Royal Pines

Mirpur, Dhaka
Expected Completion Date March 2025
Status Updated March, 2025
Back to all projects
Royal Pines

Construction progress details

The progress table comes directly from the WordPress post content.

SL. No Name of the work Progress details
  Foundation work 100% Completed
  Super Structure work 100% completed
  Block work All flat 100% Complete, Common area 100% Complete.
  Electrical conduit work All flat 100% Complete, Common area 100% Complete
  Door frame fitting work All flat 100% Complete, Common area 100% Complete
  Sanitary & plumbing line work Internal Sanitary & Plumbing work all flat 100% Complete
  In side Plastering work All flat 100% Complete, Common area 99% Complete
  Electrical cable wiring work All flat 100% Complete, Common area 99% Complete
  Wall tiles work All flat 100% Completed, Common area 100% Complete
  Common sanitary & Plumbing line work 98% completed
  Outside plastering work 100% completed
  Floor tiles/Marble work 100% Completed
  L.C.C work 100% Completed
  Grill & Railing work 99% Completed
  Inside paint & Polishing work 99% Completed
  Switch -Socket fitting work 99% Completed
  Outside paint work 90% Completed
  Door shutter work 100% Completed
  Aluminum/Glazing work 99% Completed
  Tiles Pointing work & Marble finishing work 94% Completed
  Commode – Basin fitting work and C.P fittings work 95% Completed
  Lift/Generator /Substation /Solar work 90% Completed
  Boundary wall /Ground floor development work 95% Completed
  Roof top finishing work 98% Completed
  Roof top Gardening work 40% Completed