Completion Date
October 2024
Status Updated
February, 2024
SL. No | Name of the work | Progress details |
Foundation work | 100% Completed | |
Super Structure work | 100% completed | |
Block work | All flat 100% Complete, Common area 38% Complete. | |
Electrical conduit work | All flat 100% Complete, Common area 27% Complete | |
Door frame fitting work | All flat 100% Complete ,Common area 50% Complete | |
Sanitary & plumbing line work | Internal Sanitary & Plumbing work all flat 100% Complete, Vertical line work 58 %Complete | |
In side Plastering work | All flat 100% Complete ,Common area 48% Complete | |
Electrical cable wiring work | All flat 100% Complete ,Common area 10% Complete | |
Wall tiles work | All flat 88% Completed | |
Common sanitary & Plumbing line work | N/A | |
Outside plastering work | 70% completed | |
Floor tiles/Marble work | Total Apartments 76 nos, Floor tiles completed 69 nos. | |
L.C.C work | 5% Completed | |
Grill & Railing work | 68% Completed | |
Inside paint & Polishing work | N/A | |
Switch -Socket fitting work | N/A | |
Outside paint work | N/A | |
Door shutter work | N/A | |
Aluminum/Glazing work | N/A | |
Tiles Pointing work & Marble finishing work | N/A | |
Commode – Basin fitting work and C.P fittings work | N/A | |
Lift/Generator /Substation /Solar work | 5% Completed | |
Boundary wall /Ground floor development work | 12% Completed | |
Roof top finishing work | N/A | |
Roof top Gardening work | 2% Completed |