Expected Completion Date
May 2026
Status Updated
May, 2025
SL. No | Name of the work | Progress details |
01 | Foundation work | 100% completed. |
02 | Super Structure work | 97 % completed. |
03 | Block Work | A-1 =95%, A-2= 100%, A-3= 100%, A-4 =95%, A-5= 95%, A-6= 95%, A-7= 95%,A-8=95%,A-9=90% B-1=100%, B-2=100%,B-3 = 98%, B-4=95%, B-5=98%, B-6=98%, B-7=98%, B-8=98%B-9=90% C-1=98%, C-2=100%, C-3 =98 %, C-4 =98 %, C-5 =98 %, C-6 =98 %, C-7 =98 %, C-8= 95%,C-9=90%I-2 (D2)=80% , D-3= 98%, D-4= 98%, D-5= 98%, D-6= 95%,D-7=90%,D-8=70%,D-9=70% E-2 = 98%, E-3=98%
E-4= 96%, E-5= 95%, E-6= 95%, E-7=95%, E-8=55%, E-9=50% F-2 =50%, F-3 =70%, F-4=80%, F-5=95%, F-6=95%, F-7=95%, F-8=50%,F-9=50% G-2=95%, G-3 =95%, G-4=95%, G-5=95%, G-6=95%.G-7=95%, G-8=70%,G-9=50% |
04 | Electrical conducting work | A-1 =95%, A-2= 100%, A-3= 100%, A-4 =92%, A-5= 95%, A-6= 95%, A-7= 95%,A-8=95% B-1=100%, B-2=100%,B-3 = 98%, B-4=95%, B-5=98%, B-6=98%, B-7=8%,B-8=98%B-9=98% C-1=98%, C-2=100%, C-3 =98 %, C-4 =98 %, C-5 =98 %, C-6 =98 %, C-7 =98 %,C-8=95%,C-9=90% I-2 (D2)=80% , D-3= 98%, D-4= 98%, D-5= 98%, D-6= 95%,D-7=90%, D-8=70%,D-9=70%E-2 = 98%, E-3= 96%, E-4= 95%, E-5= 95%, E-6= 95%, E-7=95%, E-8=60%, E-9=50%F-2 =30%, F-3 =70%, F-4=80%, F-5=95%, F-6=90%, F-7=95%,F-9=50% G-2=95%, G-3 =95%, G-4=95%, G-5=95 %, G-6=95%.G-7=95%,G-8=60% G-9=50% |
05 | Door frame fitting work | 50% completed |
06 | Sanitary & plumbing line work | 10% completed |
07 | In side Plastering work | A-1 =90%, A-2= 95%, A-3= 95%, A-4 =90%, A-5= 90%, A-6= 90%, A-7= 90%, A-8=90%,B-1 =90%, B-2= 95%, B-3= 95%, B-4=95%, B-5=95%, B-6=95%, B-7=80%B-8=90%, C-1 =90%, C-2= 95%, C-3= 90%, C-4 =90 %, C-5 =90%, C-6 =95 %, C-7 =90%,C-8=90% I-2 (D2)=50% , D-3=90%, D-4= 90%, D-5= 80%, D-6=80%, D-7=30%, D-8=30%, E-2=80%, E-3=85%, E-4= 85%, E-5=80%, E-6=80%, E-7=80%, E-8=30%, F-2=40%, F-3=40%, F-4=40%, F-5=70%, F-6=80%, F-7=30%, F-8=40%, G-2=80%, G-3=70%, G-4=80%, G-5=80%, G-6=80%. G-7=70%. G-8=30%. |
08 | Electrical cable wiring work | 10% completed |
09 | Wall tiles work | 0% completed |
10 | Common sanitary & Plumbing line work | 0% completed |
11 | Outside plastering work | 10% completed |
12 | Floor tiles/Marble work | 0% completed |
13 | L.C.C work | 0% completed |
14 | Grill & Railing work | 0% completed |
15 | Inside paint & Polishing work | 0% completed |
16 | Switch -Socket fitting work | 0% completed |
17 | Outside paint work | 0% completed |
18 | Door shutter work | 0% completed |
19 | Aluminum work | 0% completed |
20 | Tiles Pointing work & Marble finishing work | 0% completed |
21 | Commode – Basin fitting work and C.P fittings work | 0% completed |
22 | Lift/Generator /Substation /Solar work | 0% completed |
23 | Boundary wall /Ground floor development work | 0% completed. |
24 | Roof top finishing work | 0% completed. |
25 | Roof top Gardening work G.F Garden work | 0% completed. |