Royal Pines

Mirpur, Dhaka

Completion Date

March 2025

Status Updated

September, 2024

SL. No Name of the work Progress details
  Foundation work 100% Completed
  Super Structure work 100% completed
  Block work All flat 100% Complete, Common area 70% Complete.
  Electrical conduit work All flat 100% Complete, Common area 60% Complete
  Door frame fitting work All flat 100% Complete, Common area 75% Complete
  Sanitary & plumbing line work Internal Sanitary & Plumbing work all flat 100% Complete, Vertical line work 80 %Complete
  In side Plastering work All flat 100% Complete, Common area 75% Complete
  Electrical cable wiring work All flat 100% Complete, Common area 50% Complete
  Wall tiles work All flat 99% Completed
  Common sanitary & Plumbing line work 20% completed
  Outside plastering work 96% completed
  Floor tiles/Marble work 100% Completed
  L.C.C work 100% Completed
  Grill & Railing work 88% Completed
  Inside paint & Polishing work 65% Completed
  Switch -Socket fitting work 20%
  Outside paint work 30% Completed
  Door shutter work 30% Completed
  Aluminum/Glazing work 30% Completed
  Tiles Pointing work & Marble finishing work 5%
  Commode – Basin fitting work and C.P fittings work N/A
  Lift/Generator /Substation /Solar work 15% Completed
  Boundary wall /Ground floor development work 30% Completed
  Roof top finishing work 20% Completed
  Roof top Gardening work 5% Completed