Royal Pines

Mirpur, Dhaka

Expected Completion Date

March 2025

Status Updated

November, 2024

SL. No Name of the work Progress details
  Foundation work 100% Completed
  Super Structure work 100% completed
  Block work All flat 100% Complete, Common area 95% Complete.
  Electrical conduit work All flat 100% Complete, Common area 95% Complete
  Door frame fitting work All flat 100% Complete, Common area 95% Complete
  Sanitary & plumbing line work Internal Sanitary & Plumbing work all flat 100% Complete, Vertical line work 95 %Complete
  In side Plastering work All flat 100% Complete, Common area 90% Complete
  Electrical cable wiring work All flat 100% Complete, Common area 85% Complete
  Wall tiles work All flat 99% Completed
  Common sanitary & Plumbing line work 60% completed
  Outside plastering work 99% completed
  Floor tiles/Marble work 100% Completed
  L.C.C work 100% Completed
  Grill & Railing work 92% Completed
  Inside paint & Polishing work 78% Completed
  Switch -Socket fitting work 70% Completed
  Outside paint work 60% Completed
  Door shutter work 75% Completed
  Aluminum/Glazing work 80% Completed
  Tiles Pointing work & Marble finishing work 65% Completed
  Commode – Basin fitting work and C.P fittings work 40% Completed
  Lift/Generator /Substation /Solar work 55% Completed
  Boundary wall /Ground floor development work 50% Completed
  Roof top finishing work 50% Completed
  Roof top Gardening work 12% Completed

16604