Prime View

Uttara, Dhaka

Expected Completion Date

September 2025

Status Updated

July, 2025

SL. No Name of the work Progress details
1 Foundation work 100% completed
2 Basement work N/A
3 Super Structure work 100% completed. (Roof slab casting completed)
4 Block Work A1-100% completed, A2-100% completed, A3-100% completed, A4-100% completed, A5-100% completed, A6-100% completed, A7-100% completed, A8- 100% completed.
5 Electrical conduiting work A1-100% completed, A2-100% completed, A3-100% completed, A4-100% completed, A5-100% completed, A6-100% completed, A7 – 100% completed, A8 – 100% completed.
6 Door frame fitting work A1-100% completed, A2-100% completed, A3-100% completed, A4-100% completed, A5-90% completed. A6-100% completed, A7- 100% completed, A8- 100% completed.
7 Sanitary & plumbing line work 95% Completed.
8 Inside Plastering work A1-90% completed, A2-90% completed, A3-98% completed, A4-98% completed, A5- 98% completed, A6- 100% completed, A7- 100% completed, A8- 98% completed,
9 Electrical cable wiring work 95% completed.
10 Wall tiles work 80% completed.
11 Common sanitary & Plumbing line work 80% Completed.
12 Outside plastering work 95% Completed.
13 Floor tiles/Marble work 80% Completed.
14 L.C.C work 100 Completed.
15 Grill & Railing work 80% Completed.
16 Inside paint & Polishing work Not Yet Started.
17 Switch -Socket fitting work Not Yet Started.
18 Outside paint work Not Yet Started.
19 Door shutter work Not Yet Started.
20 Aluminum work Not Yet Started.
21 Tiles Pointing work & Marble finishing work Not Yet Started.
22 Commode – Basin fitting work and C.P fittings work Not Yet Started.
23 Lift/Generator /Substation /Solar work Lift Installation work going on.
24 Boundary wall /Ground floor development work 20% Completed
25 Roof top finishing work 35% completed
26 Roof top Gardening work G.F Garden work Not Yet Started.
27 Land escape /Logo work Not Yet Started.