Royal Pines

Mirpur, Dhaka

Completion Date

October 2024

Status Updated

February, 2024

SL. No Name of the work Progress details
  Foundation work 100% Completed
  Super Structure work 100% completed
  Block work All flat 100% Complete, Common area 38% Complete.
  Electrical  conduit work All flat 100% Complete, Common area 27% Complete
  Door frame fitting work All flat 100% Complete ,Common area 50% Complete
  Sanitary & plumbing line  work Internal Sanitary & Plumbing work all flat 100% Complete, Vertical line work 58 %Complete
  In side Plastering work All flat 100% Complete ,Common area 48% Complete
  Electrical cable wiring work All flat 100% Complete ,Common area 10% Complete
  Wall tiles  work All flat 88% Completed
  Common sanitary & Plumbing line work N/A
  Outside plastering work 70% completed
  Floor tiles/Marble work Total Apartments 76 nos, Floor tiles completed 69 nos.
  L.C.C work 5% Completed
  Grill & Railing work 68% Completed
  Inside paint & Polishing work N/A
  Switch -Socket fitting work N/A
  Outside paint work N/A
  Door shutter work N/A
  Aluminum/Glazing work N/A
  Tiles Pointing work & Marble finishing work N/A
  Commode – Basin fitting work and C.P fittings work N/A
  Lift/Generator /Substation /Solar work 5% Completed
  Boundary wall /Ground floor development work 12% Completed
  Roof top finishing work N/A
  Roof top Gardening work 2% Completed