Expected Completion Date
March 2025
Status Updated
January, 2025
SL. No | Name of the work | Progress details |
Foundation work | 100% Completed | |
Super Structure work | 100% completed | |
Block work | All flat 100% Complete, Common area 97% Complete. | |
Electrical conduit work | All flat 100% Complete, Common area 95% Complete | |
Door frame fitting work | All flat 100% Complete, Common area 98% Complete | |
Sanitary & plumbing line work | Internal Sanitary & Plumbing work all flat 100% Complete | |
In side Plastering work | All flat 100% Complete, Common area 95% Complete | |
Electrical cable wiring work | All flat 100% Complete, Common area 92% Complete | |
Wall tiles work | All flat 99% Completed, Common area 94% Complete | |
Common sanitary & Plumbing line work | 75% completed | |
Outside plastering work | 99% completed | |
Floor tiles/Marble work | 100% Completed | |
L.C.C work | 100% Completed | |
Grill & Railing work | 95% Completed | |
Inside paint & Polishing work | 84% Completed | |
Switch -Socket fitting work | 80% Completed | |
Outside paint work | 70% Completed | |
Door shutter work | 85% Completed | |
Aluminum/Glazing work | 95% Completed | |
Tiles Pointing work & Marble finishing work | 75% Completed | |
Commode – Basin fitting work and C.P fittings work | 65% Completed | |
Lift/Generator /Substation /Solar work | 75% Completed | |
Boundary wall /Ground floor development work | 65% Completed | |
Roof top finishing work | 60% Completed | |
Roof top Gardening work | 20% Completed |