Resonance

Adabor, Dhaka

Expected Completion Date

May 2026

Status Updated

January, 2026

SL. No Name of the work Progress details
01 Foundation work 100% completed.
02 Super Structure work 100 % completed.
03 Block Work A-1 =100%, A-2= 100%, A-3= 100%, A-4 =100%, A-5= 100%, A-6= 100%, A-7= 100%,A-8=100%,A-9=100%  B-1=100%, B-2=100%,B-3 = 100%, B-4=100%, B-5=100%,  B-6=100%,  B-7=100%, B-8=100%,B-9=100%  C-1=100%, C-2=100%, C-3 =100%, C-4 =100%, C-5 =100%, C-6 =100 %, C-7 =100%, C-8= 100%,C-9=100%I-2 (D2)=100% , D-3= 100%, D-4= 100%, D-5= 100%, D-6= 100%,D-7=100%,D-8=100%,D-9=100% E-2 = 100%, E-3=100%

E-4= 100%, E100% F-2 =100%, F-3 =100%, F-4=100%, F-5=100%, F-6=100%, F-7=100%, F-8=100%,F-9=100% G-2=100%, G-3 =95%, G-4=95%, G-5=95%, G-6=95%.G-7=100%, G-8=95%,G-9=100%

04 Electrical conducting work A-1 =100%, A-2= 100%, A-3= 100%, A-4 =100%, A-5= 100%, A-6= 100%, A-7= 100%,A-8=100%,A-9=100%  B-1=100%, B-2=100%,B-3 = 100%, B-4=100%, B-5=100%,  B-6=100%,  B-7=100%, B-8=100%,B-9=100%  C-1=100%, C-2=100%, C-3 =100%, C-4 =100%, C-5 =100%, C-6 =100 %, C-7 =100%, C-8= 100%,C-9=100%I-2 (D2)=100% , D-3= 100%, D-4= 100%, D-5= 100%, D-6= 100%,D-7=100%,D-8=100%,D-9=100% E-2 = 100%, E-3=100%

E-4= 100%, E100% F-2 =100%, F-3 =100%, F-4=100%, F-5=100%, F-6=100%, F-7=100%, F-8=100%,F-9=100% G-2=100%, G-3 =95%, G-4=95%, G-5=95%, G-6=95%.G-7=100%, G-8=95%,G-9=100%

05 Door frame fitting work 95% completed
06 Sanitary & plumbing line work 75% completed
07 In side Plastering work A-1 =100%, A-2= 100%, A-3= 100%, A-4 =100%, A-5= 100%, A-6= 100%, A-7= 100%,A-8=100%,A-9=100%  B-1=100%, B-2=100%,B-3 = 100%, B-4=100%, B-5=100%,  B-6=100%,  B-7=100%, B-8=100%,B-9=60%  C-1=100%, C-2=100%, C-3 =100%, C-4 =100%, C-5 =100%, C-6 =100 %, C-7 =100%, C-8= 100%,C-9=70%I-2 (D2)=100% , D-3= 100%, D-4= 100%, D-5= 100%, D-6= 100%,D-7=100%,D-8=100%,D-9=40% E-2 = 100%, E-3=100%

E-4= 100%, E100% F-2 =100%, F-3 =100%, F-4=100%, F-5=100%, F-6=100%, F-7=100%, F-8=100%,F-9=60% G-2=100%, G-3 =95%, G-4=95%, G-5=95%, G-6=95%.G-7=100%, G-8=95%,G-9=60%

08 Electrical cable wiring work 75% completed
09 Wall tiles work 85% completed
10 Common sanitary & Plumbing line work 0% completed
11 Outside plastering work 95% completed
12 Floor tiles/Marble work 70% completed
13 L.C.C work 100% completed
14 Grill & Railing work 60% completed
15 Inside paint & Polishing work 0% completed
16 Switch -Socket fitting work 0% completed
17 Outside paint work 0% completed
18 Door shutter work 0% completed
19 Aluminum work 0% completed
20 Tiles Pointing work & Marble finishing work 0% completed
21 Commode – Basin fitting work and C.P fittings work 0% completed
22 Lift/Generator /Substation /Solar work 0% completed
23 Boundary wall /Ground floor development work 0% completed.
24 Roof top finishing work 70% completed.
25 Roof top Gardening work G.F Garden work 0% completed.