Resonance

Adabor, Dhaka

Completion Date

August 2025

Status Updated

March, 2024

SL. No Name of the work Progress details
01 Foundation work 100% completed.
02 Super Structure work 80 % completed.
03 Block Work A-1 =95%, A-2= 100%, A-3= 100%, B-1=100%, B-2=100%,B-3 = 90% C-1=90%, C-2=100%, C-3 =95 %, E-2 = 90%, G-2=90% , I-2 (D2)=80% , D-3= 90%, E-3= 90%, F-3 =40%, G-3 =80%, D-4=80%, E-4= 70%, F-4=70% ,G-4=60%, D-5=50%, E-5= 70%, F-5=70%  & G-5=70%,
04 Electrical conducting work A-1 =50%, A-2= 20%, B-1=50%, B-2=20%, C-1=50%, C-2=30%, E-2 = 50%, G-2=50% , I-2 =10%
05 Door frame fitting work 20% completed
06 Sanitary & plumbing line work 0% completed
07 In side Plastering work A-1 =90%, A-2= 90%, A-3= 90%,
08 Electrical cable wiring work 0% completed
09 Wall tiles work 0% completed
10 Common sanitary & Plumbing line work 0% completed
11 Outside plastering work 0% completed
12 Floor tiles/Marble work 0% completed
13 L.C.C work 0% completed
14 Grill & Railing work 0% completed
15 Inside paint & Polishing work 0% completed
16 Switch -Socket fitting work 0% completed
17 Outside paint work 0% completed
18 Door shutter work 0% completed
19 Aluminum work 0% completed
20 Tiles Pointing work & Marble finishing work 0% completed
21 Commode – Basin fitting work and C.P fittings work 0% completed
22 Lift/Generator /Substation /Solar work 0% completed
23 Boundary wall /Ground floor development work 0% completed.
24 Roof top finishing work 0% completed.
25 Roof top Gardening work G.F Garden work 0% completed.

16604