Resonance

Adabor, Dhaka

Expected Completion Date

May 2026

Status Updated

October, 2024

SL. No Name of the work Progress details
01 Foundation work 100% completed.
02 Super Structure work 90 % completed.
03 Block Work A-1 =95%, A-2= 100%, A-3= 100%, A-4 =75%, A-5= 75%, A-6= 75%, A-7= 65%,  B-1=100%, B-2=100%,B-3 = 90%, B-4=75%, B-5=75%,  B-6=75%,  B-7=65%,   C-1=90%, C-2=100%, C-3 =95 %, C-4 =75 %, C-5 =75 %, C-6 =75 %, C-7 =60 %, I-2 (D2)=80% , D-3= 95%, D-4= 95%, D-5= 75%, D-6= 75%, E-2 = 95%, E-3= 95%, E-4= 90%, E-5= 75%, E-6= 75%,  F-2 =30%, F-3 =50%, F-4=70%, F-5=70%, F-6=60%, F-7=60%, G-2=95%, G-3 =90%, G-4=90%, G-5=70%, & G-6=70%.
04 Electrical conducting work A-1 =95%, A-2= 100%, A-3= 100%, A-4 =75%, A-5= 75%, A-6= 75%, A-7= 65%,  B-1=100%, B-2=100%,B-3 = 90%, B-4=75%, B-5=75%,  B-6=75%,  B-7=65%,   C-1=90%, C-2=100%, C-3 =95 %, C-4 =75 %, C-5 =75 %, C-6 =75 %, C-7 =60 %, I-2 (D2)=80% , D-3= 95%, D-4= 95%, D-5= 75%, D-6= 75%, E-2 = 95%, E-3= 95%, E-4= 90%, E-5= 75%, E-6= 75%,  F-2 =30%, F-3 =50%, F-4=70%, F-5=70%, F-6=60%, F-7=60%, G-2=95%, G-3 =90%, G-4=90%, G-5=70%, & G-6=70%.
05 Door frame fitting work 25% completed
06 Sanitary & plumbing line work 0% completed
07 In side Plastering work A-1 =90%, A-2= 90%, A-3= 90%, A-4 =20%, A-5= 20%, A-6= 20%, A-7= 20%, B-1 =90%, B-2= 90%, B-3= 90%, B-4=20%, B-5=20%,  B-6=20%,  B-7=20%, C-1 =90%, C-2= 90%, C-3= 80%, C-4 =20 %, C-5 =20 %, C-6 =20 %, C-7 =20 %, I-2 (D2)=20% , D-3=80%, %, D-4= 20%, D-5= 20%, D-6=20%, D-7=20%, D-8=20%, E-2=80%, E-3=80%, E-4= 20%, E-5=20%, E-6=20%, E-7=20%,  E-8=20%, F-2=20%,  F-3=20%, F-4=20%, F-5=20%, F-6=20%, F-7=20%, F-8=20%, G-2=80%, G-3=50%, G-4=20%, G-5=20%, G-6=20%. G-7=20%. G-8=20%.
08 Electrical cable wiring work 10% completed
09 Wall tiles work 0% completed
10 Common sanitary & Plumbing line work 0% completed
11 Outside plastering work 0% completed
12 Floor tiles/Marble work 0% completed
13 L.C.C work 0% completed
14 Grill & Railing work 0% completed
15 Inside paint & Polishing work 0% completed
16 Switch -Socket fitting work 0% completed
17 Outside paint work 0% completed
18 Door shutter work 0% completed
19 Aluminum work 0% completed
20 Tiles Pointing work & Marble finishing work 0% completed
21 Commode – Basin fitting work and C.P fittings work 0% completed
22 Lift/Generator /Substation /Solar work 0% completed
23 Boundary wall /Ground floor development work 0% completed.
24 Roof top finishing work 0% completed.
25 Roof top Gardening work G.F Garden work 0% completed.

 

16604