Expected Completion Date
May 2026
Status Updated
January, 2026
| SL. No | Name of the work | Progress details |
| 01 | Foundation work | 100% completed. |
| 02 | Super Structure work | 100 % completed. |
| 03 | Block Work | A-1 =100%, A-2= 100%, A-3= 100%, A-4 =100%, A-5= 100%, A-6= 100%, A-7= 100%,A-8=100%,A-9=100% B-1=100%, B-2=100%,B-3 = 100%, B-4=100%, B-5=100%, B-6=100%, B-7=100%, B-8=100%,B-9=100% C-1=100%, C-2=100%, C-3 =100%, C-4 =100%, C-5 =100%, C-6 =100 %, C-7 =100%, C-8= 100%,C-9=100%I-2 (D2)=100% , D-3= 100%, D-4= 100%, D-5= 100%, D-6= 100%,D-7=100%,D-8=100%,D-9=100% E-2 = 100%, E-3=100%
E-4= 100%, E100% F-2 =100%, F-3 =100%, F-4=100%, F-5=100%, F-6=100%, F-7=100%, F-8=100%,F-9=100% G-2=100%, G-3 =95%, G-4=95%, G-5=95%, G-6=95%.G-7=100%, G-8=95%,G-9=100% |
| 04 | Electrical conducting work | A-1 =100%, A-2= 100%, A-3= 100%, A-4 =100%, A-5= 100%, A-6= 100%, A-7= 100%,A-8=100%,A-9=100% B-1=100%, B-2=100%,B-3 = 100%, B-4=100%, B-5=100%, B-6=100%, B-7=100%, B-8=100%,B-9=100% C-1=100%, C-2=100%, C-3 =100%, C-4 =100%, C-5 =100%, C-6 =100 %, C-7 =100%, C-8= 100%,C-9=100%I-2 (D2)=100% , D-3= 100%, D-4= 100%, D-5= 100%, D-6= 100%,D-7=100%,D-8=100%,D-9=100% E-2 = 100%, E-3=100%
E-4= 100%, E100% F-2 =100%, F-3 =100%, F-4=100%, F-5=100%, F-6=100%, F-7=100%, F-8=100%,F-9=100% G-2=100%, G-3 =95%, G-4=95%, G-5=95%, G-6=95%.G-7=100%, G-8=95%,G-9=100% |
| 05 | Door frame fitting work | 95% completed |
| 06 | Sanitary & plumbing line work | 75% completed |
| 07 | In side Plastering work | A-1 =100%, A-2= 100%, A-3= 100%, A-4 =100%, A-5= 100%, A-6= 100%, A-7= 100%,A-8=100%,A-9=100% B-1=100%, B-2=100%,B-3 = 100%, B-4=100%, B-5=100%, B-6=100%, B-7=100%, B-8=100%,B-9=60% C-1=100%, C-2=100%, C-3 =100%, C-4 =100%, C-5 =100%, C-6 =100 %, C-7 =100%, C-8= 100%,C-9=70%I-2 (D2)=100% , D-3= 100%, D-4= 100%, D-5= 100%, D-6= 100%,D-7=100%,D-8=100%,D-9=40% E-2 = 100%, E-3=100%
E-4= 100%, E100% F-2 =100%, F-3 =100%, F-4=100%, F-5=100%, F-6=100%, F-7=100%, F-8=100%,F-9=60% G-2=100%, G-3 =95%, G-4=95%, G-5=95%, G-6=95%.G-7=100%, G-8=95%,G-9=60% |
| 08 | Electrical cable wiring work | 75% completed |
| 09 | Wall tiles work | 85% completed |
| 10 | Common sanitary & Plumbing line work | 0% completed |
| 11 | Outside plastering work | 95% completed |
| 12 | Floor tiles/Marble work | 70% completed |
| 13 | L.C.C work | 100% completed |
| 14 | Grill & Railing work | 60% completed |
| 15 | Inside paint & Polishing work | 0% completed |
| 16 | Switch -Socket fitting work | 0% completed |
| 17 | Outside paint work | 0% completed |
| 18 | Door shutter work | 0% completed |
| 19 | Aluminum work | 0% completed |
| 20 | Tiles Pointing work & Marble finishing work | 0% completed |
| 21 | Commode – Basin fitting work and C.P fittings work | 0% completed |
| 22 | Lift/Generator /Substation /Solar work | 0% completed |
| 23 | Boundary wall /Ground floor development work | 0% completed. |
| 24 | Roof top finishing work | 70% completed. |
| 25 | Roof top Gardening work G.F Garden work | 0% completed. |