Expected Completion Date
February 2025
Status Updated
May, 2025
| SL NO | Name of Work | Progress details |
| 1 | Foundation work | Completed |
| 2 | Super Structure Work | Completed |
| 3 | Brick work/ Block work | Tower-1, 2, 3, &4 – Block work 100% complected |
| 4 | Electrical conduiting work | Tower-1, 2, 3, &4 – Ele work 100% complected |
| 5 | Door frame fitting work | Door fame fitting 100% completed. |
| 6 | Sanitary & Plumbing line work | Tower 1, 2, 3 &4 bath room ppr work 100% completed |
| 7 | In side plastering work | Tower-1, 2, 3 &4 – In side Plaster work 100% complected |
| 8 | Electrical cable wiring work | Tower-1, 2,3 &4 – 13th floor cable Wiring 100% complected |
| 9 | wall tiles work | Bath Room wall 100% completed |
| 10 | Common Sanitary & Plumbing line work | Tower – 1,2,3&4 sanitary & plumbing line 100% |
| 11 | Outside plastering work | Tower-3, outside plaster 100% & tower -4, Outside plaster 100 % & tower-2 Outside plaster 100% tower -1 Outside plaster 100% |
| 12 | Floor tiles/ Marble work | Main Floor Tiles work 100% |
| 13 | L.C.C work | Tower-4 (100%) Tower-1 (100%) Tower-2 (100%) |
| 14 | Grill & Railing work | Tower – 1,2,3&4 Grill Work 100 % |
| 15 | In side paint & Polishing work | Tower – 1, 2 ,3 & 4 In side paint 100% |
| 16 | Switch – Socket fitting work | 100% |
| 17 | Outside Paint work | Tower – 1,2,3 & 4 Outside 100% completed |
| 18 | Door Shutter work | 100% |
| 19 | Aluminum work | 100% |
| 20 | Tiles pointing work &Marble finishing work | 100% |
| 21 | Commode – Basin fitting work & C. P fitting work | 100% |
| 22 | Lift / Generator/Substation/ Solar work | Tower – 1,2,3&4 Lift installation completed. Generator installation completed. |
| 23 | Boundary wall/ Ground Floor development work | Boundary wall 100% |
| 24 | Roof top finishing work | Tower – 1,2,3 & 4 Roof top 100 % completed |
| 25 | Roof top Gardening work G.F. Garden work | 100% completed |