Sandringham

Bashundhara R/A, Dhaka

Expected Completion Date

February 2025

Status Updated

November, 2024

SL. No Name of the work Progress details
01 Foundation work 100%
02 Super Structure work 100%
03 Block Work A-1 = 100%, A-2= 100%, A-3= 100%, A-4= 100%, A-5=100%, A-6= 100%, A-7= 90% A-8= 100%,,
04 Electrical conducting work A-1 = 100% , A-2= 100%, A-3= 100%, A-4= 100%, A-5= 100%, A-6= 100%, A-7= 100%, A-8= 100%,
05 Door frame fitting work A-1 =100% , A-2= 100%, A-3= 100%, A-4= 100% ,A-5= 100% ,A-6= 100% ,A-7= 100% A-8= 100%
06 Sanitary & plumbing line work A-1 =60% , A-2= 70%, A-3= 80%, A-4= 80% , A-5= 80%, A-6= 80%, A-7= 90%, A-8= 90%
07 In side Plastering work A-1 =90% , A-2= 100%, A-3= 100%, A-4= 100%, A-5= 100% A-6= 100% A-7= 100%, A-8= 100%
08 Electrical cable wiring work Over all 90%
09 Wall tiles work Over all100%
10 Common sanitary & Plumbing line work N/A
11 Outside plastering work 100%
12 Floor tiles/Marble work A-1 =90% , A-2= 100%, A-3= 100%, A-4= 100%, A-5= 100% A-6= 100% A-7= 100%, A-8= 100%
13 L.C.C work 100%
14 Grill & Railing work Over all 80%
15 Inside paint & Polishing work 30%
16 Switch -Socket fitting work N/A
17 Outside paint work N/A
18 Door shutter work N/A
19 Aluminum work N/A
20 Tiles Pointing work & Marble finishing work N/A
21 Commode – Basin fitting work and C.P fittings work N/A
22 Lift/Generator /Substation /Solar work 20%
23 Boundary wall /Ground floor development work 50%
24 Roof top finishing work 80%
25 Roof top Gardening work G.F Garden work N/A

 