Expected Completion Date
October 2024
Status Updated
October, 2024
SL NO | Name of Work | Progress details |
1 | Foundation work | Completed |
2 | Super Structure Work | Completed |
3 | Brick work/ Block work | Tower-1, 2, 3, &4 – Block work 100% complected |
4 | Electrical conduiting work | Tower-1, 2, 3, &4 – Ele work 100% complected |
5 | Door frame fitting work | Door fame fitting 100% completed. |
6 | Sanitary & Plumbing line work | Tower 1, 2, 3 &4 bath room ppr work 100% completed |
7 | In side plastering work | Tower-1, 2, 3 &4 – In side Plaster work 100% complected |
8 | Electrical cable wiring work | Tower-1, 2,3 &4 – 13th floor cable Wiring complected |
9 | wall tiles work | Bath Room wall 100% completed |
10 | Common Sanitary & Plumbing line work | Tower – 1,2,3&4 sanitary & plumbing line 90% |
11 | Outside plastering work | Tower-3, outside plaster 100% & tower -4, Outside plaster 100 % &tower-2 Outside plaster 100% tower -1 Outside plaster 100% |
12 | Floor tiles/ Marble work | Main Floor Tiles work 100% |
13 | L.C.C work | Tower-4 (100%) Tower-1 (100%) Tower-2 (100%) |
14 | Grill & Railing work | Tower – 1,2,3&4 Grill Work 100 % |
15 | In side paint & Polishing work | Tower – 1, 2 ,3 & 4 In side paint 70% |
16 | Switch – Socket fitting work | 90% |
17 | Outside Paint work | Tower – 1,2,3&4Out side 60% % |
18 | Door Shutter work | 100% |
19 | Aluminum work | 95% |
20 | Tiles pointing work &Marble finishing work | 80% |
21 | Commode – Basin fitting work & C. P fitting work | 50% |
22 | Lift / Generator/Substation/ Solar work | Tower – 2,2,3&4Lift Generator 50% |
23 | Boundary wall/ Ground Floor development work | Boundary wall 100% |
24 | Roof top finishing work | Tower – 1,2,3&4Roof top 85 % |
25 | Roof top Gardening work G.F. Garden work | 70% |
16604