 100% completed.
7 Sanitary & plumbing line work 98% Completed.
8 Inside Plastering work A1-100% completed, A2-100% completed, A3-100% completed, A4-100% completed, A5- 100% completed, A6- 100% completed, A7- 100% completed, A8- 100% completed,
9 Electrical cable wiring work 98% completed.
10 Wall tiles work 100% completed.
11 Common sanitary & Plumbing line work 100% Completed.
12 Outside plastering work 100% Completed.
13 Floor tiles/Marble work 100% Completed.
14 L.C.C work 100 Completed.
15 Grill & Railing work 100% Completed.
16 Inside paint & Polishing work 100% Completed
17 Switch -Socket fitting work 98% completed.
18 Outside paint work 10% Completed
19 Door shutter work 100% completed
20 Aluminum work 90% Completed.
21 Tiles Pointing work & Marble finishing work 90% Completed.
22 Commode – Basin fitting work and C.P fittings work 95% completed
23 Lift/Generator /Substation /Solar work 70% Completed.
24 Boundary wall /Ground floor development work 70% Completed
25 Roof top finishing work 70% completed
26 Roof top Gardening work G.F Garden work Not Yet Started.
27 Land escape /Logo work Not Yet Started.