Prime View

Uttara, Dhaka

Completion Date

May 2025

Status Updated

March, 2024

SL. No Name of the work Progress details
1 Foundation work 100% completed
2 Basement work N/A
3 Super Structure work 35% completed. (2nd floor roof slab casting completed)
4 Block Work  
5 Electrical conduiting work  
6 Door frame fitting work  
7 Sanitary & plumbing line work  
8 Inside Plastering work  
9 Electrical cable wiring work  
10 Wall tiles work  
11 Common sanitary & Plumbing line work  
12 Outside plastering work  
13 Floor tiles/Marble work  
14 L.C.C work  
15 Grill & Railing work  
16 Inside paint & Polishing work  
17 Switch -Socket fitting work  
18 Outside paint work  
19 Door shutter work  
20 Aluminum work  
21 Tiles Pointing work & Marble finishing work  
22 Commode – Basin fitting work and C.P fittings work  
23 Lift/Generator /Substation /Solar work  
24 Boundary wall /Ground floor development work  
25 Roof top finishing work  
26 Roof top Gardening work G.F Garden work  
27 Land escape /Logo work  

16604