Expected Completion Date
May 2026
Status Updated
October, 2024
SL. No | Name of the work | Progress details |
01 | Foundation work | 100% completed. |
02 | Super Structure work | 90 % completed. |
03 | Block Work | A-1 =95%, A-2= 100%, A-3= 100%, A-4 =75%, A-5= 75%, A-6= 75%, A-7= 65%, B-1=100%, B-2=100%,B-3 = 90%, B-4=75%, B-5=75%, B-6=75%, B-7=65%, C-1=90%, C-2=100%, C-3 =95 %, C-4 =75 %, C-5 =75 %, C-6 =75 %, C-7 =60 %, I-2 (D2)=80% , D-3= 95%, D-4= 95%, D-5= 75%, D-6= 75%, E-2 = 95%, E-3= 95%, E-4= 90%, E-5= 75%, E-6= 75%, F-2 =30%, F-3 =50%, F-4=70%, F-5=70%, F-6=60%, F-7=60%, G-2=95%, G-3 =90%, G-4=90%, G-5=70%, & G-6=70%. |
04 | Electrical conducting work | A-1 =95%, A-2= 100%, A-3= 100%, A-4 =75%, A-5= 75%, A-6= 75%, A-7= 65%, B-1=100%, B-2=100%,B-3 = 90%, B-4=75%, B-5=75%, B-6=75%, B-7=65%, C-1=90%, C-2=100%, C-3 =95 %, C-4 =75 %, C-5 =75 %, C-6 =75 %, C-7 =60 %, I-2 (D2)=80% , D-3= 95%, D-4= 95%, D-5= 75%, D-6= 75%, E-2 = 95%, E-3= 95%, E-4= 90%, E-5= 75%, E-6= 75%, F-2 =30%, F-3 =50%, F-4=70%, F-5=70%, F-6=60%, F-7=60%, G-2=95%, G-3 =90%, G-4=90%, G-5=70%, & G-6=70%. |
05 | Door frame fitting work | 25% completed |
06 | Sanitary & plumbing line work | 0% completed |
07 | In side Plastering work | A-1 =90%, A-2= 90%, A-3= 90%, A-4 =20%, A-5= 20%, A-6= 20%, A-7= 20%, B-1 =90%, B-2= 90%, B-3= 90%, B-4=20%, B-5=20%, B-6=20%, B-7=20%, C-1 =90%, C-2= 90%, C-3= 80%, C-4 =20 %, C-5 =20 %, C-6 =20 %, C-7 =20 %, I-2 (D2)=20% , D-3=80%, %, D-4= 20%, D-5= 20%, D-6=20%, D-7=20%, D-8=20%, E-2=80%, E-3=80%, E-4= 20%, E-5=20%, E-6=20%, E-7=20%, E-8=20%, F-2=20%, F-3=20%, F-4=20%, F-5=20%, F-6=20%, F-7=20%, F-8=20%, G-2=80%, G-3=50%, G-4=20%, G-5=20%, G-6=20%. G-7=20%. G-8=20%. |
08 | Electrical cable wiring work | 10% completed |
09 | Wall tiles work | 0% completed |
10 | Common sanitary & Plumbing line work | 0% completed |
11 | Outside plastering work | 0% completed |
12 | Floor tiles/Marble work | 0% completed |
13 | L.C.C work | 0% completed |
14 | Grill & Railing work | 0% completed |
15 | Inside paint & Polishing work | 0% completed |
16 | Switch -Socket fitting work | 0% completed |
17 | Outside paint work | 0% completed |
18 | Door shutter work | 0% completed |
19 | Aluminum work | 0% completed |
20 | Tiles Pointing work & Marble finishing work | 0% completed |
21 | Commode – Basin fitting work and C.P fittings work | 0% completed |
22 | Lift/Generator /Substation /Solar work | 0% completed |
23 | Boundary wall /Ground floor development work | 0% completed. |
24 | Roof top finishing work | 0% completed. |
25 | Roof top Gardening work G.F Garden work | 0% completed. |
16604