Completion Date
May 2026
Status Updated
September, 2024
SL. No | Name of the work | Progress details |
01 | Foundation work | 100% completed. |
02 | Super Structure work | 90 % completed. |
03 | Block Work | A-1 =95%, A-2= 100%, A-3= 100%, B-1=100%, B-2=100%,B-3 = 90% C-1=90%, C-2=100%, C-3 =95 %, E-2 = 90%, G-2=90% , I-2 (D2)=80% , D-3= 90%, E-3= 90%, F-3 =50%, G-3 =90%, D-4=80%, E-4= 90%, F-4=70% ,G-4=70%, D-5=50%, E-5= 70%, F-5=70% & G-5=70%, |
04 | Electrical conducting work | A-1 =50%, A-2= 20%, B-1=50%, B-2=20%, C-1=70%, C-2=70%, E-2 = 70%, G-2=70% , I-2 =40% |
05 | Door frame fitting work | 20% completed |
06 | Sanitary & plumbing line work | 0% completed |
07 | In side Plastering work | A-1 =90%, A-2= 90%, A-3= 90%, |
08 | Electrical cable wiring work | 0% completed |
09 | Wall tiles work | 0% completed |
10 | Common sanitary & Plumbing line work | 0% completed |
11 | Outside plastering work | 0% completed |
12 | Floor tiles/Marble work | 0% completed |
13 | L.C.C work | 0% completed |
14 | Grill & Railing work | 0% completed |
15 | Inside paint & Polishing work | 0% completed |
16 | Switch -Socket fitting work | 0% completed |
17 | Outside paint work | 0% completed |
18 | Door shutter work | 0% completed |
19 | Aluminum work | 0% completed |
20 | Tiles Pointing work & Marble finishing work | 0% completed |
21 | Commode – Basin fitting work and C.P fittings work | 0% completed |
22 | Lift/Generator /Substation /Solar work | 0% completed |
23 | Boundary wall /Ground floor development work | 0% completed. |
24 | Roof top finishing work | 0% completed. |
25 | Roof top Gardening work G.F Garden work | 0% completed. |