Prime View

Uttara, Dhaka
Expected Completion Date September 2025
Status Updated October, 2025
Back to all projects
Prime View

Construction progress details

The progress table comes directly from the WordPress post content.

SL. No Name of the work Progress details
1 Foundation work 100% completed
2 Basement work N/A
3 Super Structure work 100% completed. (Roof slab casting completed)
4 Block Work A1-100% completed, A2-100% completed, A3-100% completed, A4-100% completed, A5-100% completed, A6-100% completed, A7-100% completed, A8- 100% completed.
5 Electrical conduiting work A1-100% completed, A2-100% completed, A3-100% completed, A4-100% completed, A5-100% completed, A6-100% completed, A7 – 100% completed, A8 – 100% completed.
6 Door frame fitting work A1-100% completed, A2-100% completed, A3-100% completed, A4-100% completed, A5-90% completed. A6-100% completed, A7- 100% completed, A8- 100% completed.
7 Sanitary & plumbing line work 100% Completed.
8 Inside Plastering work A1-100% completed, A2-100% completed, A3-100% completed, A4-100% completed, A5- 100% completed, A6- 100% completed, A7- 100% completed, A8- 100% completed,
9 Electrical cable wiring work 100% completed.
10 Wall tiles work 100% completed.
11 Common sanitary & Plumbing line work 100% Completed.
12 Outside plastering work 100% Completed.
13 Floor tiles/Marble work 100% Completed.
14 L.C.C work 100 Completed.
15 Grill & Railing work 100% Completed.
16 Inside paint & Polishing work 100% Completed
17 Switch -Socket fitting work 100% completed.
18 Outside paint work 10% Completed
19 Door shutter work 100% completed
20 Aluminum work 100% Completed.
21 Tiles Pointing work & Marble finishing work 100% Completed.
22 Commode – Basin fitting work and C.P fittings work 100% completed
23 Lift/Generator /Substation /Solar work 90% Completed.
24 Boundary wall /Ground floor development work 100% Completed
25 Roof top finishing work 100% completed
26 Roof top Gardening work G.F Garden work 70% completed
27 Land escape /Logo work 70% completed

 