Resonance

Adabor, Dhaka

Expected Completion Date

May 2026

Status Updated

May, 2025

SL. No Name of the work Progress details
01 Foundation work 100% completed.
02 Super Structure work 97 % completed.
03 Block Work A-1 =95%, A-2= 100%, A-3= 100%, A-4 =95%, A-5= 95%, A-6= 95%, A-7= 95%,A-8=95%,A-9=90%  B-1=100%, B-2=100%,B-3 = 98%, B-4=95%, B-5=98%,  B-6=98%,  B-7=98%, B-8=98%B-9=90%  C-1=98%, C-2=100%, C-3 =98 %, C-4 =98 %, C-5 =98 %, C-6 =98 %, C-7 =98 %, C-8= 95%,C-9=90%I-2 (D2)=80% , D-3= 98%, D-4= 98%, D-5= 98%, D-6= 95%,D-7=90%,D-8=70%,D-9=70% E-2 = 98%, E-3=98%

E-4= 96%, E-5= 95%, E-6= 95%, E-7=95%, E-8=55%, E-9=50% F-2 =50%, F-3 =70%, F-4=80%, F-5=95%, F-6=95%, F-7=95%, F-8=50%,F-9=50% G-2=95%, G-3 =95%, G-4=95%, G-5=95%, G-6=95%.G-7=95%, G-8=70%,G-9=50%

04 Electrical conducting work A-1 =95%, A-2= 100%, A-3= 100%, A-4 =92%, A-5= 95%, A-6= 95%, A-7= 95%,A-8=95%  B-1=100%, B-2=100%,B-3 = 98%, B-4=95%, B-5=98%,  B-6=98%,  B-7=8%,B-8=98%B-9=98%   C-1=98%, C-2=100%, C-3 =98 %, C-4 =98 %, C-5 =98 %, C-6 =98 %, C-7 =98 %,C-8=95%,C-9=90% I-2 (D2)=80% , D-3= 98%, D-4= 98%, D-5= 98%, D-6= 95%,D-7=90%, D-8=70%,D-9=70%E-2 = 98%, E-3= 96%, E-4= 95%, E-5= 95%, E-6= 95%, E-7=95%, E-8=60%, E-9=50%F-2 =30%, F-3 =70%, F-4=80%, F-5=95%, F-6=90%, F-7=95%,F-9=50% G-2=95%, G-3 =95%, G-4=95%, G-5=95 %, G-6=95%.G-7=95%,G-8=60% G-9=50%
05 Door frame fitting work 50% completed
06 Sanitary & plumbing line work 10% completed
07 In side Plastering work A-1 =90%, A-2= 95%, A-3= 95%, A-4 =90%, A-5= 90%, A-6= 90%, A-7= 90%, A-8=90%,B-1 =90%, B-2= 95%, B-3= 95%, B-4=95%, B-5=95%,  B-6=95%,  B-7=80%B-8=90%, C-1 =90%, C-2= 95%, C-3= 90%, C-4 =90 %, C-5 =90%, C-6 =95 %, C-7 =90%,C-8=90% I-2 (D2)=50% , D-3=90%,  D-4= 90%, D-5= 80%, D-6=80%, D-7=30%, D-8=30%, E-2=80%, E-3=85%, E-4= 85%, E-5=80%, E-6=80%, E-7=80%,  E-8=30%, F-2=40%,  F-3=40%, F-4=40%, F-5=70%, F-6=80%, F-7=30%, F-8=40%, G-2=80%, G-3=70%, G-4=80%, G-5=80%, G-6=80%. G-7=70%. G-8=30%.
08 Electrical cable wiring work 10% completed
09 Wall tiles work 0% completed
10 Common sanitary & Plumbing line work 0% completed
11 Outside plastering work 10% completed
12 Floor tiles/Marble work 0% completed
13 L.C.C work 0% completed
14 Grill & Railing work 0% completed
15 Inside paint & Polishing work 0% completed
16 Switch -Socket fitting work 0% completed
17 Outside paint work 0% completed
18 Door shutter work 0% completed
19 Aluminum work 0% completed
20 Tiles Pointing work & Marble finishing work 0% completed
21 Commode – Basin fitting work and C.P fittings work 0% completed
22 Lift/Generator /Substation /Solar work 0% completed
23 Boundary wall /Ground floor development work 0% completed.
24 Roof top finishing work 0% completed.
25 Roof top Gardening work G.F Garden work 0% completed.

 